SAB4#43 Scope Levels

anesio.benna English

Mind map about scope levels: control account, deliverable and work packages

Mind map: scope levels

Map content

SAB4#43 Scope Levels

  1. Control Account

    • Work Package 1
      • Activity 1
      • Activity 2
    • Work Package 2
      • Activity 3
      • Activity 4
        • A distinct, scheduled portion of work performed during the course of a project
      • The work defined at the lowest level of the WBS for which cost and durtion can be estimated and managed
    • A management control point where is possible the analysis of work performance data regarding costs, schedule and scope.
  2. Deliverable

Information

Description
Rita 190-191 HF 198-200