Definition of the problem

The feasibility of the proposed system is considered.

This stage is also known as "the feasibility stage"

An initial look at the existing system to see how it can be improved or meet the needs of the end user

A feasibility report is produced at the end of this stage

Main Process Constraints

Important Questions that should be answered in this stage

Time

Budget

Hardware Choice

Software Choice

Can the need for a new system be justified?

Is it technically feasible and economically desirable to the end users?

Can the solution be designed and implemented within the given constraints of timescale allocated and budget?

Will the solution have a positive impact on the end users and will the new system bring benefits

Will the solution fulfil all the needs and requirements of the end users

Design

The design stage follows a set of objectives (the requirement specification) that have been defined in the investigation and analysis stage

The methods of data capture that are going to be used have to be considered to make sure that they are compatible with the new system

The preparation, input, process, output and storage of the data must also be considered

The structure of the data must be defined together with the processing and the validation routines that will be used

The design of the queries and reports that have to be identified as requirements during the investigation stage needs to be considered as well

The main output from this stage is the design specification

This also covers such activities as the design of the user interface and the screen layout

Development of any user feedback requirements (error messages) should be linked with this

Documentation

The documentation that gets passed to the end user includes

Detailed program specifications

Recovery procedures

Operating procedures

User manuals

Test plans, data and logs

Security details

Version details

Technical details for associated hardware

Investigation and Analysis

This stage uses the feasibility report as its main input

The full nature of the problem is investigated in this stage

Methods of investigating the current system

The results of the investigation have to be fully analysed to gain a full understanding of the current system

The user requirements have to be defined during this stage

The requirement specification has to be constantly referred to to make sure that the new system meets all of the criteria of this

Questionnaires

Interviews

Meetings

Document Analysis

Observations

If the investigation is incomplete, the new system may not cover all the issues with the current system

Therefore, the new system may not benefit the organisation

The requirements are agreed with the client and will form the basis for the rest of the system lifecycle

The agreed needs/ requirements are the output of this stage (the requirement specification)

Implementation

This stage is also known as the development stage

This stage uses the design specification as its main input

During this stage, programmers will create the code required for the software solution.

The main output of this stage will be working software code that is ready to be tested

This includes the development of the user interfaces and outputs, which were designed in the design stage

Any macros, processing and queries that are required by the client must be developed as well

Testing

Two main functions of this stage

A well-defined and comprehensive test plan must be produced

This stage can be vey expensive and time consuming but if it carried out correctly and throughly there will be fewer bugs and issues with the new system

If there are any bugs or errors in the code

If the system correctly meets the defined user requirements

The test plan must be followed and results must be documented

Evaluation and Maintenance

This is the final stage of the system lifecycle.

This stage concludes the whole cycle and a report is produced to summarise each stage of the project and all finds, problems encountered.

Installation

Parallel

Phased

Pilot

Direct

This type of installation is when the new system is run along the existing system. This allows any persistent bugs with the new system to be corrected without affecting the day to day running of the company. Once all problems have been resolved, the existing system will be withdrawn from operation and the new system will run on its own

An example of this type of installation is self service checkouts in supermarkets

This type of installation is when a new system is introduced into the company is stages ("phases"). This is done by running the new system in certain departments or areas

An example of this is self service checkouts in supermarkets. This is because they were introduced to a few shops to start with to see how consumers reacted to the change and then converting the rest of the stores to the new system

This is still an ongoing process for some supermarkets because not all of their stores are running the new system. In this case, self service checkout system

This method of installation is done by introducing the system to one department or store to see how it works

There is less of a risk involved in this type of installation because if the new system is unsuccessful, it can be withdrawn easily with little disruption

This type of installation is done by introducing the new system to the company in one hit. The existing system is removed and the new system is left to run on its own.

This is a risky method of installation because the new system may not work due to undiscovered bugs or because users may not be able to adapt fast enough to use the new system

Installation Parallel Phased Pilot Direct This type of installation is when the new system is run along the existing…

The System Lifecycle

Informações

Descrição
A-Level ICT Notas sobre The System Lifecycle - created from Mind Map_2, criado por harry.spong em 30-12-2013.
Criado por
harry.spong
Visualizações
22
Tags
a-level ictict
Histórico
  • Criado por harry.spong · 30 dez 2013
  • Copiado para Nota por harry.spong · 30 dez 2013
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?