7. PROJECT COST MANAGEMENT
Map content
7. PROJECT COST MANAGEMENT
7.1 Plan Cost Management
- This defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
- .1 Inputs
- .1 Project charter
- .2 Project management plan
- .3 Enterprise environmental factors
- .4 Organizational process assets
- .2 Tools & Techniques
- .1 Expert judgment
- .2 Data analysis
- Alternatives analysis
- can include reviewing strategic funding options, consideration of ways to acquire project resources such as making, purchasing, renting, or leasing.
- Alternatives analysis
- .3 Meetings
- .3 Outputs
- .1 Cost management plan
- Describes how the project costs will be planned, structured, and controlled
- Units of measure
- such as staff hours, staff days, or weeks for time measures; meters, liters, tons, kilometers, etc for each of the resources.
- Level of precision
- (e.g., US$995.59 to US$1,000)
- Level of accuracy
- The acceptable range (e.g., ±10%)
- Organizational procedures links.
- provides the framework for the cost management plan
- Control thresholds
- For monitoring cost performance
- Rules of performance measurement.
- Reporting formats.
- Additional details
- .1 Cost management plan
7.2 Estimate Costs
- This developing an approximation of the monetary resources needed to complete project work.
- .1 Inputs
- .1 Project management plan
- Cost management plan
- Describes estimating methods that can be used and the level of precision and accuracy required for the cost estimate.
- Quality management plan
- Describes the activities and resources necessary for the project management team
- Scope baseline
- Includes the project scope statement, WBS, and WBS dictionary:
- Cost management plan
- .2 Project documents
- Lessons learned register
- To improve the accuracy and precision of the cost estimates.
- Project schedule
- Includes the type, quantity, and amount of time that team and physical resources will be active on the project
- Resources requirements
- Identify the types and quantities of resources required for each work package or activity.
- Risk register
- Provides detailed information that can be used to estimate costs
- Lessons learned register
- .3 Enterprise environmental factors
- Include are Market conditions, Published commercial information, Exchange rates and inflation.
- .4 Organizational process assets
- .1 Project management plan
- .2 Tools & Techniques
- .1 Expert judgment
- 2 Analogous estimating
- Using for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
- Is generally less costly and less time-consuming than other techniques, it is also less accurate
- .3 Parametric estimating
- Uses a statistical relationship between historical data and other variables
- .4 Three-point estimating
- Most likely (tM), Optimistic (tO) and Pessimistic (tP).
- .5 Bottom-up estimating
- Is a method of estimating project duration or cost by aggregating the estimates of the lower level components of the WBS.
- .6 Data analysis
- Alternatives analysis
- Used to compare various levels of resource capability or skills; scheduling compression techniques
- Reserve analysis
- Contingency reserves are the estimated duration within the schedule baseline, which is allocated for identified risks that are accepted, are associated with the known-unknowns
- Management reserves are a specified amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within the scope of the project; also is not included in the schedule baseline.
- Alternatives analysis
- .7 Decision making
- .8 Meetings
- .3 Outputs
- .1 Duration estimates
- Are quantitative assessments of the likely number of time periods that are required to complete an activity, a phase, or a project. Example: A range of 2 weeks ± 2 days, 15% probability of exceeding 3 weeks
- .2 Basis of estimates
- .3 Project documents updates
- Activity attributes
- Assumption log
- Lessons learned register
- .1 Duration estimates
7.3 Determine Budget
- This aggregating the estimated costs of individual activities or work packages
- .1 Inputs
- .1 Project management plan
- Cost Mabagement Plan
- Describes how the project costs will be structured into the project budget.
- Resource management plan
- Provides information on rates, estimation of travel costs, and other foreseen costs.
- Scope baseline
- Includes the project scope statement, WBS, and WBS dictionary details for cost estimation and management
- Cost Mabagement Plan
- .2 Project documents
- .3 Business documents
- Business case
- Identifies the critical success factors for the project, including financia success factors.
- Benefits management plan
- Includes the target benefits, such as net present value calculations, timeframe for realizing benefits, and the metrics associated with the benefit
- Business case
- .4 Agreements
- .5 Enterprise environmental factors
- .6 Organizational process assets
- .1 Project management plan
- .2 Tools & Techniques
- .1 Expert judgment
- .2 Cost aggregation
- Are aggregated by work packages in accordance with the WBS, are then aggregated for the higher component levels of the WBS and, ultimately, for the entire project.
- .3 Data analysis
- * Management reserves are an amount of the project budget withheld for management control purposes and are reserved for unforeseen work that is within scope of the project. * Are intended to address the unknown unknowns that can affect a project. *Is not included in the cost baseline but is part of the overall project budget
- .4 Historical information review
- .5 Funding limit reconciliation
- This is accomplished by placing imposed date constraints for work into the project schedule.
- .6 Financing
- Involves the acquisition of funds for projects
- .3 Outputs
- .1 Cost baseline
- Is developed as a summation of the approved budgets for the different schedule activities, used as a basis for comparison to actual results.
- .2 Project funding requirements
- Are derived from the cost baseline.
- .3 Project documents updates
- Cost estimates
- Project schedule
- Risk register
- .1 Cost baseline
7.4 Control Costs
- This monitoring the status of the project to update the project costs and managing changes to the cost baseline
- .3 Outputs
- .1 Work performance information
- .2 Cost forecasts
- .3 Change requests
- .4 Project management plan updates
- Cost baseline
- Cost management plan
- Performance measurement baseline
- .5 Project documents updates
- Assumption log
- Basis of estimates
- Cost estimates
- Lessons learned register
- Risk register
- .2 Tools & Techniques
- .1 Expert judgment
- Include: Variance analysis, Earned value analysis, Forecasting, and Financial analysis
- .2 Data analysis
- Earned value analysis
- Earned value analysis (EVA).
- Compares the performance measurement baseline to the actual schedule and cost performance.
- Planned value (PV)
- It is the authorized budget planned for the work to be accomplished for an activity or work breakdown structure (WBS) component, not including management reserve.
- is also known as budget at completion (BAC).
- Earned value (EV)
- It is the budget associated with the authorized work that has been completed.
- Is used to calculate the percent complete of a project.
- Actual cost (AC)
- Is the realized cost incurred for the work performed on an activity during a specific time period
- Earned value analysis (EVA).
- Variance analysis
- Cost variance (CV = EV – AC),
- Is the amount of budget deficit or surplus at a given point in time, it indicates the relationship of physical performance to the costs spent.
- Schedule variance (SV = EV – PV),
- Is a measure of schedule performance
- It is the amount by which the project is ahead or behind the planned delivery date, at a given point in time.
- Schedule performance index (SPI) = EV/PV.
- Is a measure of schedule efficiency
- An SPI value less than 1.0 indicates less work was completed than was planned..
- An SPI greater than 1.0 indicates that more work was completed than was planned.
- The cost performance index (CPI) = EV/AC.
- Is a measure of the cost efficiency of budgeted resources
- CPI value of less than 1.0 indicates a cost overrun for work completed.
- A CPI value greater than 1.0 indicates a cost underrun of performance to date.
- Cost variance (CV = EV – AC),
- Trend analysis
- Examines project performance over time to determine if performance is improving or deteriorating.
- Charts.
- In earned value analysis, three parameters of planned value, earned value, and actual cost can be monitored and reported on both a period-by-period basis (typically weekly or monthly) and on a cumulative basis.
- Forecasting
- EAC forecasting approach is a manual, bottom-up summation by the project manager and project team.
- Reserve analysis
- Earned value analysis
- .3 To-complete performance index
- a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal,
- .4 Project management information system
- .1 Expert judgment
- 01 Inputs
- .1 Project management plan
- Cost management plan • Cost baseline • Performance measurement baseline
- .2 Project documents
- Lessons learned register
- .3 Project funding requirements
- Include projected expenditures plus anticipated liabilities.
- .4 Work performance data
- Contains data on project status such as which costs have been authorized, incurred, invoiced, and paid.
- .5 Organizational process assets
- .1 Project management plan