6. Quality Management (Rita's)

Tuan Lam PMP Exam Prep Certificate Inglés 5,0Valoración media 5,0 de 5 (1 valoración) 9 fichas

Fichas del conjunto (9)

  1. 1PMI-ism's Quality?The degree to which the project fulfills the requirements
  2. 2Who determines quality metrics and keep finding ways to improve quality?Project manager
  3. 3Who recommends improvements?Project manager
  4. 4Should consider Quality if one of the project constraints changes?YES
  5. 5Could there be a separate QA department performing some quality activities, i.e. quality audits?YES
  6. 6Differences among: Plan, Perform and Control processes?Plan: look forward in time
    Perform: look backward in time at processes and procedures
    Control: look backward in time at results
  7. 7Pareto diagram purposes?Help focus on the most critical issues
    Separate the critical from the uncritical many
  8. 8Cost of Quality, is it a tool for Control Quality?NO. CoQ is part of Plan Quality
  9. 9Project completed. The client is very satisfied with the delivery and the features added by the team without the client asking. Is this a successful project?NO. Gold plating is not allowed

Información

Descripción
Certificate (Tips & Tricks) PMP Exam Prep Fichas sobre 6. Quality Management (Rita's), creado por Tuan Lam el 17/12/2015.
Creado por
Tuan Lam · dic 2015
Actualizado
1 jun 2016
Visitas
47
Valoración
Valoración media 5,0 de 5 (1 valoración)

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?