1You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the followin topics should NOT be included in the test progress report?
- AProduct risks which have been mitigated and those which are outstanding
- BRecommendations for taking controlling actions
- CStatus compared against the started exit criteria
- DDetailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved
2Explain how the above mentioned report may differ from a report that you produve for the project manager, who is a test specialist. Select TWO items from the following options that can be used to report to the project manager and woild not be included in a report to senior management.
- AShow details on effort spent
- BList of all outstanding defects with their priority and severity
- CGive product risk status
- DShow trend analysis
- EState recommendations for release
3Consider the typical objectives of testing. Which of the following metrics can be used to measure the effectiveness of the testing process in archieving one of those objectives?
- AAverage number of days between defect discovery and resolution
- BPercentage of requirements covered
- CLines of code written per developer per day
- DPercentage of test efforts spent on regression testing
4You have been given responsibility for the non-functional testing of a safety-critical monitoring and diagnostics package in the medical area. Which of the following would you least expect to see addressed in the test plan?
- AAvailability
- BSafety
- CPortability
- DReliability
5Since the system is in the medical domain and therefore in the safety critical area, testing needs to be rigorous and evidence is required that the system has been adequately tested. Identify THREE measures that would typically be part of the test approach in this domain and which are not always applicable in other domains!
- AHigh level of documentation
- BFailure Mode and Effect Analysis (FEMA) sessions
- CTraceability of requirements
- DNon-functional testing
- EMaster test planning
- FTest design techniques
- GReviews
6A test log is one of the documents that need to be produced in this domain in order to provide evidence of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing factor for the level of detail of the test logs being produced?
- ALevel of test execution automation
- BTest level
- CRegulatory requirements
- DExperience level of testers
7Considerable attention will be given in this project to defining exit criteria and on reporting back on their status. Which combination of TWO exit criteria from the list woild be best to use?
I. Total number of defects found
II. Percentage of test cases executed
III. Total test effort planned versus total actual test effort spent
IV. Defect trend (number of defects found per test run over time)- A(i) and (ii)
- B(i) and (iv)
- C(ii) and (iii)
- D(ii) and (iv)
8Section 2
Details: Topic 2, Scenario 2 "Reviews"
A software development organization wants to introduce some specific improvements to its test process. Currently, most of their testing resources are focused on system testing. They are developing embedded software, and do not have a simulation environment to enable them to execute software modules on the development host. They have been advised that introducing inspections and reviews could be the most appropriate step forward.
Identify the THREE types of formal peer reviews that can be recognized.- AInspection
- BManagement review
- CWalkthrough
- DAudit
- ETechnical review
- FInformal review
- GAssessment
9As part of the improvement program, the organization is also looking at tool support.
Which type of tool could be used to ensure higher quality of the code to be reviewed?- AReview tool
- BTest execution tool
- CStatic analysis tool
- DTest design tool
10What is the main reason why reviews are especially beneficial in the above-mentioned scenario?
- AThey ensure a common understanding of the product
- BThey find defects early
- CThey enhance project communication
- DThey can be performed without exercising the code
11The introduction of reviews and inspections has often failed as process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail
- AProcess ownership and experienced moderators who drive the inspection process.
- BManagement support
- CTraining of those involved
- DThe availability of stands and processes
- EUsage of a more traditional software development lifecycle
- FAlignment with software process improvement
- GUsing a reference model, e.g. TMMi
12IEEE 1028 also defines "management review" as a type of review. What is the main purpose of a management review?
- AAlign technical concepts during the design phase
- BEstablish a common understanding of requirements
- CProvide independent evaluation of compliance to process, regulations, standards etc.
- DTo monitor progress, assess the status of a project, and make decisions about future actions.
13Which of the following is an example of testing as part of the requirements specification phase?
- AA requirements review meeting
- BA business analyst eliciting requirements
- CPerforming acceptance tests against requirements
- DA test report showing requirements coverage
14Section 3: Sec Three (14w 15)
Details: Topic 3_ Scenario 3 "Tool Selection and Implementation" Your company is considering whether or not to purchase a test tool suite from a respectable vendor. Your manager has searched the internet for comparable products but none of them meets his specific requirements. A tool demonstration has been arranged for next week and your team has been invited to attend, The tool suite consists of a test management tool, test execution tool and a requirements management tool. There is the possibility of adding a performance testing tool at a later stage. You have decided to attend the demo but raise some issues beforehand regarding expectations.
Select THREE issues from the options provided that should at least be raised.- AHas there been sufficient comparison of tools?
- BWhat are the problems we are trying to address?
- CDo we have a set of tool requirements to validate the tool against?
- DHow will the implementation be organized?
- EWhich project will be selected to perform the tool pilot?
- FIs customized training available?
- GHow will the change process be managed?
15Which of the following would you least expect to form part of the analysis of initial tool costs?
- AIntegration with other tools
- BLearning time required to use the new tool
- CTool portability
- DEvaluation of suitable tools
16Section 4: Sec Four (16 to 24)
Details: Topic 4. Scenario 4. V2 "Test Management Tool"
The project situation alter 1 1 months is: - The first increment was released one week late but contained sufiicient functionalit) to be declared fit for purpose', However. there were 20 outstanding incidents deferred to increment two. - The amount of voluntary overtime worked PV the test team has reduced the second Increment slippage to just 3 weeks. - There is talk of reducing the scope of requirements. The purpose of this is to first deliver the application with support for manual testing and then to provide a delivery “
Which of the following are valid reasons for adopting a different life cycle (from the V model), for increments after the first year?
i. We do not have a clear understanding of the requirements from a customer perspective.
ii. We see the risk of delivering requested functionality late as being higher than the risk of delivering a lower quality product.
iii. We do not have a budget for additional regression testing which is needed to ensure that existing functionality is not compromised by future iterations.
iv. The company test strategy does not fit well within the V life cycle model.- A(i) and (ii)
- B(i) and (iv)
- C(ii) and (iii)
- D(ii) and (iv)
17Which of the following is a characteristic of good testing in any life cycle model?
- AAnalysis and design of tests begins as soon as development is completed.
- BSome, but not all, development activities have corresponding test activities.
- CEach test level has test objectives specific to that level.
- DAll document reviews involve the development team.
18Which of the following would you expect to see in the master test plan?
- AA description of how the test cases are cross—referenced to requirements in the test management tool.
- BA detailed identification of the resources that will early out structural testing in the first iteration.
- CThe test approach that will be applied at system integration testing.
- DA list of the names of the testers who will early out the performance testing for the filial iteration.
19Which of the following would be the most significant input to estimating the time to cany out the specified testing tasks?
- AThe skills and experience of developers to correct the failures.
- BThe standards used for the requirements specification.
- CThe metrics recorded from testing the capture-replay tool.
- DThe number of testers in the company and their grade.
20Which of the following would be the TWO most appropriate examples of ent1y criteria documented in the system integration test plan?
- AThe percentage of decision coverage achieved during 1mit testing.
- BThe availability of the latest version of the capture-replay tool (for testing the interface with the newly developed test management tool).
- CThe sign-off of a performance test software release note (test item transmittal report) by both development and testing showing that system performance meets the specified acceptance criteria.
- DThe percentage of acceptance test procedures scheduled for execution.
- EThe percentage of requirements coverage achieved during system integration test.
21Which test management control option is most appropriate to adopt under these circumstances?
- AIntroduce mandatory evening and weekend working to retrieve the 3 week slippage.
- BReconsider the exit criteria and review the test plan in the context of the current situation.
- CAdvise the user community regarding the reduced scope of requirements and the additional incremental delivery.
- DArrange a meeting with the user community representatives to discuss the user interface.
22Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk?
- AThe concerns over the user interface may lead to changes to the interface which cannot be implemented by development in time for the second test iteration.
- BThe concerns over the user interface raises the likelihood of a risk in that area and increases the amount of test effort needed for the user interface, thereby limiting the test effort available for other parts of the test management tool.
- CThe delivery of the application without the interface changes may upset the user community.
- DThe method used for test estimation is not accurate enough and hence the money spent on testing exceeded its budget.
23Which of the following is least likely to be used as a technique to identify project and product risks?
- ABrainstorming
- BInspections
- CExpert interviews
- DIndependent assessments
24Which of the following is a project risk mitigation step you might take as test manager?
- ATesting for performance problems
- BHiring a contractor after a test analyst leaves the company
- CArranging a back-up test environment in case the existing one fails during testing
- DPerforming a project retrospective meeting using the test results after each increment
25Section 5: Sec Five (25 to 29) Details: Topic 5, Scenario 5, V2 "Human Resource System" For the first increment of the new enterprise HR product you have performed a product risk analysis using the FMEA method. Five risk items have been identified and the likelihood and impact have been scored using scoring tables. This has resulted in the following scores.
You have been asked to mite a testing strategy for the company. Which statement best exp1ains how risk can be addressed within the testing strategy?
- AA test strategy should address identified generic product risks and present a process for mitigating those risks in line with the testing policy.
- BA test strategy identifies the specific product for a project risk and defines the approach for the test project.
- CA test strategy is derived from the test policy and describes the way risk assessments are performed in projects.
- DA test strategy is the result of a project risk analysis and defines the approach and resources for testing.
26In addition to risk, identify TWO other components of a testing strategy.
- AThe entry and exit criteria for each test phase
- BTest training needs for the project resources
- CThe test design techniques to be used
- DTest performance indicators
- EThe test schedule
27Pan of the testing strategy indicates that you are going to be using systematic test design techniques. Your manager has asked that you present the main advantages of using these techniques at the next board meeting. Identify THREE main benefits of using systematic test design techniques within this company.
- AEasier to quickly adapt testing to changing requirements compared to experienced- based testing
- BTargets certain types of faults
- CWill guide experienced testers to find defects
- DProvides a way to differentiate depth of testing based on product risks by using different techniques
- EMore enhanced documentation and therefore higher repeatability and reproducibility
- FWill make non-systematic testing redundant
- GWill reduce the need for early reviews
28What is the Risk Priority Number for risk item number 2?

- A16
- B2
- C1
- D63
29What would be a test approach regarding the test design techniques to be applied that would fit an item with the highest risk?
- AComponent testing: decision testing; System testing: exploratory testing
- BComponent testing: decision testing; System testing: decision table testing
- CComponent testing: statement testing; System testing: equivalence partitioning
- DComponent testing: statement testing; System testing: decision table partitioning
30Which of the following is a benefit of independent testing?
- ACode cannot be released into production until independent testing is complete.
- BTesting is isolated from development.
- CIndependent testers find different defects and are unbiased.
- DDevelopers do not have to take as much responsibility for quality.
31A numnber of options have been suggested for the level of independence to be employed for the testing on the next project, and are shown below.
i. External test specialists perfmm non-functional testing.
ii. Testing is outsourced.
iii. Testing is carried out by the developer.
iv. A separate test team carries out the testing.
v. Testing is performed by the business.
vi. Testing is performed by a different developer.
Which of the following orders the above in a correct order of independence?- Ai, ii, iv, vi
- Bii, i, V, vi
- Cii, v, i, iii
- Di, iv, v, Vi
32Which of the following is a valid drawback of independent testing?
- ADeveloper and independent testing will overlap and waste resources.
- BDevelopers loose the sense of responsibility and independent testers may become a bottleneck.
- CIndependent testers need extra education and always cost more.
- DIndependent testers will become a bottleneck and introduce problems in incident management.
33Based on the information given in the scenario, identify how the team could be improved most effectively?
- Aby providing training 1n the payroll domain
- BBy providing a workshop on test design techniques
- CBy providing specific training on the systems being tested
- DBy providing training on reviewing requirements
34Which of the following team roles would be most appropriate to enhance the team and why?
- AA person with the ability to complete tasks
- BA quality assurance officer
- CA person with in-depth technical skills
- DA person who brings new ideas to the team
35You are considering involving users dining test execution. In general. what is the main reason for involving users during test execution?
- AThey are a cheap resource
- BThey have good testing skills
- CThis can serve as a way to build their confidence in the system
- DThey have the ability to also focus on invalid test cases
36In addition to introducing the new team member, you have decided to raise motivation. Which of the measures listed below would be the best measure to take in order to increase the motivation of the team?
- AProvide more time for testing in the schedule
- BAllow people to take some time off
- CIntroduce entry criteria to the testing phase
- DOrganize a meeting with senior management in which they address the importance of good testing for this project
37Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status?
- ACriteria A : OK, Criteria B : OK, criteria C : OK
- BCriteria A : NOT OK, Criteria B : NOT OK, Criteria C : OK
- CCriteria A : OK, criteria B : NOT OK, criteria C : NOT OK
- DCriteria A : NOT OK, Criteria B : NOT OK, criteria C : NOT OK
38You have investigated different possibilities and selected four of them to present to IT management. Which of the proposals will you most likely give your highest recommendations?
- AInsourcing of test automation based on an offer from a local company ABC that has people who are specialists in system level capture-replay automation tools and they also do regular training courses in test automation methods and tools. They can then work closely with Vicki.
- BOutsourcing of test automation based on an offer from an Asian company, AsiaAutoTest, which has people who are specialists in system level capture-replay automation tools. They also offer training and besides they offer to inn and maintain the regression tests in the future.
- CInternal offer from the development department of XYZ to create the regression package using CppUnit as test automation tool. One of the development groups have very good experiences in automating unit tests, and they are willing to do training as well.
- DSolution from a tool vendor offering to educate two test team members in the use of their easy- to-use test automation capture replay tool over the first 3 month and based on that build the regression test suite. In addition to Vicki, Steve is the only one that has time available to be educated.
39Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing?
- ATest environment more complex
- BDefine expectation for tasks and deliverables
- CClear channels of communications
- DPossibly different cultures
- ETesting of non-functional requirements
- FAudit hail from requirements to test cases
- GApplying test automation
40Section 7: Sec Seven (40 to 43) Details: Topic 7, Scenario 7 "Test Estimation" You have been contracted to manage the acceptance testing of a new computer-based reservation system for a travel agency. You have provided an approximate budget estimate for the testing project based on previous experience with similar sized projects. However, the management of the parent company of the travel agency will not commit to the budget until detailed cost estimates are provided. The reservation system is being developed by a third party However, detailed specifications of the software are available, as well as an estimate of the total effort that will be spent in developing the software. The software is to be delivered in four increments, and the functionality to be delivered in each increment has already been agreed on.
Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project.- ATest planning test case preparation and test execution for each of the four iterations
- BWork should be explicitly allocated to test completion, test management, installation and to training on using the system
- CActivities to deploy the system in the user environment
- DRegression testing in the second, third and fourth iterations
- EDevelopment activities for unit and integration testing
- FReviews on requirements documentation
- GDefining test environment requirements for system testing
41In general which pan of the testing activity is most difficult to estimate?
- ATest planning
- BTest execution
- CTest management
- DTest design
42In general, why is it NOT a good idea to estimate the testing effort based only on a percentage of development effort? Identify THREE valid reasons.
- AThe quality of the development estimate may be poor.
- BIn general bottom-up estimation is always better than top—down estimation.
- CThe percentage based technique only applies to the V life cycle model.
- DUsing the same percentage every time does not address the level of risk of the application to be tested.
- EThe maturity of the organization, e.g. the quality of the test basis, quality of development testing, configuration management, availability of test tools, also influence the effort needed for testing.
- FIt builds on large set of historical data
- GThe result is almost always a too low estimate for the required test effort
43Which aspect in the test estimate is the main risk in this project?
- AQuality of the specification
- BAvailability of end-users
- CThe costs of hardware and tools
- DUnknown input quality due to third party development
44Section 8: Sec Eight (44 to 49)L1El Details: Topic 8, Scenario 8, V2 "Test Proems Improvement' You have raised the issue that improving the testing process is also dependent on the status of the software development process.
Model characteristics: Which THREE of the below mentioned characteristics relate to TMMi?- A5 maturity levels
- BFocused on higher level testing
- C20 key areas
- DHighly related to CMMI
- EContinuous model
- FStaged model
- GFocused on component and integration testing
- HIs build around 12 critical testing processes
45The test improvement project will take place in an organization developing a safety- critical avionics application. Which one of the following standards do you believe would be most appropriate to take into account for compliance during your assignment?
- AISO 9126
- BIEEE 829
- CBS 7925/2
- DDO—178B
46Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi?
- AIf the scope of test performance improvement covers all test levels, TMMi is preferred since TPI focusses mainly on black-box testing.
- BIf the organization is already applying CMMI, TMMi may be preferred since it has the same structure and uses the same terminology. TMMi addresses management commitment very strongly and is therefore more suitable to support a top-down improvement process.
- CTPI is much more a bottom-up model that is suitable for addressing test topics for a specific (test) project.
- DTMMi can only be used with the traditional V model,whereas TPI can be used with all types of software life cycles.
47A test assessment has been carried out using the selected model as a reference fi'amework. A number of recommendations have been identified and you are asked to prioritize them. Based on your knowledge of the project, you are expecting severe resistance to change. Which of the following would be the most important selection criterion for defining the priority of the recommendations?
- ASynchronized with the overall long-term organizational strategy
- BDefined according to the maturity model used
- CMost Visible to stakeholders
- DLow costs actions first
48During test process improvement it is recommended to use standards where possible. Standards originate from various sources and they cover different subjects in relation to testing Pick TWO sources of software standards, useful to software testing from the ones mentioned below.
- AISO 9126-1 ‘Software engineering- Product quality Part 1: Quality model’ is an international standard, that provides a basis on which to define quality assurance solutions.
- BISA 4126-1 ‘Software engineering- Product quality Part 1: Quality model’ is an international standard, that provides a basis on which to define quality assurance solutions.
- CBS-7925-2 ‘Software testing. Software component testing is a national standard used internationally. It covers a number of testing techniques that may be useful both on component testing level and on system testing level.
- DSY—395-Ol ‘Standard for East Coast Hospital software’ is a regional standard adapted from a national one. Besides hospital software, this standard ought to be used also by other types of software system in the region.
- EIEEE 829 ‘standard for software test documentation’ is an international standard to be following mandatory by all testing origination regardless of lifecycle models.
49Which of the following phases in the flu1da1nental test process is considered to deliver a document which can be used as a major input for test process improvement?
- ATest planning and control
- BTest implementation & execution
- CEvaluating exit criteria and reporting
- DTest project closure
50Section 9: Sec Nine (50 to 53) Details: Topic 9, Scenario 9 "Test Management Doclunentation"
A software house is concerned about the number of defects fotu1d in software released to its customers. They are stalting to plan a new software product. In the past, releases have often been stopped due to poor plamiing and too many defects found dining high level testing. You have been recluited to the newly created position of test manager and asked to develop a test strategy, manage the testing of the project and organize the resources needed to cany out the testing.
Which THREE activities would be valid steps during the development of the test strategy?- AIdentify test staff members that will be involved in the system test
- BDefine test career paths
- CUnderstand the software development life cycle used by the software house
- DAssess the testing that needs to be done to minimize the risks
- EIssue the test strategy document for review
- FDefine a master test plan template
- GPerform a project risk analysis
51As pan of the test strategy, ent1y and exit criteria will be defined for each test level. Which is NOT a Valid reason for using ent1y and exit criteria?
- AThe expectation is that development testing is not adequate.
- BExit criteria are used to decide on when to stop testing.
- CEntry and exit criteria are a principal way for getting adequate resources.
- DUsing entry and exit criteria will prevent software that is not or poorly tested from going to the next test level.
52Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test strategy document
b. The overall estimated costs, timescales and resource requirements
c. A detailed schedule of testing activities
d. The development deliverables to be tested
e. Which test staff members (names) will be involved and when
f. Level of requirements coverage achieved
Which THREE of the above mentioned characteristics relate to the master test plan?- Aa
- Bb
- Cc
- Dd
- Ee
- Ff
53Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a. Any deviation from the procedures described in the test
b. strategy document
c. The overall estimated costs, timescales and resource
d. requirements
e. A detailed schedule of testing activities
f. The development deliverables to be tested
g. Which test staff members (names) will be involved and when
h. Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan?- Aa
- Bb
- Cc
- Dd
- Ee
- Ff
54Section 10: Sec Ten (54 to 60) Details: Topic 10, Scenario 10, V3 "Online Application" The cancellation of a current major development project has released resources. The development manager has decided to respond to his own request to tender and has proposed an in-house development with the use of a Rapid Application Development (RAO) approach.
Which of the following product risks would be most effectively addressed just by static testing?- AIn the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.
- BThe application takes too long to process a request for additional cover.
- CThe test cases do not cover the key requirements.
- DThe successful bidder may not deliver all the required functionality on time.
55The development manager is managing the review of the responses received from bidders, and has asked the in—house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate?
- AThe bidder’s test policy should enforce that incident management fully conforms to IBEE 1044.
- BThe bidder’s project strategy shows that the data content of all the test environments conforms to EU standards.
- CThe bidder’s test plan shows that the application will be delivered for acceptance in six months time.
- DThe bidder’s project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.
56Which one of the following estimation approaches is appropriate at this stage of the project?
- ACreate an estimate based on the function point analysis technique and test point analysis
- BCreate an estimate based on the complexity of the code
- CCreate an estimate based on the credentials of the successful bidder
- DCreate an estimate based on a percentage of the development effort
57Why might a RAD approach he a better option for the test manager rather than a sequential development?
- AIt will extend the development team’s abilities and enhance future delivery capabilities.
- BIt will allow the marketing, clerical and testing staff to validate and verify the early screen prototypes.
- CTime-box constraints will guarantee code releases are delivered on schedule.
- DMore time can be spent on test execution as less formal documentation is required.
58Which of the following is NOT a typical key challenge for testing in a RAD based development approach?
- ARe-usable test scripts for (automated) regression testing
- BProject management and control
- CNo complete requirements specification
- DTime-boxing
59As a result of the RAD based development approach, the test manager has decided to change the risk mitigation approach. Which test technique might be most appropriate to use?
- ADecision Table Testing
- BBoundary Value Analysis
- CError Guessing
- DExploratory Testing
60The business has asked for a weekly progress report. Which of the following would be appropriate as a measure of test coverage?
- APercentage of business requirements exercised
- BPercentage of planned hours worked this week
- CPercentage of countries that have test scenarios
- DPercentage of test iterations completed
61Regarding the process described above, what is the most important recommendation you would make using IEEE 1044 as a guide?
- ANo priority or severity assigned
- BIncident numbering is manual rather than automated
- CNo mentioning of reproducibility
- DNo classification on type of incident
62Section 12: Sec Twelve (62 to 65) Details: Topic 12, Scenario 12 “Automatic Teller Machine (ATM)”
You are a test manager in charge of integration, system and acceptance testing for a bank. You are working on a project to upgrade an existing ATM to allow customers to obtain cash advances from supported credit cards. The system should allow cash advances from €20 to €500, inclusively, for all supported credit cards. The supported credit cards are American Express, VISA, Eurocard and Mastercard. In the master test plan the following items are listed in the section named “items and/or features to be tested”:
I All supported credit cards
II Language localization
III Valid and invalid advances
IV Usability
V Response time
Relying only on the information provided in the scenario, select the TWO items and/or features for which sufficient information is available to proceed with test design.- AAll supported credit cards
- BLanguage localization
- CValid and invalid advances
- DUsability
- EResponse time
63Continuing with the Scenario described in the previous question, which of the following topics would you need to address in detail in the master test plan?
- AAn approach to regression testing
- BA list of boundary values for “advance amount”
- CA description of dependencies between test cases
- DA logical collection of test cases
64Given the following figures for the testing on a project, and assuming the failure rate for initial tests remains constant and that all retests pass, what number of tests remain to be run?
Test planned: 1000
Initial tests run: 500
Initial tests passed: 350
Retests run: 80- A700
- B720
- C784
- D570
65Given is the following defect removal chart reported at the end of system testing - showing total defects detected and closed defects (fixed and successfully retested). A number of open defects are classified as critical. All tests have been executed.
Based on the chart above, what is the most appropriate next test phase?
- AAcceptance testing to verify the business process
- BAcceptance testing to verify operational requirements
- CRequirements testing as pan of testing regulatory compliance
- DAnother system test cycle to verify defect resolution
Information
- Description
- Testing Quiz on Advanced TM, created by szando on 12/04/2015.
- Author
- szando
- Language
- English
- Views
- 6
- Tags
- Rating
- No ratings yet Rate this quiz