Work Breakdown Structure

Niamh Ryan Project Management Inglês 7 slides

Slides do conjunto (7)

  1. What is a Work Breakdown Structure?

    • A Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables
    • It is not a description of the processes followed to perform the project
    • It is one of the essential steps to planning a project
  2. Advantages of using a WBS

    • Helps the project manager to be both comprehensive and specific
    • Helps to define the scope of a project which is essential in ensuring the delivery of the project's objectives and outcomes
    • Makes it easier to:
    • Estimate required resources
    • Create a realistic project schedule
    • Control each stage of the project
    • Especially useful for bigger projects that involve many elements
  3. Importance of the WBS

    • A poorly constructed WBS can result in:
    • Ongoing, repeated project re-plans and extensions
    • Unclear work assignments
    • Scope creep
    • Budget overrun
    • Missed deadlines
    • Unusable new products or delivered features
    • Importance of the WBS
  4. Developing a WBS

    • Determine the major deliverables or products of the project. These are what must be produced in order to meet the project's objectives.
    • Divide major deliverables into component/intermediate deliverables.
    • Divide each of these work pieces into its component parts.
    • 8/80 rule: Continue to subdivide components until the lowest level component requires between 8 and 80 hours of work.
    • Work packages: When components are defined in sufficient detail for management and planning purposes, they are known as work packages.
  5. Example of Work Breakdown Structure

    • Example of Work Breakdown Structure
  6. Example of Work Breakdown Structure

    • Example of Work Breakdown Structure
  7. WBS interacting with other planning tools

    • WBS Dictionary: Contains detailed information about each element of the project, including definitions of each work package, effort level and duration of tasks, resources and more
    • Scope statement: High level elements of WBS should match, word for word, the nouns used to describe the project outcomes in the scope statement
    • Resource breakdown structure: Describes the project's resource organisation - Can be used in conjunction with WBS to define work package assignments.
    • Network diagram: A sequential arrangement of the work defined by the WBS
    • Project schedule: Elements of the WBS are starting points for defining the activities included in the project schedule.

Informações

Descrição
Overview of how to use a Work Breakdown structure to manage your business