1The authors identify three forces that combine to mandate the use of teams to solve problems. Identify the force that the authors named.
- Aexplosion in the growth of certified project managers
- Bworldwide acceptance of the Project Management Institute
- Cinteraction of supply and demand
- Devolution of worldwide competitive markets for the production and consumption of goods and services
2According to the authors, the prime objectives of project management are
- Ascope, cost, time
- Bquality, scope, schedule
- Ccustomer satisfaction, budget, schedule
- Dcost, quality, customer satisfaction
3The military uses the term __________ to refer to an exceptionally large, long-range
objective that is broken down into a set of projects.- Atask
- Bprogram
- Csubproject
- Dcampaign
4The seven attributes that characterize a project are __________.
- Apurpose, repetition, interdependencies, consistency, uncertainty, conflict, and lifecycle
- Blifecycle, schedule, cost, uncertainty, independence, uniqueness, and purpose
- Cscope, resources, uniqueness, conflict, interdependencies, importance, and lifecycle
- Dpurpose, lifecycle, conflict, certainty, independence, performance, and consistency
5This “stretched-S” pattern observed during the proj ect lifecycle, for the most part, is a result of the _________.
- Achanging levels of resources used during successive stages of the project lifecycle
- Bchanging attitudes of the people who work in the project.
- Cdifficulty in performing the individual activities of a project
- Dprinciple that work expands to fill the allotted time
6The conventional project lifecycle can be described as a pattern characterized by
____________.- Aparabolic progress
- Blogarithmic progress
- Cslow-rapid-slow progress
- Dextremely slow progress
7In a conventional project lifecycle, as work progresses, uncertainty about the expected outcome should __________.
- Abecome a constant
- Bdecrease
- Cincrease
- Dfully removed
8As sub-elements of a task, these __________ need to be accomplished to achieve the objectives of the task.
- Asubprojects
- Bprograms
- Cwork packages
- Dlevels of effort
9The project to construct a highway is unique because __________.
- Athe characteristics of terrain will be different for different segments.
- Bconsistency of the concrete will vary for different segments.
- Cdifferent types of laborers will be used to build various segments of the highway.
- Ddifferent people manage different sections of the highway.
10The process of creating artificial deadlines and budgets to accomplish specific, though routine, tasks within a functional department is called ______.
- Aprogramming
- Broutinizing
- Caccepting
- Dprojectizing
11Identify the example that would not usually be considered a project.
- Abuilding a house
- Bdeveloping a computer software application program
- Chosting a wedding reception
- Dassembly line manufacturing of automobiles
12Who, according to the authors, has played a significant role in the development of
techniques for project management?- Aeuropean navigators
- Btrader community
- Cbrokerage firms
- Dthe military
13The most crucial attribute of a project is that it must be important in the eyes of the
________- Aproject team
- Boperation managers
- Csenior management
- Dproject manager
14The authors identify four parties-at-interest or stakeholders in any project. These stakeholders are
- Aclient, funsctional manager, sponsor, and user
- Bclient, sponsor, public, and investors
- Cclient, functional manager, decision makers, and interveners
- Dclient, parent organization, project team, and the public
15Earned value is based on the concept that the percentage of project completion is closely correlated with __________.
- Athe number of levels in the project
- Brelevance of the project
- Ccost or the use of resources
- Dfinal assembly of the output
16The desired outcomes or results of a project are called ____________.
- Asubgroups
- Bwork packages
- Csubprojects
- Ddeliverables
17The largest amount of effort applied to a project is during the __________ phase.
- Aconception
- Bplanning, scheduling, monitoring, and control
- Cselection
- Devaluation and termination
18Which of the following is not one of the four dimensions of project success?
- Aopening new opportunities for the future
- Bnumber of people working on the project
- Cimpact on the customer
- Dbusiness impact on the organization
19Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources
between project. This is an example of project __________.- Abottleneck
- Bbreakdown
- Cinterdependencies
- Dmalfunctioning
20A project selected using the sacred cow model will be maintained until successfully completed or until __________.
- Athe project exceeds its budget
- Bthe project falls behind schedule
- Cthe boss recognizes the project as a failure and terminates it
- Dthe project manager is terminated
21If the NPV for a project is < 0, it indicates that the project will __________.
- Areport a profit loss
- Breport a profit gain
- Cfail to cover its required rate of return
- Dfail to generate cash inflows
22Which of the following is NOT a type of nonnumeric model?
- Athe sacred cow
- Bthe operating necessity
- Cpayback period
- Dthe product line extension
23Firms usually have two or more projects and this collection of projects is referred to as
__________.- Aa portfolio
- Ban initiation
- Ca planning
- Da stochastic model
24The project manager's responsibilities are broad and fall primarily into three separate areas. Identify the item that is NOT one of these.
- Aresponsibilities to the parent organization
- Bresponsibilities to the project and the client
- Cresponsibilities to the members of the project team
- Dresponsibilities to special-interest groups
25According to the authors, of all the characteristics desirable in a project manager,
__________ is the most important.- Aavailability
- Ba strong technical background
- Cability to keep the project team happy
- Ddrive to complete the task
26Project managers must have __________, which refers to possessing enough technical abilities to direct the project.
- Atechnical credibility
- Bmanagerial credibility
- Cnegotiation skill
- Ddrive to complete the task
27Resources initially budgeted for a project are frequently __________ for the task, partly because of natural optimism by the proposer about how many resources are needed.
- Asufficient
- Bdelayed
- Cinsufficient
- Dhindrances
28The functional manager uses the __________ approach and the PM uses the __________
approach.- Asystems; analytic
- Bnumerical; nonnumeric
- Canalytic; systems
- Dnonnumeric; numerical
29Which of the following is NOT typically recommended to be considered when hiring new team members?
- Ahigh-quality technical skills
- Bpolitical, and general, sensitivity
- Cstrong goal orientation
- Dlow self-esteem
30The two basic types of project selection models identified in the text are ________.
- Abiased and unbiased
- Bnumeric and nonnumeric
- Cactive and passive
- Dnumeric and qualitative
31Project proposals should include all of the following, EXCEPT __________.
- Aa section describing the past experience of the proposing group
- Ban executive summary
- Ca description of the ability of the proposer to supply the facilities, needed during the project
- Da list of the top executives in the proposing firm
32The __________ is also called the benefit-cost ratio.
- AQ-sort method
- Bprofitability index
- Cinternal rate of return
- Dpayback period
33Identify the attribute that is NOT normally associated with the job of functional manager.
- AThe functional manager is usually a generalist in the area being managed.
- BThe functional manager is responsible for deciding what resources will be devoted to accomplishing the task.
- CThe functional manager is administratively responsible for deciding how something will be done.
- DThe functional manager is responsible for deciding who will do the work.
34According to the authors the project manager should be more skilled at __________.
- Ageneral management
- Btechnology
- Csynthesis
- Danalysis
35The project manager needs __________ credibility.
- Atechnical and personal
- Badministrative and personal
- Ctechnical and administrative
- Dtechnical and financial
36PMI offers a certification for project managers. PMI offers examination for certification
as __________.- AProject Management Professionals
- BProject Management Experts
- CProject Management Associates
- DProject Management Engineers
37One of the major problems project managers have with creating a project team is coming up with adequate human resources. One way this commonly happens is by __________.
- Ahiring employees fired by other departments
- Btraining unskilled immigrants in project skills
- Cborrowing employees from other functional departments
- Ddemoting executive board members
38Most of the time spent by a project manager is spent __________.
- Aattending technical workshops
- Boverseeing the workforce
- Cfiling paperwork
- Dcommunicating
39A party to a conflict will usually be satisfied when the level of frustration has been
__________.- Aincreased by the domination of the other party
- Blowered to the point where no action against the other party is contemplated
- Clowered because the party realizes the hopelessness of continuing the conflict
- Deliminated because the party has surrendered to the other party
40Conflicts within the organization typically differ from conflicts with outsiders in one important way. As far as the organization is concerned, these conflicts are __________.
- Aconflicts between opponents
- Bconflicts between allies
- Cconflicts between microcultures
- Dconflicts between subcultures
41During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of
all conflicts involving __________.- Acontractual obligations
- Bproperty rights
- Cbudgeting
- Dresource allocation, and scheduling
42Personality conflicts during project phase-out are often caused by __________.
- Ahe absence of deadlines
- Bthe influx of newer technology
- Cpressure to complete the project and anxiety about leaving the project
- Ddistribution of expenses charged to the project
43The authors mention three situations where the highest level of negotiating skill is
required by the project manager. Which of the following is NOT one of them?- Agetting personnel from the functional manager
- Busing sub-contractors
- Cchanging project deliverables in midstream
- Dusing input from multiple functional units in developing the project mission
44Identify the statement that is NOT a major advantage of placing a project within a functional element of the parent organization.
- AThe flexible use of staff increases
- BExpertise is easily shared across multiple projects.
- CThe functional division tends to be oriented towards activities particular to its function.
- DThe functional division serves as a base of technological continuity.
45Identify the statement that is NOT a major advantage of placing a project within the pure project organization.
- AThe functional manager retains full line authority over project team members.
- BThe lines of communication are shortened.
- CCentralized authority tends to increase the speed of decision-making.
- DA holistic approach to performing the project is supported.
46Identify the statement that is NOT a major advantage of placing a project in the matrix approach.
- AA single individual, the project manager, takes responsibility for managing the project.
- BThe project will have access to representatives from the administrative units of the parent firm.
- CThe division of authority between the project manager and the functional managers is complex.
- DThere is less anxiety among team members about what will happen to them when the project is completed.