PMC 100 - Week 1,2,3 Revision Quiz

waynejonesjnr 9 questions

Take the quiz

Questions in this quiz (9)

  1. 1A _______________ is a temporary endeavor undertaken to create a unique
    product, service, or result.
    1. AProgram
    2. BProcess
    3. CProject
    4. DPortfolio
  2. 2Which of the following is not an attribute of a project?
    1. Aprojects are unique
    2. Bprojects are developed using progressive elaboration
    3. Cprojects have a primary customer or sponsor
    4. Dprojects involve no uncertainty
  3. 3Which of the following is not part of the triple constraint of project
    management?
    1. Ameeting scope goals
    2. Bmeeting time goals
    3. Cmeeting communications goals
    4. Dmeeting cost goals
  4. 4_______________ is the application of knowledge, skills, tools and techniques
    to project activities to meet project requirements.
    1. AProject management
    2. BProgram management
    3. CProject portfolio management
    4. DRequirements management
  5. 5Project portfolio management addresses _______________ goals of an
    organization, while project management addresses _______________ goals..
    1. Astrategic, tactical
    2. Btactical, strategic
    3. Cinternal, external
    4. Dexternal, internal
  6. 6Several individual housing projects done in the same area by the same firm
    might best be managed as part of a _______________.
    1. Aportfolio
    2. Bprogram
    3. Cinvestment
    4. Dcollborative
  7. 7What is the certification program called that the Project Management Institute
    provides?
    1. AMicrosoft Certified Project Manager (MCPM)
    2. BProject Management Professional (PMP)
    3. CProject Management Expert (PME)
    4. DProject Management Mentor (PMM)
  8. 8An individual - group - or organization who may affect - be affected by - or perceive itself to be affected by a decision - activity - or outcome of a project - program - or portfolio.
    1. Arisk mitigation
    2. Bstakeholder
    3. Ctotal float
  9. 9Which of the following best describes "fast-tracking"?
    1. AOne phase finishes before the next starts.
    2. BA phase starts before the previous phase is
      completed.
    3. CPlanning for the next phase is done while the previous
      phase is being executed.

Information

Description
Source 1 - http://web.augsburg.edu/~schwalbe//ipm3ch1.pdf