CHL Chapter 18 Quiz

Description

Iahcsmm Sterile Processing (CHL Exam) Quiz on CHL Chapter 18 Quiz, created by william Hoover on 10/05/2017.
william Hoover
Quiz by william Hoover, updated more than 1 year ago
william Hoover
Created by william Hoover almost 7 years ago
210
2

Resource summary

Question 1

Question
A request made to prospective architects,contractors/builders, suppliers, or others to learn the price of a product or service
Answer
  • Request for Proposal
  • Bid Request
  • Construction Estimate
  • Contractor Statement

Question 2

Question
An individual or business that signs a contract to perform part of the project that is the responsibility of the contractor
Answer
  • Internal Contractor
  • Secondary Contractor
  • Back-Up Contractor
  • Sub Contractor

Question 3

Question
A multi-disciplinary process that focus's on reducing risk from infection throughout planning, design, and construction (including renovation) activities undertaken by a healthcare facility
Answer
  • Failure Mode Effect Analysis (FMEA)
  • Infection Control Risk Assessment (ICRA)
  • Requested Proposal Plan (RPP)
  • Construction Proposal Plan (CSP)

Question 4

Question
The cost to acquire or make improvements to a long-term asset such as a building, property, or equipment
Answer
  • General Fund Acquisition
  • General Fund Expenditure
  • Capital Expenditure
  • Capital Acquisition

Question 5

Question
An unlicensed person who typically plans changes that do not relate to regulatory (building code) requirements
Answer
  • Designer
  • Architect
  • Draftsman
  • Contractor

Question 6

Question
A licensed professional who focuses on the aesthetic design of buildings and spaces, structures, mechanical systems, acoustics, regulatory, and other requirements needed to make buildings useful and safe for their occupancy
Answer
  • Draftsman
  • Architect
  • Designer
  • Contractor

Question 7

Question
The act of purchasing a product or service from an external provider that could alternatively be provided by the facilities own employees
Answer
  • PRN Contract
  • Sub-Contract
  • Rental
  • Outsource

Question 8

Question
A revision to a construction purchase order issued by a buyer to a contractor or service provider
Answer
  • Request for Revision
  • Change Order
  • Contractor Revision
  • Designer Change

Question 9

Question
An initial step in project planning is to form a ______ that includes physicians, care givers, central service leaders, department managers, technicians, and infection prevention specialists
Answer
  • Strategic Project Planning Team
  • Infection Control Team
  • Patient Protection Team
  • Environmental Audit Team

Question 10

Question
A study that considers safety concerns applicable to the environment, employees, and community
Answer
  • Feasibility Study
  • Patient Impact Study
  • Environmental Impact Study
  • Infection Control and Waste Impact Study
Show full summary Hide full summary

Similar

CHL Chapter 4 Exam
william Hoover
CHL Chapter 3 Quiz
william Hoover
CHL Chapter 7 Quiz
william Hoover
CHL Chapter 5 Exam
william Hoover
CHL Chapter 6 Quiz Exam
william Hoover
CHL Chapter 14 Quiz
william Hoover
CHL Quiz chapter 11
william Hoover
CHL Chapter 8 Quiz
william Hoover
CHL Chapter 20 Quiz
william Hoover
CHL Chapter 16 Quiz
william Hoover
CHL Chapter 10 Quiz
william Hoover