T016 CONTRACT ADMINSTRATION

Description

Mind Map on T016 CONTRACT ADMINSTRATION, created by chrissi.cowan on 08/25/2014.
chrissi.cowan
Mind Map by chrissi.cowan, updated more than 1 year ago
chrissi.cowan
Created by chrissi.cowan over 10 years ago
28
0

Resource summary

T016 CONTRACT ADMINSTRATION
  1. ROLES/RESPONSIBILITES
    1. GENERAL ADMINSTRATION
      1. PROVISION OF INFO
        1. ENSURE: - clause 2.10 requires the CA to issue 2 copies of the information referred in the information release schedule
          1. SUPPLY: documents etc clause 2.8
            1. PROVIDE: additional info clause 2.11
            2. FINANCIAL
              1. Certify: Clause 4.6 - the amount of interim payments
                1. Consider: Clause 4.6 - interim valuations
                  1. Send: Clause 2.4 - send computations of the adjusted contract sum to the contractor
                  2. SUPERVISION
                    1. APPROVE: Clause 2.2.1 - quality of materials, goods and workmanship
                      1. INSTRUCT: (3.10)
                        1. OBTAIN: the contractors consent
                          1. ISSUE: (2.25)
                            1. (2.17 & 3.5) Consent to the removal of unfixed materials on site 'in writing' or sub letting
                              1. MAKE: (2.19) a fair and reasonable EOT in writing
                              2. MISC
                                1. UNDERTAKE: the role of CDMC
                                  1. UNDERTAKE: the role of the QS
                                    1. GIVE NOTICE: (8.4) identifying default by the contractor prior to termination
                                      1. DIRECT: contractors design portion
                                    2. RECORDS
                                      1. NOTES OF SITE INSPECTIONS
                                        1. OFFICE FILES
                                          1. PHOTOS
                                          2. SITE INSPECTIONS
                                            1. Frequency is determined by:
                                              1. Complexity
                                                1. Calibre of contractor
                                                  1. Progress and stages
                                                    1. CA's terms
                                                    2. Not determined by value
                                                      1. recording of information
                                                        1. date/time
                                                          1. weather
                                                            1. nr & type of operatives on site
                                                              1. onsite instructions
                                                                1. progress
                                                                2. review of quality of workmanship. The CA needs to know whats in the prelims & spec & be familar with codes of practice
                                                                  1. review of progress made in relation to the contract programme
                                                                    1. check materials against specified
                                                                      1. check the works conform to the spec & drawings
                                                                        1. records of any measurement of work that may be needed for certification
                                                                          1. health & safety
                                                                            1. confirm outcomes in writing
                                                                            2. SITE MEETINGS
                                                                              1. formal
                                                                                1. progress to date/expected completion/associated risks
                                                                                  1. contractor reported delays
                                                                                    1. instructions required
                                                                                      1. health &safety
                                                                                        1. employer changes
                                                                                          1. information required
                                                                                            1. sequencing of works
                                                                                              1. input by others i.e. specialists
                                                                                                1. queries relating to drawings/specification
                                                                                                  1. EOT
                                                                                                    1. claims for loss/expense
                                                                                                      1. valuations
                                                                                                        1. payments
                                                                                                          1. dayworks
                                                                                                            1. quality
                                                                                                              1. review of subcontractors
                                                                                                                1. effectiveness of communications
                                                                                                                2. informal
                                                                                                                  1. held on site, with operatives, contracts managers, suppliers, employer
                                                                                                                  2. Pre-contract
                                                                                                                    1. contacts, intros, emergency info, responsibilites
                                                                                                                      1. general matters
                                                                                                                        1. confirmation of general arrangements i.e. access, egress, emergency procedures
                                                                                                                          1. enabling works i.e. asbestos, scaffolding etc
                                                                                                                          2. licenses & obligations under the Party Wall etc. Act 1996
                                                                                                                            1. working hours
                                                                                                                              1. site arrangements i.e. welfare
                                                                                                                                1. schedule of condition
                                                                                                                                  1. employer & contractor insurance obligations
                                                                                                                                    1. VAT status confirmation
                                                                                                                                    2. Statutory matters
                                                                                                                                      1. CDM/F10/construction phase plan
                                                                                                                                        1. fire precautions/means of escape (Regulatory Reform (Fire Safety) Order
                                                                                                                                          1. confirmation of planning/listed consent
                                                                                                                                            1. confirmation of building control
                                                                                                                                              1. confirmation of obligations relating to environmental legislation i.e. site waste, noise, flora/fauna protection, land conttamination
                                                                                                                                              2. Programme
                                                                                                                                                1. stages
                                                                                                                                                  1. meetings
                                                                                                                                                    1. payments
                                                                                                                                                      1. valuations
                                                                                                                                                  2. REPORTING TO EMPLOYER
                                                                                                                                                    1. INSTRUCTIONS
                                                                                                                                                      1. TIME
                                                                                                                                                        1. VALUATIONS
                                                                                                                                                          1. INSTRUCTIONS/VARIATIONS
                                                                                                                                                            1. COMPLETION
                                                                                                                                                              1. LOSS/EXPENSE
                                                                                                                                                                1. ADJUSTED CONTRACT SUM
                                                                                                                                                                  1. INSOLVENCY OF CONTRACTOR
                                                                                                                                                                  2. RELATIONSHIP WITH THE EMPLOYER
                                                                                                                                                                    1. OTHER CONSIDERATIONS
                                                                                                                                                                      Show full summary Hide full summary

                                                                                                                                                                      Similar

                                                                                                                                                                      Memory Key words
                                                                                                                                                                      Sammy :P
                                                                                                                                                                      Geography - Unit 1A
                                                                                                                                                                      NicoleCMB
                                                                                                                                                                      CHEMISTRY C1 7
                                                                                                                                                                      x_clairey_x
                                                                                                                                                                      Biology- Genes, Chromosomes and DNA
                                                                                                                                                                      Laura Perry
                                                                                                                                                                      GCSE Mathematics Topics
                                                                                                                                                                      goldsmith.elisa
                                                                                                                                                                      GCSE REVISION TIMETABLE
                                                                                                                                                                      rebekahanne11
                                                                                                                                                                      Biology (B3)
                                                                                                                                                                      Sian Griffiths
                                                                                                                                                                      PSBD TEST # 3_1
                                                                                                                                                                      yog thapa
                                                                                                                                                                      Using GoConqr to teach science
                                                                                                                                                                      Sarah Egan
                                                                                                                                                                      Art styles
                                                                                                                                                                      Sarah Egan
                                                                                                                                                                      Creating Mind Maps with GoConqr
                                                                                                                                                                      Sarah Egan