Risk & Uncertainty

Hoa Truong English

Map content

Risk & Uncertainty

  1. 'disaster' projects

    • fail 2 out of
      • 1. >40% cost growth
      • 2. >40% time slippage
      • 3. produce <50% than 1st year plan
    • 1/8 major project -> disaster
    • the bigger, >important project gets -> >likely -> disaster
  2. problem: business outcome not up to expectations/ possibilities

    • better decisions
      • accurate = unbiased + appropriate range
      • uncertainty assessment & response
      • non-intuitive
      • lead to better performances
      • supported by petrol. geoscientist, engineers, economist
    • Reasons
      • under-estimate: uncertain factors (no. & magnitude), complexity of uncertainties' relationships, consequences
      • systematic biases: mental short-cuts
      • planning fallacy
        • spin success scenarios, overlook potential of mistake & miscalculations - believe in outcomes: unlikely come in budget/time - unexpected returns
      • proceed on beliefs, judgments of P but not uncertainty
  3. UNCERTAINTY

    • not remove but accurately assess
    • uncertainty assessment
      • priority
        • 1. accurate (unbiased)
          • 2. uncertainty reduction (> data,time,detail, analysis)
            • 3. stop when further analysis don't change decision
    • knowing when enough is enough
    • defin: not knowing if the statement/ even is true/false
    • predictions: range/list possible outcomes
    • language of uncertainty
      • probabilities
        • scientific way to deal with uncertainty
        • systematically quantify beliefs about uncertainty
        • rules pf probability -> how to reason logically under uncertainty
        • chance of possible outcomes occur
        • views
          • Classical (Theoretical)
            • no. outcomes represent / total no. possible outcomes (3 red, 7 green -> P(red)=3/10)
          • Relative Frequency
            • probability ESTIMATED from sample data ASSUME identical events (15/20 sample wells: dry -> P(dry)=75%)
            • bigger sample -> more accurate P
          • Subjective
            • personal degree of belief of likelihood of a future event occur
            • can based on data, pass similar occurances
            • Oil & industry ( exist: unknowable possible outcomes, distribution, parameters)
    • function of not a system but what known about the system, function of personal state of information
    • RISK
      • possible -ve consequence of uncertainty
    • OPPORTUNITY
      • possible +ve consequence of uncertainty
  4. Variability

    • distribution that describes variability of a natural phenomenon is not usually appropriate to describe uncertainty of a single occurance
  5. Ambiguity

    • imprecise (unclear) definition of event/ statement/ outcome (wine-drinker)
    • must be removed from uncertainty statement before assign probability
  6. often estimate in 80% Confidence Intervals

    • goal is set a range narrow enough to contain actual value >8/10times on ave
  7. Bias

    • optimistic on central value (mean)
    • width of distribution

Information

Description
Mind Map on Risk & Uncertainty, created by Hoa Truong on 19/11/2015.