Planning introduction and planning techniques
Map content
Planning introduction and planning techniques
Why is planning important
- Communication
- Logistics
- Claims
- Legally bound
Engineering contract content
- Within two weeks of contractor submitting the work, a project manager either accepts or gives reasons why they are not
- Dates when contractor requires important information
- Float and seperately, time risk allowances
- Order and timing of operation
- Dates stated in the contract data or works info
- Other information required in the works info
- Health and safety requirements
- Method statement for each operation which identifies equipment/resources to contractor plans to use
Projects
- Poor stats
- 30% of construction is rework
- 40% of man power on site is wasted
- at least 10% of materials are wasted
- 40% of projects are completed late or over budget
- Main reasons for projects failing
- Lack of control over progress
- Insufficient measureables
- lack of communication with interested parties
- Lack of quality control
- Inadequate planning of resources
- Poor estimation of duration and costs
- lack of co-ordination of resources and activities
- Project is a temporary endeviour to create a unique product or service
- Planning is the process of preparing for the commitment of resources in the most effective fashion
- Programme is a diagram or list showing the work to be done with assosiated times
- Programme technique is the method chosen to produce a program
- planners task is to develop an achievable construction sequence within contractual sequence within contract required timings which fully relates to the contractors available resources
- Poor stats
RIBA plan of work
- Robust protocol which describes the activities involved in a construction project from appraising the clients requirements through to post construction
- 8 stages
- 2/ Preperation and brief
- 3/Concept design
- 4/ Developed design
- 5/ Technical design
- 1/ strategic definition
- 6/ Construction
- 7/ Handover and close out
- 8/ In use
Planning process
- Consultant
- Design phases
- Pre-construction planning (conception to construction)
- Health and safety planning
- Check client is aware of duties and a CDM coordinator has been appointed
- Provide info about remaining risks
- Provide info for health and safety file
- eliminate hazards and risks during design
- Environmental assesment planning
- Applying for planning permission
- Quality planning
- Design planning
- Health and safety planning
- Construction planning
- Tender planning
- Contractors
- Pre construction planning
- Conception to construction (pre tender/ contract planning
- Construction planning (actual site activities)
- Planning stages
- Pre-tender planning
- Pre contract planning
- Site layout planning
- Placing orders
- Requirements schedule
- Budgetary control proceedure
- Master programme
- Organisational structure
- Pre contract arrangements
- Consultant
Construction programming
- Programming steps
- Identify
- Sequence of tasks/ activities (from drawings)
- Quantities involved (from B of Q)
- Construction method (logistics)
- Risk
- Choice of construction plant (logistics)
- Calculate duration of activities
- Programme/ schedule the tasks/ activities
- Identify
- Programme duration
- Dependant on
- Resource availability
- sub contractors
- plant
- labour
- supervision
- resource output
- Resource availability
- Dependant on
- Programming techniques
- Gantt/ bar chart
- Network analysis (critical path method) (activity on arrow/ precedence diagrams)
- Programme evaluation and review technique
- line of balance
- time chainage
- Programming steps
Network analysis
- General
- Method of planning projects by analysisng them into their component activities and depicting these in a network form so as show their detailed relationships throughout the project
- Network used for optimising the utilisation of resources, progress reporting and control
- Techniques
- Activity on arrow
- Precedence
- Programme evaluation and review technique (PERT)
- Logical relationships
- What activities must be complete before this activity starts??
- What activities cannot start until this activity is completed??
- Which activities have no logical relationship with this activity and can take place together??
- Conventions
- 1/ Before an activity can begin, all preceeding activities must be completed
- 2/ Arrows imply logical precedence only. Length and direction are not sagnificant
- 3/ Events numbers must not be dublicated
- 4/ Any two events may be directly connected by one activity
- 5/ Networks can only have one start and one end date
- General
Critical path
- Shortest logical time to finish the project
- A continuous chain of events
- Forward and backward parries produce the earliest times (ET) and latest times (LT) for events
- Pros
- Relationship between activities are clear
- Very detailed for monitoring
- Cons
- Technical for client
- Changes require complete rework