Project Governance and Scope Change Management

  1. General Concepts

    • Project Scope Management
      • Defines project boundaries of what is included in the project deliverables required, and what is excluded
      • Required process that helps to ensure that the project includes all the work required to complete the project successfully.
      • Scope Management Plan
        • Documents the validation of the project scope and describes a definition of each aspect of the scope and how it will be controlled.
        • It is measured in order to identify deficiencies in performance which may occur in the execution of work
        • Determines and clarifies the deliverables of the project and provides a focused direction to allow the project manager to work towards the predefined goal and objectives.
      • Relationship
        • Three key areas need to be considered a properly governed scope management
          • Appropriate project organization structure is in place and formally documented
          • Decision-making body to be defined within the governance arrangements
          • Regulation of the quality of outputs
    • Project Governance
      • Use of systems, structures of authority, and processes to allocate resources and coordinate or control activity in a project
      • Good governance systems include
        • Aligning project goals with current strategic plan
        • Modifying strategic plan in response to changing circumstances
        • Monitoring performance of projects
        • Communicating these assurances as appropriate to external stakeholder
  2. KLIA 2

    • Main issues
      • Lack of project governance structure
        • No appropriate governance structure established to address the needs of the project and to oversee the performance of the project activities
      • Blurred Authority and Responsibilities
        • Lack of clarity of roles and responsibilities, as well as ownership of decision making within the project team and project setting, resulted in confusion.
      • Inadequate Assurance System
        • KLICS failed to exercise the optimum level of project oversight, leading to the failure of progress monitoring which subsequently caused project delays.
        • No clear guidelines on the statement of need, employer's requirements and concept drawings.

Information

Description
Mind Map on Project Governance and Scope Change Management, created by Ana Laura Salazar on 01/08/2018.
Views
0
Rating

More on Control Scope

Feedback

What is it about?

What do you think of the new look?

How do you like it?