Help shape GoConqr. What should we add next?

Quiz

Managing - Chapter 9

Emma Ghini 44 questions

Take the quiz

Questions in this quiz (44)

  1. 11. In CPM, __________ are specified.
    1. Aa) exact levels of uncertainty associated with activities
    2. Bb) an expected time, a crash time, and the standard deviation time
    3. Cc) three costs
    4. Dd) two activity times and two costs
  2. 22. The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are __________.
    1. Aa) probabilistic
    2. Bb) crashed
    3. Cc) normal
    4. Dd) dynamic
  3. 33. If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will __________.
    1. Aa) not be necessary to crash any activities in projects
    2. Bb) be necessary to crash the last few activities of most projects
    3. Cc) be completed on time and within budget
    4. Dd) be completed as per schedule
  4. 44. The formula for computing the cost/time slope for each activity that can be crashed is __________.
    1. Aa) (crash cost + normal cost) / (crash time + normal time)
    2. Bb) (crash cost - normal cost) / (crash time - normal time)
    3. Cc) (normal cost + crash cost) / (normal time + crash time)
    4. Dd) (normal cost - crash cost) / (normal time - crash time)
  5. 55. Economically speaking, crashing a project creates a technology change in the __________ for an activity.
    1. Aa) deliverable demand function
    2. Bb) production function
    3. Cc) audit function
    4. Dd) deliverable supply function
  6. 66. The __________ technique overlaps the design and builds phases of a project to expedite its completion.
    1. Aa) crashing
    2. Bb) fast-tracking
    3. Cc) leading
    4. Dd) blitzing
  7. 77. The points between the extreme points of the relationship between time use and resource use represent __________.
    1. Aa) time constrained projects
    2. Bb) resource constrained projects
    3. Cc) alternative trade-offs between time and resources
    4. Dd) a non-feasible solution space of trade-off alternatives related to time and resource use
  8. 88. The two fundamental approaches to constrained allocation problems are __________.
    1. Aa) heuristic approaches and rules of thumb
    2. Bb) linear programming approaches and optimization models
    3. Cc) heuristic approaches and optimization models
    4. Dd) goal programming and trial and error
  9. 99. The __________ approach to constrained resource scheduling problems is the only feasible method of attacking large, nonlinear, complex problems that tend to occur in the real world of project management.
    1. Aa) goal programming
    2. Bb) heuristic
    3. Cc) optimization modeling
    4. Dd) linear programming
  10. 1010. Most heuristic solution methods start with the __________ and analyze resource usage period by period, resource by resource.
    1. Aa) GERT schedule
    2. Bb) Gantt chart
    3. Cc) PERT/CPM schedule
    4. Dd) Master schedule

Information

Description
Managing Managing Quiz on Managing - Chapter 9, created by Emma Ghini on 11/01/2021.
Language
English
Views
2
Tags
managing
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What should we add next?