EARNED VALUE MANAGEMENT

  1. Plan Schedule Management

    • Inputs
      • Project charter
        • It defines the summary milestone schedule
      • Project management plan
        • Scope baseline
        • Other information.
      • Enterprise environmental factors
        • Organizational culture
        • Published commercial information
      • Organizational process assets
        • Historical information
        • Historical information
    • Tools & Techniques
      • Expert judgment
        • It provides valuable insight about the environment from prior similar projects
      • Analytical techniques
        • Scheduling methodology
        • Scheduling tools
        • Techniques
        • Estimating approaches
      • Meetings
        • Project sponsor
        • Stakeholders
    • Outputs
      • Schedule management plan
        • Project schedule model development
        • Level of accuracy
        • Organizational procedures links
        • Units of measure
        • Organizational procedures links
        • Project schedule model maintenance
        • Control thresholds
  2. Estimate Activity Durations

    • Inputs
      • Schedule management plan
      • Activity list
        • It identifies the activities that will need duration estimates
      • Activity attributes
      • Activity resource requirements
      • Resource calendars
      • Project scope statement
        • Existing conditions
        • Availability of information
        • Length of the reporting periods.
      • Risk register
      • Resource breakdown structure
      • Enterprise environmental factors
        • Duration estimating databases and other reference data
        • Productivity metrics
        • Published commercial information
      • Organizational process assets
        • Historical duration information
        • Project calendars
    • Tools & Techniques
      • Expert judgment
      • Analogous estimating
      • Parametric estimating
      • Three-point estimating
        • Most likely
        • Optimistic
        • Pessimistic
      • Group decision-making techniques
      • Reserve analysis
    • Outputs
      • Activity duration estimates
      • Project documents updates
  3. Estimate Activity Resources

    • Inputs
      • Schedule management plan
      • Enterprise environmental factors
      • Organizational process assets
      • Activity cost estimates
      • Activity attributes
      • Risk register
      • Resource calendars
      • Activity list
    • Tools & Techniques
      • Alternative analysis
        • Many schedule activities have alternative methods of accomplishment
      • Published estimating data
      • Expert judgment
        • It is often required to assess the resource-related inputs to this process
      • Bottom-up estimating
        • It is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS. When an activity cannot be estimated with a reasonable
      • Project management software
    • Outputs
      • Activity resource requirements
      • Resource breakdown structure
      • Project documents updates
        • Activity list
        • Activity attributes
        • Resource calendars
  4. Define Activities

    • Input
      • Schedule management plan
        • It is the prescribed level of detail necessary to manage the work.
      • Scope baseline
        • Deliverables
        • Constraints
      • Enterprise environmental factors
        • Organizational cultures and structure
        • Published commercial information from commercial databases
      • Organizational process assets
        • Standardized processes
        • Existing formal and informal activity planning-related policies
    • Tools & Techniques
      • Decomposition
        • Each work package within the WBS is decomposed into the activities required
      • Rolling wave planning
        • It is a form of progressive elaboration
      • Expert judgment
    • Output
      • Activity list
        • includes all schedule activities required on the project
      • Activity attributes
        • Describe a necessary sequence of events or successor relationships
      • Milestone list
        • It has scheduled dates for specific milestones
  5. Sequence Activities

    • Input
      • Schedule management plan
      • Activity list
      • Activity attributes
      • Milestone list
      • Project scope statement
      • Enterprise environmental factors
      • Organizational process assets
    • Tools & Techniques
      • Precedence diagramming method (PDM)
        • Finish-to-finish (FF)
        • Finish-to-start (FS)
        • Start-to-start (SS).
        • Start-to-finish (SF).
      • Dependency determination
        • Mandatory dependencies
      • Leads and lags
    • Outputs
      • Project schedule network diagrams
      • Project documents updates
        • Activity lists
        • Activity attributes
  6. Develop Schedule

    • Inputs
      • Schedule management plan
      • Activity list
      • Activity attributes
      • Project schedule network diagrams
      • Activity resource requirements
      • Resource calendars
      • Activity duration estimates
      • Project scope statement
      • Risk register
      • Project staff assignments
      • Resource breakdown structure
      • Enterprise environmental factors
      • Organizational process assets
    • Tools & Techniques
      • Schedule network analysis
      • Critical path method
      • Critical chain method
      • Resource optimization techniques
      • Modeling techniques
      • Leads and lags
      • Schedule compression
      • Scheduling tool
    • Outputs
      • Schedule baseline
      • Project schedule
      • Schedule data
      • Project calendars
      • Project management plan updates
      • Project documents updates
  7. Control Schedule

    • Input
      • Project management plan
      • Project schedule
      • Work performance data
      • Project calendars
      • Schedule data
      • Organizational process assets
    • Tools & Techniques
      • Performance reviews
      • Project management software
      • Resource optimization techniques
      • Modeling techniques
      • Leads and lags
      • Schedule compression
      • Scheduling tool
    • Outputs
      • Work performance information
      • Schedule forecasts
      • Change requests
      • Project management plan updates
      • Project documents updates
      • Organizational process assets updates

Information

Description
Mind Map on EARNED VALUE MANAGEMENT, created by Mariela Gastelu on 24/03/2018.
Created by
Mariela Gastelu
Views
1
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?