Project Controls - Exam II

Tyler Warford 77 preguntas Actualizado el 14 oct 2024

Hacer el test

Preguntas del test (77)

  1. 1change order is a written order to the contractor signed by the owner and the architect, issued after the contract execution
    1. AVerdadero
    2. BFalso
  2. 2notice window to submit a change order. time to tell the owner that an issue has been discovered.
    1. A48 hrs
    2. B24 hrs
    3. C1 week
    4. D12 hrs
  3. 3a change order signed by the contractor indicates the contractors agreement to contract price sum and contract time.
    1. AVerdadero
    2. BFalso
  4. 4What initiates a change?
    1. Acontractors, owner, or designer request.
    2. Bproposal request
    3. CRFI
    4. DError in Drawings
    5. EError in Specifications
    6. FDiffering site conditions
    7. GLack of product available
    8. HWeather
    9. IWorker strikes (union)
  5. 5Change Process
    1. ARecognition or initiation of a change
    2. Bproper contractual notice
    3. Cdetailed change analysis
    4. Destimate direct costs
    5. Eestimate indirect costs
    6. Foverhead and profit
    7. Gschedule impact & time extension
  6. 6change to work can have significant economic consequences for the contractors and subcontractors. therefore contractors must receive equitable compensation for accomplishing change work.
    1. AVerdadero
    2. BFalso
  7. 7anchoring is when a person relies heavily on the first piece of information received.
    1. AVerdadero
    2. BFalso
  8. 8a change order clause allows a GC to mark up a change order by 5% for the GC to make money. it is a common misconception that GC's make a lot of money on change orders
    1. AVerdadero
    2. BFalso
  9. 9revenue - cost = profit
    1. AVerdadero
    2. BFalso
  10. 10revenue and costs can be offset to balance the books.
    1. AVerdadero
    2. BFalso

Información

Descripción
Management Construction Test sobre Project Controls - Exam II, creado por Tyler Warford el 14/10/2024.
Idioma
English
Visitas
76
Historial
Creado el 14 oct 2024 · actualizado el 14 oct 2024
Etiquetas
constructionmanagement
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?