SAB9#70_Control Costs(Modified)
- In the exam, assume that the project manager is measuring, measuring, measuring on the project
It is all about knowing how you are doing compared to your plan and making adjustments when necessary
Project funding requirements
Project Management Plan
Work Performance Data
Orginizational Process Assets
Earned value management
Project Management Software
Reserve Analysis
To-complete performance index (TCPI)
Performance Reviews
- Earned Value Management
- Integrates COST, TIME and the WORK DONE
- PV - Planned Value
- EV - Erned Value
- AC - Actual Cost (total cost)
- BAC - Budget at Completion
- EAC - Estimate at Completion
- ETC - Estimate to Complete
- VAC - Variance at Completion
- Formulas
- CV -Cost Variance EV - AC
- SV - Schedule Variance EV - PV
- CPI - Cost Performance Index EV/AC
- The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)
- The CPI is a cumulative because it is using costs to date. It could be written as CPI(c)=EV(c)/AC(c)Eliminar
- Costo del Proyecto en un momento especifico
- SPI - Schedule Performance Index EV/PV
- EAC Estimate at Completion
- AC + Bottom-up ETC
- BAC/CPI
- AC+(BAC-EV)
- AC+(bac-EV)/CPI(c)XSPI(c))
- TCPI - To-Complete Performance Index (BAC-EV)/(BAC-AC)
- Overall del proyecto
- Siempre que EV este arriba de PV estoy adelantado en el tiempo (hago mas trabajo del que planie) , pero cuando esta EV abajo de PV estoy atrasado, Cuando AC este abajo de EV estoy ahorrando (es decir el esfuerzo que hago me esta costando menos de lo que planie), cuando AC esta arriba de PV estoy GASTANDO MAS !
- Overall del proyecto
- ETC - Estimate to Complete EAC-AC
- VAC - Variance al Complietion BAC-EAC
- Asegurarme que lo que pronostique sea lo que use de aca al final y que si tengo desviaciones sea capaz de controlarlo
- Earned Value Management
Forecasting
- ETC , con cuanto prespuesto voy a terminar del punto donde estoy al final !
Work Performance Information
- CV - Cost Variance
- SV - Schedule Variance
- CPI - Cost Performance Index
- SPI - Schedule Performance Index
- TCPI - To-Complete Performance Index
- EAC - Estimate to Complete
- VAC - Variance al Complietion
Cost Forecast
Change request
Update Management Plan
Update Project Documents
Update OPA´s
Progess Reporting
1 de 1 In the exam, assume that the project manager is measuring, measuring, measuring on the project
Images and files in the map
Information
- Description
- PMP Taller de Certificación PMI Mind Map on SAB9#70_Control Costs(Modified), created by Roman Velasquez on 27/04/2016.
- Created by
- Roman Velasquez
- Views
- 0
- History
-
- Created by Salvador Rueda · Apr 27, 2016
- Copied by Roman Velasquez · Apr 27, 2016
- Rating