O GoConqr está de visual novo! Conte para nós o que você achou.

Flashcards

CAPM Equations

Katie Brewer Project Management CAPM Inglês 19 flashcards

Flashcards do conjunto (19)

  1. 1[O + P + (4 x ML)] / 6PERT (Program Evaluation & Review Technique)
  2. 2(LS - ES) or (LF - EF)Total float
  3. 3EV - ACCost Variance (CV)
  4. 4EV / ACCost Performance Index (CPI)
  5. 5EV - PVSchedule Variance (SV)
  6. 6EV / PVSchedule Performance Index (SPI)
  7. 7SPI / SPV > 1 (positive value)Ahead of schedule
  8. 8SPI / SV < 1 (negative value)Behind schedule
  9. 9CPI / CV > 1 (positive value)Under budget (good)
  10. 10CPI / CV < 1 (negative value)Over budget (bad)
  11. 11AC + BAC - EVEstimate at Completion (EAC) - if performing at the budget rate
  12. 12BAC / CPIEstimate at Completion (EAC) - if performing at a steady rate
  13. 13AC + (BAC - EV) / (CPI x SPI)Estimate at Completion (EAC) - if considering both SPI and CPI
  14. 14EAC - ACEstimate to Completion (ETC)
  15. 15BAC - EACVariance at Completion (VAC)
  16. 16(BAC - EV) / (BAC - AC)To-Complete Performance Index (TCPI) - if based on BAC
  17. 17(% of work that should be completed) x BACPlanned Value (PV)
  18. 18(% of completed work) x BACEarned Value (EV)
  19. 19(BAC - EV) / (EAC - AC)To-Complete Performance Index (TCPI) - if based on EAC

Informações

Descrição
CAPM Project Management FlashCards sobre CAPM Equations, criado por Katie Brewer em 05-07-2018.
Criado por
Katie Brewer
Visualizações
18
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?