Ground Conditions, Foundations and Basements

Connor Benning Quantity Surveying English

Ground Conditions, Foundations and Basements

Map content

Ground Conditions, Foundations and Basements

  1. Ground investigations

    • Site history
    • Environmental assesment
      • For projects of a significant size a EIA (environmental impact assessment is required
        • Project description (key components)
        • Environment - populations, air, soil, water humans, landscape
        • Mitigation
        • Significant effects
    • Topography
    • Ground conditions (trial pits, bore holes)
    • Water table
      • Dewatering may be required on sites near rivers or water ways
        • Area should be excavated to 1m, sheet piles to 6m should be insertedd, water is them pumped out from internal area, excavation can begin
    • Interpretation
  2. Foundation types

    • Shallow
      • Pad
      • Strip
        • Various forms are used dependant on ground conditions bearing capacity
          • Normal strip on good ground
            • Wide strip on low bearing capacity ground
              • Deep strip on reasonable ground (2/3m)
      • Raft, Base slab
    • Deep
      • Pile/Pile caps
        • Driven Piles are made of site and hammered into the ground using a piling rig
        • Cast insitu pile foundations are poured on site
          • Bored piles - Pre drilling, drill pile shaft and temporary casing, construct bell out, clean pile shaft, install reinforcement cage, pour concrete
          • CFA (continuos flight auger) - Bore pile shaft and remove soil via excavator, concrete is poured as auger is removed, concrete cage is dropped in after
            • Simple and effective
        • Pile caps
          • Excavate top of pile caps (some support for earth may be required)
            • Blind pile caps to show reinforcement
              • Bend reinforcement into pile cap base
                • Suspend holding down bolt into position
                  • Add concrete base, clean out bolt holes
      • Pile walls
      • Piled rafts
  3. How can sites become well organised?

    • Clear un-propped walls
    • Sequenced working
    • Managed access
    • Managed materials and storage
  4. Structures and Temporary works

    • Basement walling
    • Excavation
    • Retaining wall propping
    • Method statements
    • Piled walls
      • Continuous - simple reinforced concrete piled walls
      • Secant - reinforced concrete piled walls with two types of concrete alternated to create a stronger bond
    • Diaphragm walls
      • Excavation of the ground using hydraulic cutter, hydraulic grab, cable grab or kelly grab on left side, then right then centre of wall
        • Bentonite mud is pumped in to stop collapse
          • Reinforcement cage is added
            • funnels are suspended and filled with concrete, when lifted out the concrete spreads evenly at the base, this is repeated until concrete reaches the desired level
              • Primary panels first, (left and right) secondary panel (right of left primary), closing panel (left of right primary)
    • Steel Walls
      • Interlocking steel panels are driven into the ground
        • Vibration driven into sand and clay, hammer driven into rock
  5. Excavating the basement

    • Excavation of more than a single storey basement requires co-ordination and sequencing for the excavated material
      • Basement walls and slabs need to form a watertight enclosure so casing against the walls needs to be done carefully
        • Basements are often large thick poured concrete slabs, it is important to reduce any cracking due to thermal activity during setting and drying out so sequence is key
          • Deeper basements will require temporary supports in the form of props to support the lateral load which is usually taken up by the floor slab
            • The props are often hydraulic so that they can be changed to support the wall and correct any movement, the temporary propping is arranged in a way that the slabs can be formed and then the propping can be removed
              • Propping is formed away from floor slabs, columns and internal wall locations
  6. Ground bearing floor slab make up

    • 1. Geotextile
      • Hardcore layer (150mm)
        • Waterproof membrane
          • Cement blinding (50mm)
            • Insulation (100mm)
              • Reinforced concrete slab
                • Vapor barrier
                  • Screed
                    • Floor finish
  7. Deep basement works

    • When time or space is very limited the basement slabs will be built from top down
    • The slabs will often require a continous pour, this can be a logistics problem when trying to get masses of concrete mix through london
    • Top down construction
      • 1. Drill piles and plunge columns into wet concrete, backfill with granulated material
        • 2. Cast ground floor slab and excavate below through opening
          • 3. Complete excavation and cast lower slab, tied into plunge columns
            • 4. Excavate base slab through opening in slab above, ensure there is plenty of ventilation
              • 5. Cast base slab, with pile caps and any lift its
                • Complete all slabs and infill openings

Images and files in the map

  • Ground Conditions, Foundations and Basements

Information

Description
Quantity Surveying Mind Map on Ground Conditions, Foundations and Basements, created by Connor Benning on 02/05/2019.
Created by
Connor Benning
Views
1
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?