- 1Schedule ManagementThe process of developing, maintaining and communicating schedules for time and resource
- 2Time SchedulingA collection of techniques used to develop and present schedules that show when work will be performed
- 3Activity DurationThe length of time that it takes to complete an activity
- 4Network DiagramA model of activities and their dependencies comprising nodes and links
- 5Network AnalysisA collective term for the different ways in which a network diagram may be analysed and including, for example, a critical path analysis, programme evaluation and review technique and critical chain
- 6FloatA term used to describe the flexibility with which an activity may be rescheduled.
There are various types of float such as total float and free float - 7Total FloatTime by which an activity may be delayed or extended without affecting the overall duration of the project or violating a target finish date
- 8Free FloatThe amount of time an activity can be delayed or extended without delaying the start of the next activity
- 9Critical PathA sequence of activities through a network diagram from start to finish, the sum of whose durations determines the overall duration.
There may be more than one such path