Chapter 5: How to estimate software effort (3708)

Map content
Chapter 5: How to estimate software effort (3708)
Introduction:
- Successful projects are delivered on time,in budget and required quality
- Effort estimates -> affect the costs
- Activity durations -> affect delivery time
- Difficulties
- Subjective nature of estimating
- Political implications
- Internal
- Changing technology
- Lack of homogeneity of project experience
- Use existing project data can also not be correct
5.2 Where are estimates done
- At Various stages
- Strategic planning
- Project portfolio management
- Feasibility study
- Benefits of system will justify the costs
- System specification
- Between requirements specification and design
- Estimates at design stage confirms feasibility
- Evaluation of suppliers proposals
- Project planning
- As planning and estimating becomes more detailed, smaller components will be estimated
- Determine staff allocations
- Step 3 of Stepwise
- Specific provision for high level estimates.
- Step 5-8 is for individual activities -> each one level lower
- Strategic planning
- At Various stages
5.3 Problems with over and under estimating
- Over estimating causes longer projects
- Two laws
- Parkinson's Law
- Work expands to fill the time available
- Staff works less hard with easy target
- Brooke's Law
- Effort to complete project increase disproportionately to the number of staff assigned to project
- Additional management, coordination and communication
- Putting more people on a late job makes it later
- Parkinson's Law
- Two laws
- Under estimating
- Might not be completed in time or cost
- Affects quality due to pressure deadlines
- Weinberg's zeroth law of reliability -> If a system doesn't have to be reliable, it can meet any other objective
- Targets must be achievable. Increases morale and motivation
- Estimates are not predictions -> They are managed goals
- Over estimating causes longer projects
5.4 Basis for software estimating
- Need for historical data
- Past projects and new projects might not have the same merrits
- Measure of work
- Difficult in the beginning as many unknowns
- Work size is estimated due to uncertainty in eg. Skill of workers
- Source lines of code (SLOC)
- Thousands lines of code (KLOC)
- Need for historical data
5.5 Software effort estimation techniques
- Boehm's software effort model
- Algorithmic models
- Uses 'Effort Drivers' which are characteristics of the system and the implementation environment to determine effort
- Expert judgement
- Staff
- Relying on a knowledgeable person
- Combination of informal analogy and bottom-up approach
- Analogy
- Compare to similar completed project
- estimator identifies other projects (Source projects) with similar traits to new project (target projects)
- Also called 'case-based reasoning'
- One way to compare source to target is using ANGEL software
- Measures Euclidean distance between projects
- Compare to similar completed project
- Parkinson
- Staff effort available becomes the estimate
- Not really effort prediction method. Methods for setting scope
- price to win
- Estimate sufficiently low to win the contract
- Not really effort prediction methods. Method to determine price
- top-down
- Overall effort of project is broken down into effort required for components
- bottom-up
- component tasks are identified and sized, and aggregated to overall estimate
- Algorithmic models
- Boehm's software effort model
5.6 Bottom-up estimating
- Iterative process to break components into small 1-2 week tasks
- Better at the later stages of planning with more details
- Top-Down approach a precursor to bottom-up
- Procedural code -orientated approach
- bottom-up works at the level of activities
- Major activity is writing code at the software components level
- How to use bottom-up on software components
- Envisage number and type of modules in final system
- Identify primitive functions -> eg CRUD
- Estimate SLOC of each identified module
- Broad structure of the system and procedures
- Estimate work content, and the complexity and technical difficulty
- Multiply SLOC by a factor -> subjective
- Calculate work days effort
- Use historical data to convert weighted SLOC to effort
- Envisage number and type of modules in final system
- How to use bottom-up on software components
5.7 Top-down approach and parametric models
- Associated with parametric or algorithmic models
- Parameters such a KLOC and system size can be input
- Can use the analogy of estimating the effort to rebuild a house to resemble Top-Down approach
- Parametric models -> use formulas like
- effort = system size * productivity rate
- A model to forecast software development effort has two key components
- 1 -> Method to estimate work needed
- 2 -> Rate at which the task can be done
- KLOC is a size driver and dev experience is a productivity driver
- Productivity = effort/size
- Or you can use 'least squares regression' to derive an equation in the form:
- effort = constant1 +(size*constant2)
- Or you can use 'least squares regression' to derive an equation in the form:
- Some parametric models are focused on system/task size while COCOMO are concerned with productivity factors
- Having calculated the effort required -> this needs to be allocated to various activities in the project
- Associated with parametric or algorithmic models
5.10 Albrecht function point analysis (IFPUG)
- Top down approach
- Need to quantify the functional size of programs independent of programming language
- The concept of functional points were created
- Functional point analysis is on the basis that information systems comprise 5 major components, or 'external user types', which benefit the users
- External input types
- Input transactions which update internal computer files
- External outputs types
- Data is output to the user
- Eg. Screen, reports
- Data is output to the user
- External inquiry types
- transactions initiated by the user which provide information but don't update the internal file
- Directs the system to the information required
- Logical internal file types
- The files used by the system. In modern terms a database, relational table/entity
- External interface file
- Allows for output and input that may flow between applications
- Each external user type is identified in the application and is classified -> high, low and average complexity
- Each complexity is multiplied by a weight to get FP score -> summed then to get overall FP for information processing size
- External input types
- Functional point analysis is on the basis that information systems comprise 5 major components, or 'external user types', which benefit the users
- The concept of functional points were created
5.11 Functional points Mark 2
- Implies a improvement on Albrecht
- Information processing size measured in unadjusted function points (UFP) to which a technical complexity adjustment (TCA) is applied
- Assumption that information system comprise transactions with the structure below
5.12 COSMIC full function points
- Albrecht (IFPUG) is suitable for information systems, not for real time and embedded systems
- The COSMIC FFP was designed as an extension of IFPUG
- Argument is that existing FP methods are good at measuring work effort in Info system-> Internal procedures are mirrored by external features
- With embedded/real time systems the system features will be hidden -> interaction will be with hardware or other software
- COSMIC deals with this -> decomposing the system architecture into a hierarchy of software layers
- Layer above provide data up and request data from below
- A single layer can contain components which engage in peer-to-peer communication
- This determines the boundaries of the software components -> The points at which it receives input and transmits outputs
- Inputs and outputs are aggregated into data groups -> each data group relate to the same object of interest
- Data groups can be moved about in four ways
- entries (E)
- exits (X)
- reads (R)
- writes (W)
- Overall FFP determined by adding all the counts of each of the four types of data movements
- UOM -> Cfsu (COSMIC functional size unit)
- COSMIC -> Common Software Measurement Consortium
5.13 COCOMO 2 : a parametric productivity model
- Constructive Cost Model
- Effort -> measured in pm (person months) consisting of units of 152 hours working hours
- Model to calc person months
- pm -> effort in person months
- A = 2.94
- size -> kdsi
- derived from FP count
- sf -> exponent scale factor
- b = 0.91
- The effect of the exponent -> increase effort prediction for larger projects
- Qualities which govern exponent drivers used to calculate scale factor
- Precedentness (PREC)
- Development Flexibility (FLEX)
- Architecture/risk resolution (RESL)
- Team Cohesion (TEAM)
- Process Maturity (PMAT)
- Each of the scale factors for a project is rated -> Very low, low, normal, high, very high
- These are summed then multiplied by 0.01 and added to constant 0.91 to get overall exponent scale factor
- In COCOMO 2 model the effort multiplier (em) adjusts the estimate to take account of productivity factors
- Doesn't involve economies or dis-economies of scale
- each multiplier, for an app can be given a rating of extra low to extra high
- Value > 1 increases dev effort and <1 decreases
- Model to calc person months
- Size -> measured in kdsi ('thousands of delivered source code instructions')
- c and k -> constants
- Step 1: Determine system size in terms of kdsi
- c and k determined by system classification
- Organic
- Small dev team, in-house environment, flexible interface requirements
- Embedded
- System operates in tight constraints. Changes to system are costly
- Semi-detached
- Combination between organic and embedded or in between the two
- Related to system environment and technical nature of system
- k >1 -> larger projects require disproportionately more effort than smaller ones
- Organic
- c and k determined by system classification
- Estimates are required at different stages -> COCOMO 2 accommodates with three models at different stages
- Application composition
- External features of the system which the user will experience is designed
- Prototyping will be used, small applications, using high productivity tools
- Early design
- Fundamental software structures are designed
- System functional complexity affects architecture
- FP's used to gauge basic system size
- FP can be converted to LOC -> multiply by factor for programming language
- Post architecture
- Final construction, modification and tuning of system structure for final system
- Application composition
Images and files in the map
Information
- Description