SabPMS#22_Project_Selection

Mau Alonso Dirección de Proyectos Certificado PMP (Dirección de Proyectos) Spanish

SabPMS#22_Project_Selection

Map content

SabPMS#22_Project_Selection

  1. the project manager is not tipically involved in project selection

  2. Categories of project selection

    • Benefit measurement methods (comparative approach)
      • Murder board (a panel of people who try to shoot down a new projet idea)
      • Peer review
      • scoring models
      • Economic models (described below)
    • Constrained optimization methods (mathematical approach)
      • Linear programming
      • Integer Programming
      • Dynamic programming
      • Multi-Objective programming
  3. Economic Models

    • Present Value
      • value today of future cash flows
      • Avoid confuse PV with planned value (also used and described in Cost Management)
    • Net present value
      • Present value of the total benefits (income or revenue) minus the costs over many time periods
      • Provides a means for the organization to compare many projects and select the best (project with best NPV) to initiate
    • Internal rate of return
      • if a company has more than one project to invest, the company may look at the return of them and then select the project with the highest return
      • for exam, just to know the higher the IRR number, the better.
    • Payback period
      • lenght of time it takes for the organization to recover its investment in the project before it starts accumulating profit
        • Project with the shorter payback period is the best choice, but if there are other considerations the best choice might be a project with a longer payback period
    • Cost-benefit analysis
      • Compares the expected costs of the prohect to the portential benefits it could bring the organization
      • the results of analysis is a benefit cost ratio
        • > 1, means benifits are greater than costs
        • = 1, means costs and benefits are the same
        • <1, means the costs are greater than benefits
      • Project Manager may also perform a cost-benefit analysis to determine the best way to implement a project selected

Images and files in the map

  • SabPMS#22_Project_Selection

Information

Description
Certificado PMP (Dirección de Proyectos) Dirección de Proyectos Mind Map on SabPMS#22_Project_Selection, created by Mau Alonso on 22/10/2016.
Created by
Mau Alonso
Views
11
Rating

More on Project Selection and Initiation

Feedback

What is it about?

What do you think of the new look?

How do you like it?