Ground Conditions, Foundations and Basements
Ground investigations
- Site history
- Environmental assesment
- For projects of a significant size a EIA (environmental impact assessment is required
- Project description (key components)
- Environment - populations, air, soil, water humans, landscape
- Mitigation
- Significant effects
- For projects of a significant size a EIA (environmental impact assessment is required
- Topography
- Ground conditions (trial pits, bore holes)
- Water table
- Dewatering may be required on sites near rivers or water ways
- Area should be excavated to 1m, sheet piles to 6m should be insertedd, water is them pumped out from internal area, excavation can begin
- Dewatering may be required on sites near rivers or water ways
- Interpretation
Foundation types
- Shallow
- Pad
- Strip
- Various forms are used dependant on ground conditions bearing capacity
- Normal strip on good ground
- Wide strip on low bearing capacity ground
- Deep strip on reasonable ground (2/3m)
- Wide strip on low bearing capacity ground
- Normal strip on good ground
- Various forms are used dependant on ground conditions bearing capacity
- Raft, Base slab
- Deep
- Pile/Pile caps
- Driven Piles are made of site and hammered into the ground using a piling rig
- Cast insitu pile foundations are poured on site
- Bored piles - Pre drilling, drill pile shaft and temporary casing, construct bell out, clean pile shaft, install reinforcement cage, pour concrete
- CFA (continuos flight auger) - Bore pile shaft and remove soil via excavator, concrete is poured as auger is removed, concrete cage is dropped in after
- Simple and effective
- Pile caps
- Excavate top of pile caps (some support for earth may be required)
- Blind pile caps to show reinforcement
- Bend reinforcement into pile cap base
- Suspend holding down bolt into position
- Add concrete base, clean out bolt holes
- Suspend holding down bolt into position
- Bend reinforcement into pile cap base
- Blind pile caps to show reinforcement
- Excavate top of pile caps (some support for earth may be required)
- Pile walls
- Piled rafts
- Pile/Pile caps
- Shallow
How can sites become well organised?
- Clear un-propped walls
- Sequenced working
- Managed access
- Managed materials and storage
Structures and Temporary works
- Basement walling
- Excavation
- Retaining wall propping
- Method statements
- Piled walls
- Continuous - simple reinforced concrete piled walls
- Secant - reinforced concrete piled walls with two types of concrete alternated to create a stronger bond
- Diaphragm walls
- Excavation of the ground using hydraulic cutter, hydraulic grab, cable grab or kelly grab on left side, then right then centre of wall
- Bentonite mud is pumped in to stop collapse
- Reinforcement cage is added
- funnels are suspended and filled with concrete, when lifted out the concrete spreads evenly at the base, this is repeated until concrete reaches the desired level
- Primary panels first, (left and right) secondary panel (right of left primary), closing panel (left of right primary)
- funnels are suspended and filled with concrete, when lifted out the concrete spreads evenly at the base, this is repeated until concrete reaches the desired level
- Reinforcement cage is added
- Bentonite mud is pumped in to stop collapse
- Excavation of the ground using hydraulic cutter, hydraulic grab, cable grab or kelly grab on left side, then right then centre of wall
- Steel Walls
- Interlocking steel panels are driven into the ground
- Vibration driven into sand and clay, hammer driven into rock
- Interlocking steel panels are driven into the ground
Excavating the basement
- Excavation of more than a single storey basement requires co-ordination and sequencing for the excavated material
- Basement walls and slabs need to form a watertight enclosure so casing against the walls needs to be done carefully
- Basements are often large thick poured concrete slabs, it is important to reduce any cracking due to thermal activity during setting and drying out so sequence is key
- Deeper basements will require temporary supports in the form of props to support the lateral load which is usually taken up by the floor slab
- The props are often hydraulic so that they can be changed to support the wall and correct any movement, the temporary propping is arranged in a way that the slabs can be formed and then the propping can be removed
- Propping is formed away from floor slabs, columns and internal wall locations
- The props are often hydraulic so that they can be changed to support the wall and correct any movement, the temporary propping is arranged in a way that the slabs can be formed and then the propping can be removed
- Deeper basements will require temporary supports in the form of props to support the lateral load which is usually taken up by the floor slab
- Basements are often large thick poured concrete slabs, it is important to reduce any cracking due to thermal activity during setting and drying out so sequence is key
- Basement walls and slabs need to form a watertight enclosure so casing against the walls needs to be done carefully
- Excavation of more than a single storey basement requires co-ordination and sequencing for the excavated material
Ground bearing floor slab make up
- 1. Geotextile
- Hardcore layer (150mm)
- Waterproof membrane
- Cement blinding (50mm)
- Insulation (100mm)
- Reinforced concrete slab
- Vapor barrier
- Screed
- Floor finish
- Screed
- Vapor barrier
- Reinforced concrete slab
- Insulation (100mm)
- Cement blinding (50mm)
- Waterproof membrane
- Hardcore layer (150mm)
- 1. Geotextile
Deep basement works
- When time or space is very limited the basement slabs will be built from top down
- The slabs will often require a continous pour, this can be a logistics problem when trying to get masses of concrete mix through london
- Top down construction
- 1. Drill piles and plunge columns into wet concrete, backfill with granulated material
- 2. Cast ground floor slab and excavate below through opening
- 3. Complete excavation and cast lower slab, tied into plunge columns
- 4. Excavate base slab through opening in slab above, ensure there is plenty of ventilation
- 5. Cast base slab, with pile caps and any lift its
- Complete all slabs and infill openings
- 5. Cast base slab, with pile caps and any lift its
- 4. Excavate base slab through opening in slab above, ensure there is plenty of ventilation
- 3. Complete excavation and cast lower slab, tied into plunge columns
- 2. Cast ground floor slab and excavate below through opening
- 1. Drill piles and plunge columns into wet concrete, backfill with granulated material
Images and files in the map
Information
- Description
- Quantity Surveying Mind Map on Ground Conditions, Foundations and Basements, created by Connor Benning on 02/05/2019.
- Created by
- Connor Benning
- Views
- 1
- Rating