SAB11#47_49 Controlling Scope & Control Scope

  • It’s how you make sure that you make only those changes to the scope that you need to make, and that everyone is clear on what the consequences of those changes are.
  • The goal of Control Scope is updating the scope, plan, baseline, and WBS info.
  1. Work performance data

    • It tell´s how well the team is doing the job
  2. Work performance information

    • These updates are how you react to necessary scope changes that are approved through change control.
  3. Requirements traceability matrix

  4. Requirements documentation

  5. Project Management plan

  6. Updates to organizational process assets

  7. Project document updates

  8. Updates to the Project Management plan

  9. Change requests

  10. Variance analysis

    • This is where you constantly compare the information that you’re gathering about. the way the project’s going to affect your baseline.
    • A change is needed.
    • Create a change request.
    • Get the change approved.
    • Do variance analysis.
    • Replan the work.
    • Create a new baseline.

Information

Description
p Taller de Certificación de PMP Mind Map on SAB11#47_49 Controlling Scope & Control Scope, created by Omar Arce on 25/06/2016.
Created by
Omar Arce
Views
16
Rating

More on Control Scope

Feedback

What is it about?

What do you think of the new look?

How do you like it?