Flashcards
Chapter 2: Project Management
Cards in this deck (55)
- 1Project ManagementA process to manage, coordinate, and monitor all personnel and resources essential for completing the project on time and within budget
- 2What's a primary responsibility for the owners of construction companies?Recognize the strengths and abilities of their management team and that they realistically review their company's capabiliteis
- 3Project Management Balancing ActOwner's responsibility to understand the whole picture and balance current work. This balancing act requires skill in planning, scheduling, and close supervision of the work
- 4For larger companies, project manager duties include...-Project budget
-Production schedule
-Submit pay reports
-Handle change orders
-Get shop drawings - 5For larger companies, project superintendent duties include...-Responsible for on-site activities (including quality control)
-Supervising workers
-Coordinate work with subs and utility companies
-Oversee materials distribution and storage
-Initiate notices like claims for extra time or work - 6Project PlanningProcess of analyzing tasks individually and as a whole, determining how they will be accomplished and the sequence which they must be performed
- 7Things that need to be done during the project planning stage...-Inspect site
-Review the overall picture and contract requirements
-Plan sequence of tasks (physical construction and other items like permits and inspections)
-Determine duration of tasks
-Calculate personnel requirements
-Arrange for and distribute delivery of materials and equipment
-Make sure income from payments is received in time to pay expenses - 8Schedule changes need to be noted...On every document that is related to the change
- 9Different schedules look like...-General schedule for the owner and GC
-More detailed schedule for PM and Sup
-In-depth schedules for foremen and subs - 10Benefits of Scheduling-Balanced workflow
-Improvements in control of material usage
-Better control of cash flow
-Better awareness of time required for specific tasks by workers and management
-Better awareness of time sequences and how different projects are related
-More efficient ordering of rental equipment
-Better planning for inspections
-Better control of lead-time for material delivery and just-in-time delivery - 11Scheduling System Stages1. Preparing the plan
2. Creating the schedule
3. Communicating its necessity and benefits to all users - 12Steps for Preparing the Plan1. Review everything required
2. Make a list of all materials, labor, costs, expenses, and equipment required to complete each phase
3. Establish the time required - 13Activity DefinitionOne identifiable item of work within the total project
- 14Contractor needs to know the following information before deciding how simple or complex the project schedule should be...-Size of the project and how complex
-Number of workers
-Time it will take for craftsmen to complete their work
-Contract's provisions
-Requirements or restrictions imposed by the owner or lender
-Other on-going projects - 15Scheduling System Types-Simple list
-Gantt chart (time scale or bar chart)
-Critical Path Method (CPM) - most complicated, also called PERT charts - 16Working DaysMon-Fri
- 17Calendar DaysMon-Fri, Sat & Sun, holidays
- 18Time is of the essenceProject must be completed by the contract completion date
- 19Time schedule guidelines-Calculate time estimates for individual activities that make up project
-Use records of past performance of labor tables found in construction reference manuals
-Determine if time estimate for each task needs to be changed
-Determine availability of labor and equipment
-Estimate number of workdays and workweeks
-Factor in contingency time - 20Contingency timeAdditional time allotted between tasks; enables contractor to develop a real-world plan
- 21What should each task be assigned?An earliest start date and latest start date
- 22What comes after scheduling the start dates?Task's earliest completion date and latest completion date
- 23Float TimeTime an activity can float before the timing becomes critical to the project completion date
- 24Types of SchedulesList, Time Scale, Bar Chart Project Schedule, Critical Path Method (CPM)
- 25Type of Schedule: Time ScaleChart can be used in the planning stages of the project; commonly used at the job site; fails to show interrelationship of tasks
- 26Type of Schedule: Bar Chart Project ScheduleContractor can quickly make decisions - reassignment of employees and equipment; very useful for planning future jobs
- 27Type of Schedule: Critical Path Method (CPM)Standard method of scheduling projects
- 28Critical PathShortest duration for an activity or series of activities
- 29Cost LoadCosts associated with activities; so cash flow can be shown on CPM
- 30What are two important key s to a successful outcome for the project?Communication and training
- 31What should all of those involved in the project know about the project plan?-How the plan will operate
-How the plan will enable the project to progress efficiently
-How the implementation of the plan will benefit users - 32Types of MeetingsPre-Construction Conference, Status Meetings, Worker Safety Meetings
- 33Pre-Construction ConferenceHas all major parties (owner, architect, engineer, project manager, sup, and major subs); establish basic guidelines
- 34Status MeetingsHeld regularly at scheduled times; discuss status of the work
- 35Worker Safety MeetingsScheduled regularly to ensure company's safety policies are being followed; OSHA compliance officers should place rosters in the company's safety files
- 36Toolbox MeetingsSafety meetings with workers
- 37Employee Manual BenefitsMore knowledge of labor laws, employees can reduce potential liability, improved teamwork
- 38What should an employee manual include?-Employee and employer rights and responsibilities
-Work hrs
-Dress code
-Rules about the use of office resources
-Drug-free workplace policies
-Standards for record keeping and reporting
-Policies and procedures for sick leave, vacation, advancement, and benefits - 39What is a construction budget based on?Total estimate of project costs and income
- 40What must the contractor factor in to arrive at the total cost?Labor, materials, equipment, equipment rentals, tools, subs, company overhead credited to project, project overhead, and contingencies
- 41How can companies monitor costs?Evaluated on an item-by-item report; then compiled into a summary report that shows total cost picture
- 42Aside from knowledge of what materials are required for the job, material management is also concerned with...-How to purchase wisely
-How to begin procedures to ensure timely delivery
-How to manage inventory to eliminate need for expanded storage space or facilities - 43Purchase Order SystemUsed to organize and control purchases of products, materials or services from another company, vendor, or sub
- 44What are the key points that should be considered when establishing a PO system?-Complete description of goods
-Complete description of services
-Price
-Terms
-Refund and return policy
-Tax
-Representation
-Warranties - 45Just in time deliveryPurchasing material for jobs on an as-needed basis and having it shipped directly to the job site; can decrease storage space
- 46What does controlling inventory require?A direct connection with the purchasing system
- 47Person responsible for inventory control procedures should...-Check-In/Check-Out system
-Secure storage and maintenance
-Establish min and max levels of inventory
-Check regularly to ensure limits are maintained
-Purchase Journal
-Compare POs to budgeted amounts
-Only authorized people using POs
-All refunds and dollars owed to company are accounted for - 48Quality ControlManagement function that ensured project is being constructed according to the standards prescribed by the specifications; covers all aspects of the job - personnel, site safety, materials,...
- 49Project Documentation: Before project activities begin, it is important that...A specific list of all required documentation be prepared
- 50Project documentation records may be needed...-For legal purposes
-Tracking docs for defective materials
-Future planning
-To satisfy government requirements for doc maintenance
-Future review of the sequence of project flow - 51What do some construction companies utilize for their record keepign system?Construction Specification Institute's Master Format codes
- 52What are the two key ingredients when setting up a record keeping system?Consistency and common sense
- 53Time limits for retention of documents...They vary; retention period may be 6 months to a number of years
- 54As the time for completion of the project nears...PM will prepare and distribute an in-house punch list
- 55After all items on punch list is addressed, the PM must compile project documents:-Admin paperwork in contract docs
-Guarantees and warranties
-Waivers of lien from suppliers and subs
-Cert. of substantial Completion
-Cert of Occupancy
-Cert for inspections (electrical, plumbing, mechanical, fire safety)
-Additional certificates required by gov agencies or contract agreement