SAB11#48 Validate Scope

Omar Arce Taller de Certificación de PMP p English

Map content

SAB11#48 Validate Scope

  • You need to gather all the stakeholders together and have them make sure that all the work really was done.
  1. Work performance data

  2. Project Management plan

  3. Deliverables

    • These are verified deliverables, which means they’ve been through Perform Quality Control.
  4. Traceability matrix

  5. Requirements documentation

  6. Verified deliverables

  7. Change requests

    • If they DON’T think that all the work was done, then you’ll need to make some changes. Back to change control!
  8. Project document updates

  9. Work performance information

  10. Group decision-making techniques

    • Once the stakeholders have inspected the deliverables, they’ll need to decide whether or not the deliverables can be accepted. Quality Assurance
    • Quality Assurance
      • In not made by the Proyect Manager. If there is not any QA the sponsor will take their place

Information

Description
p Taller de Certificación de PMP Mind Map on SAB11#48 Validate Scope, created by Omar Arce on 02/07/2016.
Created by
Omar Arce
Views
7
Rating

More on Validate Scope

Feedback

What is it about?

What do you think of the new look?

How do you like it?