{"ad_unit_id":"App_Resource_Sidebar_Upper","resource":{"id":1042349,"author_id":531402,"title":"Gestion de Riesgo","created_at":"2014-06-30T06:36:53Z","updated_at":"2017-02-10T17:43:36Z","sample":false,"description":"Gestión de riego según el PMBOK 5ta. edición","alerts_enabled":true,"cached_tag_list":"gestión del riesgo, gestión de proyectos, pmp, pmbok","deleted_at":null,"hidden":false,"average_rating":"4.85","demote":false,"private":false,"copyable":true,"score":385,"artificial_base_score":0,"recalculate_score":false,"profane":false,"hide_summary":false,"tag_list":["gestión del riesgo","gestión de proyectos","pmp","pmbok"],"admin_tag_list":["gestión de proyectos"],"study_aid_type":"Quiz","show_path":"/quizzes/1042349","folder_id":996160,"public_author":{"id":531402,"profile":{"name":"aprendiendo_pmi","about":null,"avatar_service":"gravatar","locale":"es-ES","google_author_link":null,"user_type_id":null,"escaped_name":"aprendiendo_pmi","full_name":"aprendiendo_pmi","badge_classes":""}}},"width":300,"height":250,"rtype":"Quiz","rmode":"canonical","sizes":"[[[0, 0], [[300, 250]]]]","custom":[{"key":"env","value":"production"},{"key":"rtype","value":"Quiz"},{"key":"rmode","value":"canonical"},{"key":"sequence","value":1},{"key":"uauth","value":"f"},{"key":"uadmin","value":"f"},{"key":"ulang","value":"en_us"},{"key":"ucurrency","value":"usd"}]}
{"ad_unit_id":"App_Resource_Sidebar_Lower","resource":{"id":1042349,"author_id":531402,"title":"Gestion de Riesgo","created_at":"2014-06-30T06:36:53Z","updated_at":"2017-02-10T17:43:36Z","sample":false,"description":"Gestión de riego según el PMBOK 5ta. edición","alerts_enabled":true,"cached_tag_list":"gestión del riesgo, gestión de proyectos, pmp, pmbok","deleted_at":null,"hidden":false,"average_rating":"4.85","demote":false,"private":false,"copyable":true,"score":385,"artificial_base_score":0,"recalculate_score":false,"profane":false,"hide_summary":false,"tag_list":["gestión del riesgo","gestión de proyectos","pmp","pmbok"],"admin_tag_list":["gestión de proyectos"],"study_aid_type":"Quiz","show_path":"/quizzes/1042349","folder_id":996160,"public_author":{"id":531402,"profile":{"name":"aprendiendo_pmi","about":null,"avatar_service":"gravatar","locale":"es-ES","google_author_link":null,"user_type_id":null,"escaped_name":"aprendiendo_pmi","full_name":"aprendiendo_pmi","badge_classes":""}}},"width":300,"height":250,"rtype":"Quiz","rmode":"canonical","sizes":"[[[0, 0], [[300, 250]]]]","custom":[{"key":"env","value":"production"},{"key":"rtype","value":"Quiz"},{"key":"rmode","value":"canonical"},{"key":"sequence","value":1},{"key":"uauth","value":"f"},{"key":"uadmin","value":"f"},{"key":"ulang","value":"en_us"},{"key":"ucurrency","value":"usd"}]}
Todos los siguientes puntos son factores en la valoración de riesgo de un proyecto, excepto uno:
Answer
A) evento del riesgo
B) probabilidad del riesgo
C) impacto o cantidad en juego
) prima de seguro
Question 2
Question
2.-Si un proyecto tiene una probabilidad de 60 % de ganar $100.000 y una probabilidad de 40 % de perder $100.000 ¿Cuál es el valor monetario esperado del proyecto?
Answer
A) $100.000 de Ganancia
B) $60.000 de perdida
C) $20.000 de ganancia
D) $40.000 de perdida
Question 3
Question
3 Suponiendo que el rango de estimación es +3/-3 sigma alrededor de la media. ¿Cuál de los siguientes calculo involucra el menor riesgo?
Answer
A) 30 días más 0 menos 5 días
B) 22 -30 días
C) optimista=26 días ,Mas probable=30 días , pesimista=33 días