  1. 1In unit price contracts, the line item quantities specified in the contract are set by the A/E.
    1. ATrue
    2. BFalse
  2. 2Unit price contracts are most appropriate in projects when line item quantities cannot be forecast by the A/E with accuracy at the start.
    1. ATrue
    2. BFalse
  3. 3In the unit price contracts, the GC has the obligation to complete the job even if the value of the work done exceeds the contract value by 50%
    1. ATrue
    2. BFalse
  4. 4In unit price contracts, the GC has the obligation to complete the job regardless of the line item quantities being smaller or larger than the A/E's estimates, as long as the variation is between 15-25%.
    1. ATrue
    2. BFalse
  5. 5"In unit price contracts, the owner must keep a field force to check primarily the quantities produced by the GC but also the quality of the work done"
    1. ATrue
    2. BFalse
  6. 6A big advantage of the unit price contract is that the owner knows the final duration of the job right at the outset with certainty.
    1. ATrue
    2. BFalse
  7. 7A big advantage of the unit price contract is that the owner knows the final cost of the job right at the outset with certainty.
    1. ATrue
    2. BFalse
  8. 8If a lien goes through the court, foreclosure takes place. The property is sold at auction, and the proceeds are used to pay debtors.
    1. ATrue
    2. BFalse
  9. 9A mechanics lien can be filed by a S/C if the GC does not pay the S/C.
    1. ATrue
    2. BFalse
  10. 10A mechanic's lien is an effective and much preferred dispute resolution method.
    1. ATrue
    2. BFalse

Information

Description
Engineering Quiz on Exam Practice , created by Nick Thompson on 03/05/2018.
Language
English
Views
0
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?