The initial schedule model is expected to be accurate by +/– 10%.
the schedule update increases the level of accuracy because the team knows more and more about the project.
the schedule model will be +/– 3% accurate
UNITS OF MEASURE
Annotations:
All estimates will be provided in calendar days.
ORGANIZATIONAL LINKS
Annotations:
The project schedule model will follow the organizational outline provided by the WBS. All schedule status reports will follow the format provided in the WBS as well.
REPORTING FORMATS
Annotations:
Every week a place will host a weekly status meeting to discuss how the project is tracking to its estimates. The status report for this meeting will follow the standard.
MODEL MAINTENANCE PROJECT
Annotations:
On a weekly basis, will update the project schedule model