Sab5#27 Details_Project_Mgmt_Plan

Maria Gonzalez INTEGRATION MANAGEMENT Certificacion Spanish

Map content

Sab5#27 Details_Project_Mgmt_Plan

  1. Know that management plan looks forward in time and that there are management plan for all the knowledge áreas.

  2. Project management plan is a set of plans and baselines (not just the Schedule).

  3. Project Management plan

  4. Subsidiary plans

  5. Baseline

    • The Project management plan includes scope baseline, Schedule baseline, and cost baselines against which the Project manager will report project performance. Deviation from baselines are often due to incomplete risk identification and risk management
  6. Change request approved

  7. Project management plan:

    • Change management plan
      • communications management plan
        • configuration managemente plan
          • cost baseline
            • cost management plan
              • human resource management plan
                • process improvement plan
                  • procurement management plan
                    • scope baseline: - Project scope statement - WBS - WBS dictionary
                      • Quality management plan
                        • requirements management plan
                          • Risk management plan
                            • Schedule baseline
                              • Schedule management plan
                                • Scope management plan
                                  • Stakeholder management plan
                                    • Project charter Project funding requirements Project schedule Project schedule network diagrams - Work performance data Work performance information Work performance reports
                                  • Project calendars - Team performance assessments
                                • Procurement statements of work - Stake holder registrer
                              • Procurement documents - Source selection criteria
                            • Milestone list - Seller proposals
                          • Issue log - Schedule data
                        • Forecast: Cost forecast & Schedule forecast - Risk register
                      • Change request - Resource calendars
                    • change log - Resource breakdown structure
                  • Basis of estimates - Requirements traceability matrix
                • Agrements - Requirements documentation
              • Activity resource requirements - Quality metrics
            • Activity list - Quality control measurements
          • Activity duration estimates - Quality check list
        • Activity cost estimates - Project statement of work
      • Activity attributes - Project staff assigment
  8. Project documents

    • Individual documents - They are not part of Project management plan but also they are use to manage the project as well - update it a long the Project life cicle
  9. Planning

Information

Description
Certificacion INTEGRATION MANAGEMENT Mind Map on Sab5#27 Details_Project_Mgmt_Plan, created by Maria Gonzalez on 11/04/2015.
Created by
Maria Gonzalez
Views
4
History
  • Created by Israel Miranda Torres · Apr 11, 2015
  • Copied by Maria Gonzalez · Apr 11, 2015
Rating

More on Project Management Plan

Feedback

What is it about?

What do you think of the new look?

How do you like it?