- 1What are examples of: 1. Enterprise Environmental Factors (EEF) 2. Organisational Process Assets (OPA) 3. Organisational SystemsEEF - Rules and policies. Outside of project and often outside of the company i.e GDPR
OPA - Benefits and things created through experience for PM to use. i.e Forms
OS - Structure of work is done i.e Governance framework, who reports to who, org stucture - 2What is the intention of a project?To create Business Value
- 3What are the four reasons a project are created?1. Regulatory, legal or social requirements
2. Stakeholder requests
3. Technological advances
4. Create, improve, fix - products, processes, services (MACD) - 4List a few reasons why a project would end?-Objectives met/not met
-Funds depleted
-No longer needed
-Change in requirements
-Resource issues - 5What are the two states in projects?Current State and Future State
- 6Who is a Stakeholder?Anyone that can affect or be affected by the project?
- 7What are the 5 steps in Progressive Elaboration?Idea or concept --> Formulate idea --> business case --> feasibility study --> Project
- 8What is project application area?Describes the industry the project is happening in
- 9What are some characteristics of the PMO? What is PMO?Project Management Office
Support PMs - Manage Shared Resources - Coaching, mentoring, training - Conduct P Audits, develop processes + procedures - 10What are the three types of PMO? and what do they offer?1. Supportive - Templates, training, consultative
2. Controlling - Governance, forms, templates. Compliance through framework
3. Directive - PMO owns + controls the P lifecycle. Directly managed. - 11What can predictive life cycles also be referred to?Waterfall
- 12In life cycle Iterative, how is the product developed?Series of repeated cycles
- 13In adaptive life cycle, what are the three cycles it can be?Agile
Iterative
Incremental - 14What are adaptive life cycles also referred to as?Agile or change-driven life cycles
- 15What are the 3 types of Organisational Structure?Functional
Project Orientated
Matrix - 16What are the three things to remember for the exam regarding these? Functional Project Orientated MatrixFunctional = SILO
Project Orientated = NO HOME
Matrix = 2 MANAGERS - 17What are the three types of Matrix and how do they affect the PM?Weak - Power with FM
Balanced - Equal responsibility PM/FM
Strong - Power with Project Manager - 18What is a Funtional Manager?Someone who is a manager of a department and reports to Project Manager
- 19What's an example of document in Knowledge Repository?Historical Data
- 20What are the brief definitions of Portfolio, Programme & ProjectPortfolio - Run by executive level. It's the collection of strategic goals for the organisation.
Programme - A group of multiple projects and sometimes programme(s)
Project - To complete the life cycle to meet deliverable(s) set out at the start. - 21When is a Project formally authorised and in which process group?Project Charter signed by the sponsor.
Within Initiating Process Group - 22What is Qualitative Risk Analysis?It identifies the highest risk issues to be dealt with first. Risks are ranked on the basis of their impact and likelihood and thus you can take care of the ones with high risk exposure
- 23What is Quantative Risk Analysis?This analysis is only performed on risks which are marked for further analysis by Perform Qualitative Risk Analysis process
We identify “effect of identified risks on overall project objectives.” - 24What are the three types of changes?Corrective
Preventative
Defect Repair - 25Which of the knowledge areas has processes occurring in all process groups?Integration
- 26What is the primary role of a PM?Integration Management
- 27What are the key things happen in the project charter?-Formally authorises existence of Project
-Provides authorisation to PM to apply organisational resources to P activites - 28What provides a direct link between strategic objectives and the Project?Project Charter
- 29What does the Project Management Plan provide?It's a comprehensive document that defines the basis of all Project work and how the work will be performed
- 30There are management plans for all Knowledge Areas. What additional 3 plans are there?Requirements Management Plan
Change Management Plan
Configuration Management Plan - 31A Project Management Plan is a set of plans and.....?Baselines
- 32What are the three baselines?Schedule Baseline
Scope Baseline
Cost Baseline - 33What are Schedule Baseline Scope Baseline Cost Baseline referred to as a collective?Performance Measurement Baseline
- 34With all the product + project documentation that is part of managing a P + all the changes to this documentation that will occur throughout the life cycle of a P, its essential to have a plan for making sure everyone knows what version of the scope, schedule + other components of the P Management plan is the latest version.Configuration Management Plan
- 35What are project documents?The documents outside of the Project Management Plan i.e Assumptions Log, Lessons Learned, Cost + Duration Estimates
- 36What is Direct & Manage Project Work?PM integrates all executing working into one coordinated effort to accomplish the Project Management Plan. Involves managing people + keeping them engaged in the P, doing the work. Being a service to team to get work completed.
- 37What Knowledge Area are deliverable's an output of?Integration Management
- 38What are 6 outputs of Direct + Manage Project work?Deliverables
Work Performance Data
Issue Log
Change Requests
Project Management Plan
Project Document Updates - 39Which function is Work Performance Data collected in?Integration Management
(its an input to Monitoring & Controlling) - 40What are the two types of Project Knowledge?Explicit
Tacit - 41What are the definition of Explicit & Tacit?Explicit: Knowledge codified using words, pictures, numbers. i.e Lessons Log
Tacit: Personal & difficult to express, such as beliefs, insight, experience (understood or implied WITHOUT being stated - 42What are the three things Lessons Learned contains?What went right
What went wrong
What would be done differently - 43What is Monitor & Control Project Work?The process of tracking, reviewing and reporting the overall progress to meet the performance objectives defined in the Project Management Plan
- 44If a Stakeholder would like to understand the current state of the project, where would they look?Monitoring & Controlling Project Work
- 45If I wanted to change the Project Management Plan, how would I go about this?Through organisations change control process via a change request
- 46What areas does monitoring & controlling measure against?All aspects of the Project Management Plan
- 47What should you do if a work activity takes longer than expected?Request corrective action to make up for the delay
- 48What is corrective action?Any action taken to bring the expected future peformance in line with the Project Management Plan
- 49In what process are changes Approved, Denied & Deferred?Perform Integrated Change Control
- 50What is preventive action?Put in place to stop deviations from the performance measurement baseline or other metrics
- 51What action is required from the following? The PM is evaluating trends in the measurement analysis & anticipating that, if trends continue, they could lead to deviation from performance measurement baseline.Preventive action
- 52What is another way of saying Defect Repair?Rework i.e fixing something someone did wrong like painting a wall the wrong colour
- 53Which processes is primarily concerned with defining and controlling what is and is not included in the project?Project Scope Management
- 54What are The Project Scope Management processes?Plan Scope Management
Collect Requirements
Define Scope
Create WBS
Validate Scope
Control Scope - 55“Scope” can refer two things. What are they? And their definition?Product scope :: The features and functions that characterise a product, service, or result.
Project scope :: The work performed to deliver a product, service, or result with the specified features and functions. The term “project scope” is sometimes viewed as including product scope. - 56Which project life cycles are intended to respond to high levels of change and require ongoing stakeholder engagement?Adaptive/agile
- 57In which Development approach do requirements constitute the backlog?Agile
- 58Where does the development of the scope management plan and the detailing of the project scope begin?-with the analysis of information contained in the p charter
-the latest approved subsidiary plans of the p mgmt plan
-historical information contained in the organisational process assets
-any other relevant enterprise environmental - 59What provides the basis for defining the product scope and project scope?Collect Requirements
- 60What is Requirements Traceability Matrix?The requirements traceability matrix is a grid that links product requirements to the deliverables that satisfy them and helps to focus on the final outcomes
- 61What is CCB?Change Control Board
- 62In which 3 processes are Approved changes implemented?-Direct & Manage Project Work
-Control Quality
-Control Procurements - 63Do you need to submit change requests to make changes to Project Management Plan, Charter, Baselines if you are still developing these plans?No
- 64Where are the result of the CCB decisions documented?Change Log
- 65In what document are the project success criteria, approval requirements and who will sign off the on the project held?Project Charter
- 66What function is close project or phase in?Integration Management
- 67What are the four outputs to close Project or Phase?-Final Report
-Final product, service, or result transition
-Project document updates
-Organisation Process Assets updates - 68Give example of Product & Project Scope?Project: Build new train terminal
Product: new train terminal that meets these specific technical specifications - 69What are the two management plans for Scope Management?Scope Management Plan
Requirements Management Plan - 70What is also referred to as the Business Analysis plan?Requirements Management Plan
- 71What things does Collect Requirements look for?Everything, all requirements, not just those related to the Project i.e Can't upgrade Firewalls during the week
- 72In Collect Requirements, where or what document would you read to find stakeholders requirement & expectations?Stakeholder Register
- 73What is an Affinity Diagram?Diagram with grouped similarities i.e ASA5500
- 74What is Brainstorming?Sharing and elaborating on each-others ideas
- 75What are the three subjects in User Stories?Role/Functionality/Benefit
Example: As Network Engineer I want devices patched to latest OS to avoid bugs - 76What are the two outputs of Collect Requirements?Requirements Documentation
Requirements Traceability Matrix - 77What is the key input to Define Scope process?Requirements Documentation
- 78What is a critical tool to allow the PM to make sure the product & project scope are understood and accurate?Product Analysis
- 79What is the primary output of Define Scope process?Project Scope Statement
- 80Which 3 documents comprise the scope baseline?Project Scope Statement
WBS
WBS Dictionary - 81What are and are NOT included in WBS?Are: Deliverables
Are not: Activities - 82When the WBS is broken down into activities list, what is this called?Define Activities
- 83What document can the PM use to prevent scope creep?WBS Dictionary
- 84Where can acceptance criteria be found?WBS Dictionary
- 85How do you validate scope?Involves frequent, planned meetings with customer or sponsor to gain formal acceptance of deliverables during project monitoring & controlling
- 86What does the general term Input mean in PMI world?"What do I need before I can?"
- 87What's the difference between Validate Scope and Control Quality?- Control Quality is internal to the P to make sure deliverables meet requirements before shown to the customer
-Validate Scope is the customer checks + hopefully accepts the delivrables - 88What is this validation called in control quality?Verified Deliverables
- 89What are the three outputs of Control Scope?-Work Performance Information
-Change Requests
-Project Management Plan & P Document updates - 90What is the output of Plan Schedule Management?Schedule Management Plan
- 91What is define activities?Taking work packages created in WBS and decomposing them into activities
- 92What is Rolling Wave planning?When its better to not plan the entire project to the smallest detail. Have more detailed plans when the work is done
- 93What are the three outputs to Define Activities?Activity List
Activity Attributes
Milestone List - 94What is PDM? in relation to Sequence ActivitiesPrecedence Diagramming Method
- 95What are the four types of logical relationship between Activities?FS - Finish to start
SS - Start to start
FF - Finish to finish
SF - Start to finish - 96What happens in: FS - Finish to start SS - Start to start FF - Finish to finish SF - Start to finishFS: Activity must finish before successor can start
SS: activity must start before successor can start
FF: Activity must finish before successor can finish
SF: activity must start before successor can finish - 97What are the four types of dependencies?Mandatory
Discretionary
External
Internal - 98Briefly what do the four mean? Mandatory Discretionary External InternalM: Have to be done in order
D: Org preferred approach
E: Based on needs of 3rd party
I: Based on need of Project - 99What are Leads & Lags?Lead - activity can start before predecessor activity completed
Lag - have to wait. I.e have to wait 3 days for concrete to set - 100What is in a Project Schedule Network Diagram?Image depicting the flow or Project activities in the logical order in which they are performed
- 101What is an activity that has two or more successor activities directly following it?Path Divergence
- 102What is an activity that has two or more activities directly preceeding it?Path Convergence
- 103Describe Analogous Estimating?Uses historical information for estimating i.e the last project took 6 months, this should take the same time
- 104Describe Parametric Estimating?Uses parameters to estimate. Involves creating maths equation using historical records or other sources
- 105What are the three points in Three Point Estimating?Optimistic
Pessimistic
Most Likely - 106What is Three Point Estimating also known as?Triangular Distribution
- 107What is the formula for Triangular Distribution?P + O + M /3
- 108What is Rolling Wave Planning a form of?Progressive Elaboration
- 109What are the free types of float and what are they?Free: Activity delayed without delaying early start of successor
Total: Activity delayed without delaying Project completion
Project:Activity delayed without passing customer-expected completion date - 110What are the top line and bottom line of the nodes in Network Diagram? Top & bottom left Top & bottom middle Top & bottom rightTop & bottom left - Start
Top & bottom middle - Duration
Top & bottom right - Finish - 111What is Critical Path?Longest path in duration
- 112What path is sometimes referred to as having 'no float' ?Critical Path
- 113What's the difference between Crashing & Fast Tracking?-Fast tracking is running activities in parallel
-Crashing is throwing more staff/resources at it - 114What kind of technique is Monte Carlo analysis?Simulation Technique
- 115Explain Monte CarloComputer software simulating outcome of Project
Based on 3 point estimates for each activity - 116What is Value Analysis?Focuses on finding a less costly way to do the same work with no loss of performance
- 117What is Cost Risk?The party or person that is the owner of the cost risk, i.e The Seller
- 118What is the output of Plan Cost Management?Cost Management Plan
- 119What are the two types of cost and what do they mean?Direct: Attributable to work, wages, team travel, materials
Indirect: Overhead costs e.g Taxes, cleaning services - 120What can be used to cover risk to the schedule and cost?Reserve/Reserve Analysis
- 121What is the nominal group technique?a
- 122What are the three estimate ranges?Rough order of magnitude (-25 +75)
Budget Estimate (-10 +25)
Definitive Estimate (-10 +5) - 123What does Determine Budget produce?Total cost of Project & therefore the funds needed
- 124What are two essential inputs to Determine Budge?Cost Estimates
Basis of Estimates - 125What is Cost Aggregation?All these:
Activity Cost Aggregation
Work Package Estimates
Project Costs - 126What are the 8 steps in creating a budget?1. Activity Estimates
2. Work Package Estimates
3. Control Account Estimates
4. Project Estimates
5. Contingency Reserves
6. Cost Baseline
7. Management Reserves
8. Cost Budget - 127What is Earned Value Analysis?Used in performance reviews to measure project performance against scope, schedule, and cost baselines
- 128What is 7 letter acronym for Earned Value terms?Planned
Earnings
Add
Billions
Even
Euros
Value - 129What are the full initials for them?PV
EV
AC
BAC
EAC
ETC
VAC - 130What does PEABEEV mean?Planned Value
Earned Value
Actual Cost
Budget at completion
Estimate at completion
Estimate to complete
Variance at completion - 131What is acronym for Acronym for 3 point estimates and what does it mean?Oh My Project
Optimistic
Most Likely
Pessimistic - 132What is the formula for OMP? What is the answer to this? O 25 M 45 P 75Formula: O + M + P / 3
(25+45+75) /3 = 48.33 hours - 133What does PERT mean?Program
Evaluation
Review
Technique - 134What's the formula for PERT?Formula: (O+(4xML)+P) /6 = estimate
(25+(4x45)+75) /6 = 46.6 hours - 135What is bottom up estimating?-Term associated with cost estimates
-Requires a fully-decomposed WBS for each work package - 136What are the four types of Dependency Determination?Mandatory - Hard Logic
Discretionary - Soft Logic
External Dependency - External Constraint
Internal Dependency - type of Hard Logic - 137What is another term for Activity-on-node?Precedence Diagramming Method
- 138What diagram do you use to find float?Precedence Diagramming Method
- 139Whats a schedule compression technique?Leads
- 140What are: CV SV CPI SPICost Variance
Schedule Variance
Cost Performance Index
Schedule Performance Index - 141What do I need to remember about EV?It comes first in each formula!
- 142What is the definition of Quality?Degree to which the project fulfils requirements
- 143What are the quality the 3 Quality Management processes?Plan Quality Management
Manage Quality
Control Quality - 144What is COQ?Cost of Quality
- 145What are the three things from attribute of quality that x can represent in Design for X?Reliability
Security
Serviceability - 146What is Design for X?Technical guidelines that may be applied during the design of a product for the optimisation of a specific aspect of the design
- 147What is a bar chart also referred to as?Histogram
- 148What is Pareto a type of?Histogram
- 149What is a critical part of Plan Resource Management?Definition of roles & responsibilities
- 150What is RAM?Responsibility Assignment Matrix
- 151What does RACI stand for?Responsible
Accountable
Consult
Inform - 152What is Estimate Activity Resources?PM & team determine type and quantity of resources needed to complete project work. Inclusive of HR, equipment, materials etc
- 153What is RBS?Resource Breakdown Structure
- 154What process does Acquire Resources fall under?Executing
- 155What is develop team?Its about improving knowledge + skills of team members + enhancing teamwork + team member interaction
- 156What are some tools & techniques of Develop Team?Interpersonal & team skills
Negotiation
Team Building
Influencing
Training - 157What are the 5 Tuckman ladder model stages for team building?Forming
Storming
Norming
Performing
Adjourning - 158Where are details related to team management activities included?Resource Management Plan
- 159Who should conflict be resolved by?Those involved in the conflict
- 160What are the 7 sources of conflict?Schedules
Priorities
Resources
Technical opinions
Administrative procedures
Cost
Personality - 161What are the 5 conflict resolution techniques?Collaborating (problem solving)
Compromising (reconciling)
Withdrawal (avoidance)
Smoothing (accommodating)
Forcing (directing) - 162What are control resources?Management of physical things but not human though.
- 163What does Control Resources means the PM has to ensure?Physical resources are available when needed, in the right place and quantity
- 164What are the four types of communication?Formal written - Contract
Formal verbal - Planned meeting
Informal written - Email, notes
Informal verbal - Unplanned meetings - 165What are the 5 c's of communication?Correct grammar & spelling
Concise & well-crafted
Clear & purposeful
Coherent & logical
Controlled flow of words & ideas - 166What is the communication channel formula?n x (n-1) / 2
n is the total number of S/H - 167So what is the formula for 4 people?4 x 3 / 2 = 8
- 168What is active listening?Receiver confirms they are listening. Express agreement/disagreement + ask for clarification
- 169What are the 3 communication methods?Interactive comms - 2 or more people, tcall
Push comms - 1 way, email
Pull comms - Central - SharePoint - 170What is Risk Management?Process of identifying, evaluating, and planning responses to events, both positive and negative, that might occur throughout the project, while decreasing the probability + impacts of threats to the P
- 171What are some practical things that can reduce risk?Outsourcing work
More skilled people - 172What are the 4 risk factors when accessing risk?Probability it will happen
How much it will impact the P
Expecting timing to occur in P life-cycle
How often it might occur - 173What's another term for Risk Appetite?Risk Tolerence
- 174What do you call a Stakeholder who does not want to be negatively impacted by threats?Risk Averse
- 175What answers the question: How much time should be spent on risk management based on needs of P?Plan Risk Management
- 176What is SWOT?Strengths
Weaknesses
Opportunities
Threats - 177What are prompt lists?List of categories that have been identified as possible sources of risk to the project
- 178What are the 2 outputs of Identify Risks?Risk Register
Risk Report - 179What are the possible ways risks can go after Qualitative Risk Analysis?Quantitative Risk Analysis or Risk Response
- 180What are four examples of Risk Parameters?Urgency
Dormancy
Manageability
Controllability
Strategic Impact - 181What is the 'scale' for measuring risk occurrence + impact? Word & NumberingLow, Medium, High
1-10 - 182Where are the Watch List risks stored?Risk Register
- 183What is sensitivity analysis?Technique used to analyse & compare the potential impacts of identified risks
- 184What's a good diagram for results of Sensitivity Analysis?Tornado Diagram
- 185What is Decision Tree Analysis?When a PM has to choose between alternatives, they analyse how this will benefit or hurt a P before making a decision. They are models of real situations that PMs use to make an informed decision about things like 'which option should I choose?'
- 186What diagram do you calculate the value of each branch on?Decision Tree
- 187What is the EMV formula for decision tree?Probability (P) x Impact (I)
- 188What is EMV?Expected Monetary Value
- 189Who does the PM assign residual tasks to?Risk Owner
- 190What does a risk owner do?Watch out for the occurrence of a risk + implemented pre-planned responses
- 191What are the three response strategies for threats?Avoid
Mitigate
Transfer - 192What are the 3 response strategies for opportunities?Exploit
Enhance
Share - 193Who are involved in choosing a risk strategy?The team, Stakeholders + experts
- 194What are the techniques for evaluating + ranking potential risk responses?Cost Benefit Analysis
Multicriteria Decision Making - 195What are residual risk?The risks left after risk response planning
- 196Can contingency reserves for a specific risk response be used elsewhere if the risk does not occur?No, it must be handed back to the company/sponsor