  1. 1Task #1: Perform project assessment (Initiating)Evaluate the feasibility of the deliverables
    Based on: available information, lessons learned, meetings
  2. 2Task #2: Identify key deliverables (Initiating - New)Manage client expectations and direct the achievement of project goals
    Based on: business requirements
  3. 3Initiator/Sponsor?Create SOW, Business case and Contracts
  4. 4Business case?Business needs + cost-benefit analysis
    Description of what org is trying to get out of a project
  5. 5SOW?Narrative description of deliverables
    Business need
    Strategic plan
  6. 6Task #4: Identify high-level risks, assumptions and constraints (Initiating)Propose implementation strategy
    Based on: Expert, historical data, EEF, OPA
  7. 7Task #5: Participate in developing project charter (Initiating)Ensure project stakeholders are in agreement on its elements
  8. 8Process #1: Develop Project Charter (Initiating - Integration)Process #1: Develop Project Charter (Initiating - Integration)
  9. 9Project charter?Project is officially authorized
    High level requirements, assumptions, constraints
    Summary of milestones
    Business case
  10. 10Facilitation techniques?Techniques to get everyone on the same page
  11. 11Constraints?Main: Scope, Time, Cost
    Others: Resources, Quality, Risk
    One change can affect one or more constraints
  12. 12Who creates project charter?Project Initiator/Sponsor
    Can be delegated to PM
  13. 13Who signs the project charter?Project Initiator/Sponsor
  14. 14Should the project charter has all the details?NO. It should be broad enough so that no changes are needed for most little changes in the project
  15. 15Task #6: Obtain approval for project charter from sponsor (Initiating)Formalize the authority assigned to PM
    Gain commitment and acceptance for the project
  16. 16Stakeholders?Impacted by the outcome of the project.
  17. 17Stakeholders examples?Sponsor, client, seller, business partner, functional manager, ...
  18. 18Task #3: Perform stakeholder analysis (Initiating)Align expectations and gain support
  19. 19Process #2: Identify Stakeholder (Initiating - Stakeholder)Process #2: Identify Stakeholder (Initiating - Stakeholder)
  20. 20Stakeholder register?All details regarding identified stakeholders (assessment info, classification, ...)
  21. 21Stakeholder analysis technique?Identify interests, expectations, relationships and influence of stakeholders.
    Define approach strategy.
    Assess how key stakeholders react
  22. 22Why analyzing stakeholders?Build relationship to enhance project's chance of success.
    Align expectations and gain support
  23. 23Some classification models for stakeholders analysis?Power/Interest: auth vs lv of concern
    Power/Influence: auth vs lv of involvement
    Influence/impact: involvement vs ability to change project planning/exec
    Salience: Power vs Urgency vs Legitimacy
  24. 24Task #7 - Conduct benefit analysis with stakeholders (Initiating - New)Validate project alignment with organization strategy and expected business value
  25. 25Task #8 - Inform stakeholders of approved project charterEnsure common understanding of key deliverables, milestones and their roles and responsibilities

Informações

Descrição
Have all information regarding the project before starting
Criado por
Tuan Lam
Visualizações
54
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?