Chapter 5: How to estimate software effort (3708)

Gideon Van Computer Science English

Chapter 5: How to estimate software effort (3708)

Map content

Chapter 5: How to estimate software effort (3708)

  1. Introduction:

    • Successful projects are delivered on time,in budget and required quality
    • Effort estimates -> affect the costs
    • Activity durations -> affect delivery time
    • Difficulties
      • Subjective nature of estimating
      • Political implications
        • Internal
      • Changing technology
      • Lack of homogeneity of project experience
      • Use existing project data can also not be correct
  2. 5.2 Where are estimates done

    • At Various stages
      • Strategic planning
        • Project portfolio management
      • Feasibility study
        • Benefits of system will justify the costs
      • System specification
        • Between requirements specification and design
        • Estimates at design stage confirms feasibility
      • Evaluation of suppliers proposals
      • Project planning
        • As planning and estimating becomes more detailed, smaller components will be estimated
        • Determine staff allocations
      • Step 3 of Stepwise
        • Specific provision for high level estimates.
        • Step 5-8 is for individual activities -> each one level lower
  3. 5.3 Problems with over and under estimating

    • Over estimating causes longer projects
      • Two laws
        • Parkinson's Law
          • Work expands to fill the time available
          • Staff works less hard with easy target
        • Brooke's Law
          • Effort to complete project increase disproportionately to the number of staff assigned to project
          • Additional management, coordination and communication
          • Putting more people on a late job makes it later
    • Under estimating
      • Might not be completed in time or cost
      • Affects quality due to pressure deadlines
      • Weinberg's zeroth law of reliability -> If a system doesn't have to be reliable, it can meet any other objective
    • Targets must be achievable. Increases morale and motivation
    • Estimates are not predictions -> They are managed goals
  4. 5.4 Basis for software estimating

    • Need for historical data
      • Past projects and new projects might not have the same merrits
    • Measure of work
      • Difficult in the beginning as many unknowns
      • Work size is estimated due to uncertainty in eg. Skill of workers
        • Source lines of code (SLOC)
        • Thousands lines of code (KLOC)
  5. 5.5 Software effort estimation techniques

    • Boehm's software effort model
      • Algorithmic models
        • Uses 'Effort Drivers' which are characteristics of the system and the implementation environment to determine effort
      • Expert judgement
        • Staff
        • Relying on a knowledgeable person
        • Combination of informal analogy and bottom-up approach
      • Analogy
        • Compare to similar completed project
          • estimator identifies other projects (Source projects) with similar traits to new project (target projects)
        • Also called 'case-based reasoning'
        • One way to compare source to target is using ANGEL software
          • Measures Euclidean distance between projects
      • Parkinson
        • Staff effort available becomes the estimate
        • Not really effort prediction method. Methods for setting scope
      • price to win
        • Estimate sufficiently low to win the contract
        • Not really effort prediction methods. Method to determine price
      • top-down
        • Overall effort of project is broken down into effort required for components
      • bottom-up
        • component tasks are identified and sized, and aggregated to overall estimate
  6. 5.6 Bottom-up estimating

    • Iterative process to break components into small 1-2 week tasks
    • Better at the later stages of planning with more details
    • Top-Down approach a precursor to bottom-up
    • Procedural code -orientated approach
      • bottom-up works at the level of activities
      • Major activity is writing code at the software components level
        • How to use bottom-up on software components
          • Envisage number and type of modules in final system
            • Identify primitive functions -> eg CRUD
          • Estimate SLOC of each identified module
            • Broad structure of the system and procedures
          • Estimate work content, and the complexity and technical difficulty
            • Multiply SLOC by a factor -> subjective
          • Calculate work days effort
            • Use historical data to convert weighted SLOC to effort
  7. 5.7 Top-down approach and parametric models

    • Associated with parametric or algorithmic models
      • Parameters such a KLOC and system size can be input
    • Can use the analogy of estimating the effort to rebuild a house to resemble Top-Down approach
    • Parametric models -> use formulas like
      • effort = system size * productivity rate
    • A model to forecast software development effort has two key components
      • 1 -> Method to estimate work needed
      • 2 -> Rate at which the task can be done
    • KLOC is a size driver and dev experience is a productivity driver
    • Productivity = effort/size
      • Or you can use 'least squares regression' to derive an equation in the form:
        • effort = constant1 +(size*constant2)
    • Some parametric models are focused on system/task size while COCOMO are concerned with productivity factors
    • Having calculated the effort required -> this needs to be allocated to various activities in the project
  8. 5.10 Albrecht function point analysis (IFPUG)

    • Top down approach
    • Need to quantify the functional size of programs independent of programming language
      • The concept of functional points were created
        • Functional point analysis is on the basis that information systems comprise 5 major components, or 'external user types', which benefit the users
          • External input types
            • Input transactions which update internal computer files
          • External outputs types
            • Data is output to the user
              • Eg. Screen, reports
          • External inquiry types
            • transactions initiated by the user which provide information but don't update the internal file
            • Directs the system to the information required
          • Logical internal file types
            • The files used by the system. In modern terms a database, relational table/entity
          • External interface file
            • Allows for output and input that may flow between applications
          • Each external user type is identified in the application and is classified -> high, low and average complexity
            • Each complexity is multiplied by a weight to get FP score -> summed then to get overall FP for information processing size
  9. 5.11 Functional points Mark 2

    • Implies a improvement on Albrecht
    • Information processing size measured in unadjusted function points (UFP) to which a technical complexity adjustment (TCA) is applied
    • Assumption that information system comprise transactions with the structure below
  10. 5.12 COSMIC full function points

    • Albrecht (IFPUG) is suitable for information systems, not for real time and embedded systems
    • The COSMIC FFP was designed as an extension of IFPUG
      • Argument is that existing FP methods are good at measuring work effort in Info system-> Internal procedures are mirrored by external features
      • With embedded/real time systems the system features will be hidden -> interaction will be with hardware or other software
      • COSMIC deals with this -> decomposing the system architecture into a hierarchy of software layers
        • Layer above provide data up and request data from below
        • A single layer can contain components which engage in peer-to-peer communication
        • This determines the boundaries of the software components -> The points at which it receives input and transmits outputs
        • Inputs and outputs are aggregated into data groups -> each data group relate to the same object of interest
        • Data groups can be moved about in four ways
          • entries (E)
          • exits (X)
          • reads (R)
          • writes (W)
        • Overall FFP determined by adding all the counts of each of the four types of data movements
          • UOM -> Cfsu (COSMIC functional size unit)
    • COSMIC -> Common Software Measurement Consortium
  11. 5.13 COCOMO 2 : a parametric productivity model

    • Constructive Cost Model
    • Effort -> measured in pm (person months) consisting of units of 152 hours working hours
      • Model to calc person months
        • pm -> effort in person months
        • A = 2.94
        • size -> kdsi
          • derived from FP count
        • sf -> exponent scale factor
          • b = 0.91
          • The effect of the exponent -> increase effort prediction for larger projects
          • Qualities which govern exponent drivers used to calculate scale factor
            • Precedentness (PREC)
            • Development Flexibility (FLEX)
            • Architecture/risk resolution (RESL)
            • Team Cohesion (TEAM)
            • Process Maturity (PMAT)
            • Each of the scale factors for a project is rated -> Very low, low, normal, high, very high
              • These are summed then multiplied by 0.01 and added to constant 0.91 to get overall exponent scale factor
        • In COCOMO 2 model the effort multiplier (em) adjusts the estimate to take account of productivity factors
          • Doesn't involve economies or dis-economies of scale
          • each multiplier, for an app can be given a rating of extra low to extra high
            • Value > 1 increases dev effort and <1 decreases
    • Size -> measured in kdsi ('thousands of delivered source code instructions')
    • c and k -> constants
    • Step 1: Determine system size in terms of kdsi
      • c and k determined by system classification
        • Organic
          • Small dev team, in-house environment, flexible interface requirements
        • Embedded
          • System operates in tight constraints. Changes to system are costly
        • Semi-detached
          • Combination between organic and embedded or in between the two
        • Related to system environment and technical nature of system
        • k >1 -> larger projects require disproportionately more effort than smaller ones
    • Estimates are required at different stages -> COCOMO 2 accommodates with three models at different stages
      • Application composition
        • External features of the system which the user will experience is designed
        • Prototyping will be used, small applications, using high productivity tools
      • Early design
        • Fundamental software structures are designed
        • System functional complexity affects architecture
        • FP's used to gauge basic system size
          • FP can be converted to LOC -> multiply by factor for programming language
      • Post architecture
        • Final construction, modification and tuning of system structure for final system

Images and files in the map

  • Chapter 5: How to estimate software effort (3708)
  • Chapter 5: How to estimate software effort (3708)
  • Chapter 5: How to estimate software effort (3708)
  • Chapter 5: How to estimate software effort (3708)
  • Chapter 5: How to estimate software effort (3708)
  • Chapter 5: How to estimate software effort (3708)
  • Chapter 5: How to estimate software effort (3708)

Information

Description
Computer Science Mind Map on Chapter 5: How to estimate software effort (3708), created by Gideon Van on 22/03/2019.