Engineer to set out edges of SCCP supports
Drill holes using relevant plywood template
Clean holes to allow engineer to survey
HOLD: Engineer to survey holes
If level okay, scabble substrate
If level too high, plane then scabble substrate
Install formwork box
HOLD: Engineer to check substrate levels
HOLD: Engineer to check substrate levels
HOLD: Engineer to check anchor design
If anchor design not okay stop work
HOLD: Check weather forecast
If too windy to lift stop works
Clean substrate surface and all holes
HOLD: Engineer/NNB to inspect substrate
If not okay, perform remedials
Engineer to level shims
Lift support onto shims
Dry place anchors
HOLD: Engineer to check anchor depths
If not okay, engineer to advise remedials
HOLD: Engineer to check support position
If not okay, adjust position
Check if holes contain ponded water
Resin in anchor bolts. Tighten nuts after period advised.
HOLD: Engineer to confirm date of grouting / book lab technician
HOLD: Engineer to advise whether curing tent required
Fixers to erect curing tent
If so, hoover
Grout supports
Deploy thermal blankets if required
Cure grout
Cut off anchor tops