Mind map
Buncefield Oil Terminal Explosion_1
Map content
Buncefield Oil Terminal Explosion_1
Design Life Cycle
- Detailed Design
- Storage Capacity
- Controls
- Pumps
- Tank Lid
- Materials used
- Fuel tank storage and transportation
- Construction
- Materials
- Tanks
- Fuel pumps
- Manufactoring
- Workers
- Function
- Design Lifecylce
- Usability of systems
- Materials
- Commissioning
- Testing
- Transportation of Storage Tanks
- Via road tank or pipleines
- Maintenance
- Operating
- Controls
- Level Gauge
- Monitoring systems
- Operator Skill/Requirements
- Function
- Controls
- Maintaining
- Parts/Repair
- Service Requirements
- Decomissioning
- Tanks
- Only for qualified and competent technicians
- tank must be fully drained, degassed and certified
- Only for qualified and competent technicians
- Tanks
- Detailed Design
What Happened
- 19.00, Tank 912 started receiving unleaded motor fuel; pumping at about 550 m3/hour (***)
- 3:00, Tank fuel levels recorded unchanged reading, yet still continued to be fuelled
- 05.20 Tank 912 would have been completely full. It now began to overflow (***)
- 05.38 vapour from the escaping fuel is first visible in CCTV footage
- 05.46 the vapour cloud had thickened to a depth of about 2 m and was flowing out of storage site onto all directions
- At 06.01 the first explosion occurred, followed by further explosions and a large fire that engulfed over 20 large storage tanks.
- The fire burned for several days, destroying most of the site, 2,000 homes were evacuated and 92 neighboring firms were affected
Why it happened
- Failures
- People
- Individual Factors
- Designers and suppliers of independent level switch were poorly trained
- The site operator did not exercise sufficient oversight of the ordering, installation and testing procedure
- Individual Factors
- Workplaces
- Workplace Factors
- There was only one visual display screen for all the tanks which meant that the status of only one tank could be fully viewed at a time
- lack of engineering expertise on site
- Equipment Design
- Automatic Level Gauge (ALG) did not function
- Independent level switch was inoperative
- Critical Padlock not fitted
- On the tank screen mimic a red ‘stop’ emergency shutdown button was showed.
- this was not working and had never been fitted into the system.
- Work Environment
- The ATG system hadn’t the set the alarm in the event of inconsistencies between tank level measurements and filling data
- The lack of a maintenance regime
- Workplace Factors
- Management
- Organisational/System Factors
- None of the staff at the site was aware of the need for the padlock to be replaced
- failure to implement management of change processes
- Job Design
- Poor shift working times meant workers were exhausted
- poor communications at shift handover
- Information transfer
- Tank storage supervisors did not have access to monitoring screens - Lack of control of incoming fuel
- No written evidence on which the tanks had to be filled
- Organisational/System Factors
- People
- Failures
System Parts
- Tank
- Vents on Tank roof
- Automatic Level gauge
- measured the rising level of fuel and displayed this on a screen in the control room
- Access Hatch
- vertical, cylindrical, non-refrigerated, above-ground
- side walls greater than 5 m in height
- Tankers operating from Buncefield were of 44 or 18 tonnes capacity
- Staff
- Tasks
- Operators monitored the arrival of the various grades of fuel and separated them out into dedicated tanks by fuel type
- Training
- Tasks
- Oil Pumps
- Independent High-level switch
- Alarm Circuit
- Check Lever
- Critical Padlock
- Independent High-level switch
- Storage and transfer depot
- e three pipelines all transported fuel products in discrete batches, separated by an interface or buffer of mixed product
- interface of mixed fuel was diverted to special small tanks to be reinjected into the main large storage tanks
- separated products left the depot either by road tanker or, in the case of the majority of aviation fuel, via two dedicated pipelines
- Tank
Information
- Description
- Mind Map on Buncefield Oil Terminal Explosion_1, created by sidney.irwin9101 on 02/10/2015.
- Created by
- sidney.irwin9101
- Views
- 4
- History
-
- Created by sidney.irwin9101 · Oct 2, 2015
- Copied by sidney.irwin9101 · Oct 2, 2015
- Rating