EARNED VALUE MANAGEMENT
Plan Schedule Management
- Inputs
- Project charter
- It defines the summary milestone schedule
- Project management plan
- Scope baseline
- Other information.
- Enterprise environmental factors
- Organizational culture
- Published commercial information
- Organizational process assets
- Historical information
- Historical information
- Project charter
- Tools & Techniques
- Expert judgment
- It provides valuable insight about the environment from prior similar projects
- Analytical techniques
- Scheduling methodology
- Scheduling tools
- Techniques
- Estimating approaches
- Meetings
- Project sponsor
- Stakeholders
- Expert judgment
- Outputs
- Schedule management plan
- Project schedule model development
- Level of accuracy
- Organizational procedures links
- Units of measure
- Organizational procedures links
- Project schedule model maintenance
- Control thresholds
- Schedule management plan
- Inputs
Estimate Activity Durations
- Inputs
- Schedule management plan
- Activity list
- It identifies the activities that will need duration estimates
- Activity attributes
- Activity resource requirements
- Resource calendars
- Project scope statement
- Existing conditions
- Availability of information
- Length of the reporting periods.
- Risk register
- Resource breakdown structure
- Enterprise environmental factors
- Duration estimating databases and other reference data
- Productivity metrics
- Published commercial information
- Organizational process assets
- Historical duration information
- Project calendars
- Tools & Techniques
- Expert judgment
- Analogous estimating
- Parametric estimating
- Three-point estimating
- Most likely
- Optimistic
- Pessimistic
- Group decision-making techniques
- Reserve analysis
- Outputs
- Activity duration estimates
- Project documents updates
- Inputs
Estimate Activity Resources
- Inputs
- Schedule management plan
- Enterprise environmental factors
- Organizational process assets
- Activity cost estimates
- Activity attributes
- Risk register
- Resource calendars
- Activity list
- Tools & Techniques
- Alternative analysis
- Many schedule activities have alternative methods of accomplishment
- Published estimating data
- Expert judgment
- It is often required to assess the resource-related inputs to this process
- Bottom-up estimating
- It is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS. When an activity cannot be estimated with a reasonable
- Project management software
- Alternative analysis
- Outputs
- Activity resource requirements
- Resource breakdown structure
- Project documents updates
- Activity list
- Activity attributes
- Resource calendars
- Inputs
Define Activities
- Input
- Schedule management plan
- It is the prescribed level of detail necessary to manage the work.
- Scope baseline
- Deliverables
- Constraints
- Enterprise environmental factors
- Organizational cultures and structure
- Published commercial information from commercial databases
- Organizational process assets
- Standardized processes
- Existing formal and informal activity planning-related policies
- Schedule management plan
- Tools & Techniques
- Decomposition
- Each work package within the WBS is decomposed into the activities required
- Rolling wave planning
- It is a form of progressive elaboration
- Expert judgment
- Decomposition
- Output
- Activity list
- includes all schedule activities required on the project
- Activity attributes
- Describe a necessary sequence of events or successor relationships
- Milestone list
- It has scheduled dates for specific milestones
- Activity list
- Input
Sequence Activities
- Input
- Schedule management plan
- Activity list
- Activity attributes
- Milestone list
- Project scope statement
- Enterprise environmental factors
- Organizational process assets
- Tools & Techniques
- Precedence diagramming method (PDM)
- Finish-to-finish (FF)
- Finish-to-start (FS)
- Start-to-start (SS).
- Start-to-finish (SF).
- Dependency determination
- Mandatory dependencies
- Leads and lags
- Precedence diagramming method (PDM)
- Outputs
- Project schedule network diagrams
- Project documents updates
- Activity lists
- Activity attributes
- Input
Develop Schedule
- Inputs
- Schedule management plan
- Activity list
- Activity attributes
- Project schedule network diagrams
- Activity resource requirements
- Resource calendars
- Activity duration estimates
- Project scope statement
- Risk register
- Project staff assignments
- Resource breakdown structure
- Enterprise environmental factors
- Organizational process assets
- Tools & Techniques
- Schedule network analysis
- Critical path method
- Critical chain method
- Resource optimization techniques
- Modeling techniques
- Leads and lags
- Schedule compression
- Scheduling tool
- Outputs
- Schedule baseline
- Project schedule
- Schedule data
- Project calendars
- Project management plan updates
- Project documents updates
- Inputs
Control Schedule
- Input
- Project management plan
- Project schedule
- Work performance data
- Project calendars
- Schedule data
- Organizational process assets
- Tools & Techniques
- Performance reviews
- Project management software
- Resource optimization techniques
- Modeling techniques
- Leads and lags
- Schedule compression
- Scheduling tool
- Outputs
- Work performance information
- Schedule forecasts
- Change requests
- Project management plan updates
- Project documents updates
- Organizational process assets updates