  1. Phase 1

  2. 2007

  3. Involved building rock armour on eastern end of the sea front

  4. Phase 2

  5. 2007

  6. Protecting the main town

    - shingle and sand beaches replenished and stabilised

    -rock armour extended (Beacon rocks) and realigned

    ( north wall rockery)

    - drainage systems improved ( prevent landslides

    reduce water build up

  7. £26 million

  8. Phase 3

  9. Meant to protect the west of Lyme Regis from lanslides

  10. never carried out- couldn't justify the high cost

  11. 19.5 million pounds

  12. 390 m of sea wall and rock armour

  13. protects roads going into the towm

  14. 2015