LO1 REVISION

Mohammed BUTT IT GCSE English 10 cards

Cards in this deck (10)

  1. 1Name the 4 stages of the project life cycle?initiation, planning, execution and evaluation
  2. 2Define iterationHow the phases of the project life cycle link together
  3. 3What are the constraints?time,budget,hardware/software and security
  4. 4name 2 advantages of following the project life cycle?it provides a structured approach and the tasks are clearly defined
  5. 5what are the inputs of the initiation phase?user requirements and user constraints
  6. 6What are the outputs of the initiation phase?Feasibility report
    Legislative implications
    phase review
  7. 7what are the inputs of the planning phase?Feasibility report
    Legislative implications
  8. 8what are the outputs of the planning phase?Project plan
    Test Plan
    Constraints list
    Phase review
  9. 9what are the inputs and outputs of the execution phase?inputs: Project plan
    Test Plan
    Constraints list
    outputs: Deliverable product
    Test results
    Phase review
  10. 10—

Information

Description
GCSE IT Flashcards on LO1 REVISION, created by Mohammed BUTT on 15/09/2021.
Created by
Mohammed BUTT
Views
0
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?