Project Planning/Scheduling Mid-Term Practice
Crea una cuenta gratis para terminar este test
Guarda tu progreso y consulta tu resultado final.
¿Ya tienes cuenta? Inicia sesión
Preguntas del test (50)
1what is the difference between a task and an activity
- Anothing, they are the same thing.
- Ba task has a duration of less than 5 days an activity has a duration of 5 days or more
2what the most important resource in LEAN construction?
- AWaste of Talent
- BTransportation
- CInventory
- DWaiting
3What does "Transportation" waste in TIMWOOD+U primarily refer to?
- AUnnecessary production steps
- BExcessive movement of materials leading to potential damage
- CWaiting time for materials to arrive
- DMistakes in construction
4Why is excess "Inventory" considered a form of waste?
- AIt takes up space and can result in damaged materials and inefficient capital allocation
- BIt promotes efficient allocation of capital
- CIt leads to unnecessary movement of materials
- DIt minimizes waiting time for materials
5What does waste in "Motion" refer to in the context of TIMWOOD+U?
- AUnnecessary movements of materials that don't add value
- BProduction of unneeded materials
- CWaiting for material delivery
- DErrors in construction
6Which form of waste is typically associated with subcontractors (subs)?
- AOver-Processing
- BOver-Production
- CDefects
- DInventory
7What is the consequence of "Wasted Human Potential" in lean construction?
- AEfficient work on the jobsite
- BWorkers not operating effectively on the jobsite
- CReduction in the unnecessary steps in production
- DElimination of waiting time for materials
8Mapping the value chain in Lean Construction refers to the process of making a visual representation of every step from the beginning to the end of a construction project.
- AVerdadero
- BFalso
9In the “Create Flow” principle, it's advisable to move large batches through the construction process to increase efficiency.
- AVerdadero
- BFalso
10The “Pull” work principle of Lean Construction encourages pushing activities through a project to ensure timely completion.
- AVerdadero
- BFalso
11What does the “Define Value” principle of Lean Construction emphasize?
- AMinimizing movement in the construction process
- BDefining customer value for the production system in question
- CPulling activities through a project
- DAnalyzing results and improving where needed
12The “Measure & Perfect” principle of Lean Construction involves which of the following practices?
- AMapping the entire value chain visually
- BAsking 'why' five times to understand the root cause of a problem
- CPushing activities through a project
- DBalancing crew sizes only
13What is the primary purpose of a "Notice to Proceed" in construction project management?
- ATo notify the owner of project delays
- BTo officially start the project based on the owner's authorization
- CTo request additional funding for the project
- DTo confirm the project's substantial completion
14In a "Fast-Track" construction project, what is unique about the relationship between construction and design?
- ADesign is completed before construction begins.
- BDesign continues while construction activities are in progress.
- CDesign is independent of construction activities.
- DDesign occurs after construction is finished.
15What does the term "Substantial Completion" refer to in construction projects?
- AThe completion of design documents
- BThe point in construction when all work is finished
- CThe stage of construction when the project is ready for use
- DThe project initiation phase
16What are "Liquidated Damages" in a construction contract?
- ACosts incurred by the contractor for project delays
- BMonetary charges due to completing a project ahead of schedule
- CMonetary charges due to completing a project after the contract deadline
- DExtra payments made to contractors for high-quality work
17In project scheduling, what is the purpose of "Lag"?
- AIt represents the critical path of the project.
- BIt is the difference between early start and late start times.
- CIt allows tasks to overlap by delaying one task after another.
- DIt indicates the earliest possible project completion date.
18What is "Slack" or "Float" in project scheduling?
- AIt's the delay applied to critical tasks.
- BIt's the total duration of a project.
- CIt's the flexibility to delay non-critical tasks without affecting the project's completion date.
- DIt's the duration of the critical path.
19What is the purpose of a "Constraint" in project scheduling?
- ATo allow tasks to float freely within the schedule
- BTo represent a fixed date that must be adhered to
- CTo define the project's budget
- DTo identify critical tasks in the project
20In project scheduling, when does a "Forward Pass" typically occur?
- AAt the beginning of the project schedule, from start to finish
- BAt the end of the project schedule, from finish to start
- CIt doesn't occur in project scheduling.
- DWhenever a project experiences delays
21What is the main purpose of a "Backward Pass" in project scheduling?
- ATo identify tasks that are ahead of schedule
- BTo assess project risks and opportunities
- CTo ensure that tasks are progressing in chronological order
- DTo identify issues with the project's critical path
22Which of the following is NOT a typical constraint that affects construction scheduling?
- ABudget
- BProject scope
- CHuman resources
- DWeather conditions
23Which equation is used to convert calendar days to working days in construction scheduling?
- ACalendar Days / 1.4 = Working Days
- BWorking Days / 1.4 = Calendar Days
- CWorking Days x 1.4 = Calendar Days
- DCalendar Days x 1.4 = Working Days
24What does the equation "Quantity of work / Production rate = Work Hours" represent in construction scheduling?
- AThe calculation of liquidated damages.
- BThe relationship between constraints and activities.
- CThe calculation of activity duration.
- DThe determination of stakeholders.
25 Who are some of the stakeholders in the planning phase of a construction project?
- ABuilders, Inspectors, and Suppliers.
- BDesign Team, Consultants, and Authorities.
- CContractors, Subcontractors, and Owners.
- DAll of the above.
26What are some societal conditions that can lead to changes in construction projects?
- AChanges in project management software.
- BChanges in building materials.
- CChanges in environmental regulations.
- DChanges in project financing.
27Which of the following is NOT considered a "High Risk Activity" in construction scheduling?
- AOccupied Spaces.
- BLong lead items.
- CShutdowns.
- DStandardized handoff processes.
28 What does the term “Constraints” refer to in construction planning?
- ARecommendations for start or finish dates
- BA fixed date applied to an activity's start or finish
- CFlexible date range for starting activities
- DConstraints are irrelevant to scheduling
29Which stakeholder typically publishes the bid during the Proposal phase?
- AContractor
- BDesign Team
- COwner
- DMajor Trade Partner
30What does the abbreviation “FS” stand for in construction Logic Relationships?
- AFinish-Start
- BStart-Finish
- CStart-Start
- DFinish-Finish
31Which of the 7+1 Forms of Waste involves unnecessary movement of materials?
- AOver-Processing
- BInventory
- CMotion
- DTransportation
32What is the primary focus of “Pull Planning” in Lean Construction?
- APushing activities to start simultaneously
- BCreating flow and preventing rework
- CIncreasing workforce for faster completion
- DFocusing solely on high-risk activities
33What does the equation “Calendar Days / 1.4 = Working Days” help to determine?
- AProject cost
- BWorking hours in a day
- CWorking days from calendar days
- DCalendar days from working days
34Fact finding is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
35green light thinking is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
36visualization is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
37brainstorming is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
38red light thinking is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
39reasoning is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
40gain consensus is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
41decision matrixes is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
42plan implementation is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
43control stress is for which critical thinking category?
- Aproblem identification
- Bcreative thinking
- Clogical analysis
- Ddecision making
- Ecoordination
44what is the order of critical thinking by Dale Carnegie?
- AProblem identification, creative thinking, logical analysis, decision making, coordination
- Bcreative thinking, Problem identification, logical analysis, decision making, coordination
- CProblem identification, logical analysis, logical analysis, decision making, coordination
45Whats the acronym for Critical Thinking?
- APict Lad MC
- BLad PC Mit
- CMC Pict Lad
- Dwhat the freaking heck is this?
46who are the stakeholders in scheduling?
- ABuilders
- BOwners Rep
- CDesign Team
- DSubcontractors
- EAHJ
- FProviders (Electrical, Gas, Cable)
47Why is phasing necessary in large construction projects?
- ATo increase the overall cost of the project
- BTo subdivide a large project and manage design time effectively
- CTo ensure that all tasks are completed simultaneously
- DPhasing has no particular purpose in large projects
48What is one of the benefits associated with Phased Funding in construction projects?
- AIt delays the delivery of critical plans and specifications
- BIt allows for financing to be allocated to different project phases as needed
- CIt requires all funds to be available upfront
- DPhased Funding limits the scope of the project
49 Which of the following is an example of a traditional pre-fabrication trade mentioned in the provided information?
- APlumbing
- BPainting
- CStructural Steel
- DCarpentry
50Given a total quantity of work of 400 units and a production rate of 20 units per hour, if the productivity factor is increased by 20%, how long will the activity duration be with 10 work hours per day?
- A3
- B4
- C2
- D1
Información
- Descripción
- Management Construction Test sobre Project Planning/Scheduling Mid-Term Practice, creado por Tyler Warford el 03/10/2023.
- Autor
- Tyler Warford
- Idioma
- English
- Visitas
- 45
- Etiquetas
- Valoración
- 5,0 de 5 · 1 valoración Valora este test