- 1avoiding loss of beding sand-weeping holes placed at regular intervals through pored in place or precast concrete curbs
-place cloth over joints or weep holes to prevent sand from entering - 2cleaning and sealing joint stabalizationloss of joint sand can occur high slope high wind areas with high surface run off
-can be resolved with joint stablizers - 3step 1locate area to be remediated fixed
-mark shoulder
remove pavers 0.8ft behind excavation line - 4step 2remove first paver with paver extractor
- 5step 1-5remove remaining pavers
remove bedding sand
excavate base material and soil, repair damaged base or utility as needed - 6step 6compact soil base
compact base material
compact base 2-4 inches 50-100mm
lifts to required density - 7step7replace bedding sand layer
screed with notched screed board achieving a crown, crown compensates for minor settling - 8step 8reinstate pavers
adjust joint spacing and alignment - 9step 9compact reinstated pavers
first compaction occurs After pavers are placed with no joint sand at least 2 passes - 10step 10place and spread joint sand
- 11step 11vibrate till joints are filled with sand
second pass works sand into joints sweep left over sand away - 12first interstate highway segmental paversromans empire
2000 years ago - 13seg clay brick pavement1000 ad
- 14clay pavers used in streets of north America1800s
- 15concrete pavers developed in the Netherlands1950s
- 16first paver manufacturing machine in north America1973
- 17icpi components1.compact soil subgrade
2.geotextile as required by design
3.compacted aggregate
4.beding sand 1 inch 25 mm
5.concrete pavers with sand filled joints - 18factors effecting interlock1 paver thickness
2 laying pattern
3 consistent joint widths
4 stationary edge restraints
5 paver shape and size
6 crown in cross section - 193 types of interlockhorizontal
vertical
rotational - 20load distributionslight movement in soil and from seasonal changes in moisture does not change the way the load is distributed
- 21the 4 point system OSHA program components1.managment commitment and employee involvement
2.hazrd analysis
3.hazrd prevention and control
4.traning for employees supervisors and managers - 22hazards on a hardscape instalation project-heat
-eyes
-impact
-vibration
hearing loss
-knee-silica - 23hierarchy of controls1physically remove hazard
2.replace the hazard
3.isolate people from the hazard
4.change the way people work
5.protect the worker with PPE - 24Controls 1.Engenering 2.Administrative 3.PPE1.isolate people from the hazard
2.Change the way people work
3.protect the person with PPE - 25Tool Box talk include?-work practices
-machinery
-tools
-equipment
-materials
-attitudes - 26job jacket contents?-proposal
-drawing
-maps
job sheets
daily time sheets
job quantity sheets - 27perimeter stakes always ? outside excavation ..12 inches
- 28Flow of materials1.plan flow before job starts
2.base or bedding sand distributed by loader or wheelbarrow
3.cubes of delivery of pavers timed best as possible
4.move pavers on site as little as possible
5.on a slope, start at the bottom and work uphill to maintain consistent joint widths - 29soil characteristics and compaction1gradation
2soil classification
3soil compaction
-measurement
-methods equipment
-geotextiles - 30field identification of soils1.patty test
2.shake test
3.snake test - 31patty shake snake1.evaluates water holding capacity of soil
2.tests for reaction to shaking
3.tests for thread toughness of soil - 32soil compactionincrease density and load-bearing capacity of soil
3 factors effect extent of soil compaction capability's
soil type/moisture in soil/type and amount of compacting - 33measuring soil compaction1.squeeze handful of soil to the size of a tennis ball.
2. drop the ball about 1ft 0.3 meter from the ground on to a hard surface
3. if the ball breaks into a small amount of uniform fragments, it is close to optimum moisture - 34soil compaction methods and equipment1. rammer
2.reversible plate compactor
3.forward plate compactor
4.static roller
Information
- Description
- Flashcards on icpi study stuff, created by joey steele on 05/04/2024.
- Created by
- joey steele
- Views
- 0
- History
-
- Created by Joseph Steele · Apr 3, 2024
- Copied by joey steele · Apr 5, 2024
- Rating