CPM
Karten in diesem Stapel (3)
- 1What is the critical path?The path through the network with zero floats.
- 2What is an activities float?The difference between its earliest and latest finish dates
- 3What is float a measure of?How much the start or completion of an activity may be delayed without affecting the end date of a project