Buncefield Oil Terminal Explosion_1

  1. Design Life Cycle

    • Detailed Design
      • Storage Capacity
      • Controls
      • Pumps
      • Tank Lid
      • Materials used
      • Fuel tank storage and transportation
    • Construction
      • Materials
        • Tanks
        • Fuel pumps
      • Manufactoring
        • Workers
      • Function
        • Design Lifecylce
        • Usability of systems
    • Commissioning
      • Testing
      • Transportation of Storage Tanks
        • Via road tank or pipleines
      • Maintenance
    • Operating
      • Controls
        • Level Gauge
        • Monitoring systems
      • Operator Skill/Requirements
      • Function
    • Maintaining
      • Parts/Repair
      • Service Requirements
    • Decomissioning
      • Tanks
        • Only for qualified and competent technicians
          • tank must be fully drained, degassed and certified
  2. What Happened

    • 19.00, Tank 912 started receiving unleaded motor fuel; pumping at about 550 m3/hour (***)
    • 3:00, Tank fuel levels recorded unchanged reading, yet still continued to be fuelled
    • 05.20 Tank 912 would have been completely full. It now began to overflow (***)
    • 05.38 vapour from the escaping fuel is first visible in CCTV footage
    • 05.46 the vapour cloud had thickened to a depth of about 2 m and was flowing out of storage site onto all directions
    • At 06.01 the first explosion occurred, followed by further explosions and a large fire that engulfed over 20 large storage tanks.
    • The fire burned for several days, destroying most of the site, 2,000 homes were evacuated and 92 neighboring firms were affected
  3. Why it happened

    • Failures
      • People
        • Individual Factors
          • Designers and suppliers of independent level switch were poorly trained
          • The site operator did not exercise sufficient oversight of the ordering, installation and testing procedure
      • Workplaces
        • Workplace Factors
          • There was only one visual display screen for all the tanks which meant that the status of only one tank could be fully viewed at a time
          • lack of engineering expertise on site
        • Equipment Design
          • Automatic Level Gauge (ALG) did not function
          • Independent level switch was inoperative
            • Critical Padlock not fitted
          • On the tank screen mimic a red ‘stop’ emergency shutdown button was showed.
            • this was not working and had never been fitted into the system.
        • Work Environment
          • The ATG system hadn’t the set the alarm in the event of inconsistencies between tank level measurements and filling data
          • The lack of a maintenance regime
      • Management
        • Organisational/System Factors
          • None of the staff at the site was aware of the need for the padlock to be replaced
          • failure to implement management of change processes
        • Job Design
          • Poor shift working times meant workers were exhausted
          • poor communications at shift handover
        • Information transfer
          • Tank storage supervisors did not have access to monitoring screens - Lack of control of incoming fuel
          • No written evidence on which the tanks had to be filled
  4. System Parts

    • Tank
      • Vents on Tank roof
      • Automatic Level gauge
        • measured the rising level of fuel and displayed this on a screen in the control room
      • Access Hatch
      • vertical, cylindrical, non-refrigerated, above-ground
      • side walls greater than 5 m in height
      • Tankers operating from Buncefield were of 44 or 18 tonnes capacity
    • Staff
      • Tasks
        • Operators monitored the arrival of the various grades of fuel and separated them out into dedicated tanks by fuel type
      • Training
    • Oil Pumps
      • Independent High-level switch
        • Alarm Circuit
        • Check Lever
        • Critical Padlock
    • Storage and transfer depot
      • e three pipelines all transported fuel products in discrete batches, separated by an interface or buffer of mixed product
      • interface of mixed fuel was diverted to special small tanks to be reinjected into the main large storage tanks
      • separated products left the depot either by road tanker or, in the case of the majority of aviation fuel, via two dedicated pipelines

Information

Description
Mind Map on Buncefield Oil Terminal Explosion_1, created by sidney.irwin9101 on 02/10/2015.
Views
4
History
  • Created by sidney.irwin9101 · Oct 2, 2015
  • Copied by sidney.irwin9101 · Oct 2, 2015
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?