1The INCOSE Handbook has been written to be consistent with ISO/IEC/IEEE 15288 in order to ensure it can be applied to (choose 3):
- ASystem-of-systems
- BMedical systems
- CProducts
- DServices
- EBuisness
- FAvionics
2ISO/IEC/IEEE 15288 provides (choose 2):
- APractices necessary to execute processes
- Bactivities necessary to execute processes
- Cgeneric top-level process descriptions
- Dgeneric top-level process requirements
3The number of process groups identified by ISO/IEC/IEEE 15288 is:
- A3
- B4
- C5
- D6
4The INCOSE Handbook is ready to be applied to your company or project
- ATrue
- BFalse
5The 4 process groups from ISO/IEC/IEEE 15288 that support systems engineering include (choose 2):
- AOrganizational project-enabling Processes
- BWork Breakdown Processes
- CTechnical Processes
- DProject Initiation
6The 2 Agreement Processes are:
- AContract Management
- BAcquisition
- CSupply Chain Management
- DSupply
- ENegotiate
7The 4 process groups from ISO/IEC/IEEE 15288 that support systems engineering include (choose 2):
- ALife Cycle Modeling Processes
- BAgreement Processes
- CModel Based Engineering
- DTechnical Management Processes
8The 8 Technical Management Processes include (choose 4):
- AProject Planning
- BProject Assessment and Control
- CRequirements Analaysis
- DConfiguration Management
- EImplementation
- FStakeholder Requriements Definition
- GInformation Management
9The 5 Organizational Project-Enabling Processes identified by ISO/IEC/IEEE 15288 include (choose 3):
- ATechnical Process
- BInfrastructure Management Process
- CAgreement Process
- DHuman Resources Management Process
- EQuality Management Process
10The 5 Organizational Project-Enabling Processes identified by ISO/IEC/IEEE 15288 include (choose 2):
- APortfolio Management Processes
- BAgreement Processes
- CLife Cycle Model Management Processes
- DTechnical Processes
11When joining a project, one of the first jobs of a systems engineering is to:
- ACreate Integrated Product Development Teams (IPDT's)
- BInitiate a function based analysis to establish a foundation for defining a system architecture
- CBegin writing the Concept of Operations document in order to demonstrates the organization grasps the customers wants and needs
- DEstablish nomenclature and terminology to support clear, unambiguous communication
12Input-process-output diagrams typically include controls and enablers
- ATrue
- BFalse
13How many items are called out in the Controls box
- A3
- B4
- C5
- D6
14Select the Controls from the list below:
- AApplicable laws and regulations
- BOrganizational policies, procedures and standards
- COrganizational Infrastructure
- DStandards
- EAgreements
- FProject Infrastructure
- GProject Direction
- HKnowledge Management
- IProject Control Requests
15The definition of "Process" used in the Activities box is:
- Aa series of actions or steps taken in order to achieve a particular end
- Bsequence of interdependent and linked procedures which, at every stage, consume one or more resources
- Can integrated set of activities that transforms inputs into desired outputs
- Da series of action, changes, or functions bringing about a result
16The input-process-output diagrams represent:
- Athe single best way to perform systems engineering processes
- Bthe fact that systems engineering must produce the documents listed in the outputs
- Cone potential way the systems engineering processes can be performed
17Project direction, as found in the Controls box of the input-process-output (IPO) diagram, is defined as:
- Aa vector defining the success criteria for a project
- Bthe organizations direction to a project to continue, redirect or terminate
- Ca measurement against assessment criteria that determines if a project is moving forward or stalled
- Dpermission to continue forward at the conclusion of a phase-gate or state-gate review
18The difference between "project direction: and "project control requests" is best described by:
- AProject control requests are internally generated by the project due to deviations form the project plan
- BProject direction is internally generated by the project in response to deviations from the project plan
- CProject control requests are suggestions white project direction is an authoritative order