07 PROJECT COST MANAGEMENT

kat atkins Project Management PMP English 32 cards

Cards in this deck (32)

  1. 17.1 Plan Cost Management*establishes the policies, procedures, and documentation
    for planning, managing, expending, and controlling project costs.
  2. 27.2 Estimate Costs*Developing an approximation of the monetary resources needed to
    complete project activities
  3. 37.3 Determine BudgetAggregating estimated costs of individual activities or work
    packages to establish an authorized cost baseline.
  4. 47.4 Control CostsMonitoring the status of the project:
    *Update the project costs
    Managing changes to the cost baseline.
  5. 5Different stakeholders will measure project costs indifferent ways and at different times.
  6. 6What is the cost management plan?*Component of Project Management Plan
    *Describes how the project
    costs will be planned, structured, and controlled
    *Describes tools and
    techniques
  7. 7What is a Cost estimates?*Prediction that is based on the information known at a given point in time. *Identification and consideration of costing alternatives to initiate and complete the project.
  8. 8The accuracy of a project estimate will ???*Increase as the
    project progresses through the project life cycle.
  9. 9What is a cost estimate?*Quantitative assessment of the likely costs for resources
    required to complete the activity.
    *May be presented at the activity level or in summary form.
  10. 10What is Analogous Cost Estimating ?*Uses values such as scope, cost, budget, and duration or measures of scale such
    as size, weight, and complexity from a previous, similar project as the basis for estimating the same parameter
    or measurement for a current project. *Technique relies on the actual cost of previous, similar projects as BOE for current project.
    *Gross value estimating approach,
    sometimes adjusted for known differences in project complexity.
  11. 11What are Management Reserves?*Intended to address the
    “unknown unknowns”
    *Not included in the cost baseline but
    is part of the overall project budget and funding requirements
    * If used, additional cost baseline
    *Requires an
    approved change to the cost baseline.
  12. 12What are Activity Cost Estimates?*Quantitative assessments of probable costs required to complete project
    work.
    *Cost estimates can be in summary form or in detail.
    *Costs estimated for all resources that
    are applied to the activity cost estimate.
  13. 13A project budget includes what?*All the funds authorized to execute the project
  14. 14What is the Cost Baseline?*Approved
    version of the time-phased project budget, * EXCLUDES management reserves.
  15. 15Earned value management (EVM) isbaseline, to form the performance baseline, which helps the project management team assess and measure
    project performance and progress.
  16. 16The total of the Planned Value is sometimes referred to as?*Performance Measurement Baseline
    (PMB).
    *Also known as Budget at Completion (BAC).
  17. 17Earned value (EV) is a measure of ???• Measure of work performed expressed in terms of budget authorized for that work.
    *Budget associated with the authorized work that has been completed.
    The EV being measured needs to be related to the PMB, and the EV measured cannot be greater than the
    authorized PV budget for a component. The EV is often used to calculate the percent complete of a project.
    Progress measurement criteria should be established for each WBS component to measure work in
    progress. Project managers monitor EV, both incrementally to determine current status and cumulatively
    to determine the long-term performance trends.
  18. 18Cost Performance Index (CPI) ?*Measures cost efficiency of budgeted
    resources,
    *Ratio of earned value to actual cost
    *MOST critical EVM metric
    *Measures cost efficiency of work completed
    *CPI <1.0 indicates cost overrun for work completed.
    *CPI> 1.0 indicates cost underrun of performance to date. The CPI is equal to the ratio of the EV to the AC. Equation: CPI = EV/AC
  19. 19Schedule Performance Index (SPI)*measure of schedule efficiency
    *ratio of earned value to planned value. *how efficiently the project team is
    using its time.
    *Can be used in conjunction with the CPI to forecast thefinal project completion estimates. An SPI value less than 1.0 indicates less work was completed than
    was planned. An SPI greater than 1.0 indicates that more work was completed than was planned. Since
    the SPI measures all project work, the performance on the critical path also needs to be analyzed to
    determine whether the project will finish ahead of or behind its planned finish date. The SPI is equal to
    the ratio of the EV to the PV. Equation: SPI = EV/PV
  20. 20The To-Complete Performance Index (TCPI) isa measure of the cost performance that is required to be achieved
    with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to
    finish the outstanding work to the remaining budget. TCPI is the calculated cost performance index that is achieved
    on the remaining work to meet a specified management goal, such as the BAC or the EAC.
  21. 21What is PV (Planned Value)?*Authorized budget assigned to
    scheduled work.
    *Value of the work planned to be
    completed to a point in time
  22. 22EV (Earned Value)*Measure of work performed
    *Expressed in terms of the budget
    authorized for that work.
  23. 23AC (Actual Cost)*The realized cost incurred for the
    work performed on an activity during
    a specific time period.
    *Actual cost of all the work
    completed to a point in time, usually
    the data date.
  24. 24BAC (Budget at Completion)*Sum of all budgets established
    for the work to be performed.
    *Value of total planned work, the
    project cost baseline.
  25. 25CV (Cost Variance)*Amount of budget deficit or
    surplus at a given point in time,
    *Earned Value minus actual cost.
  26. 26SV (Schedule Variance)*Amount the project is ahead or behind the planned delivery date
    *Earned Value minus Planned Value
    *Difference between work
    completed and the work planned at the same point in time
  27. 27VAC (Variance at Completion)*A projection of amount of budget
    deficit or surplus
    *Budget at Completion minus
    Estimate at Completion
  28. 28CPI (Cost Performance Index)*Cost Efficiency of budgeted resources
    *Ratio of earned value to actual cost.
    CPI =1.0 project on budget
    *work
    actually done so far is exactly the
    same as the cost so far. Other values
    show the percentage of how much
    costs are over or under the budgeted
    amount for work accomplished.
  29. 29SPI (Schedule Performance Index)*Measure of schedule efficiency
    *Ratio of earned value to planned value
    *SPI of 1.0 = project on schedule
    *Work completed = work planned
    Other values how much costs are
    over or under budgeted for work planned.
  30. 30EAC (Estimate At Completion)*Expected total cost of completing
    all work
    *Expressed as the sum of the actual cost to date and the estimate to complete.
  31. 31ETC (Estimate to Complete)*Expected cost to finish all the
    remaining project work.
  32. 32TCPI (To Complete Performance Index)?* How much is it going to cost with the existing resources to get/met a specified management goal
    *Ratio Cost to
    Finish Outstanding Work : Budget Available.

Information

Description
PMP Project Management Flashcards on 07 PROJECT COST MANAGEMENT, created by kat atkins on 07/03/2017.
Created by
kat atkins
Views
2
History
  • Created by miguelabascal · Jul 12, 2013
  • Copied by kat atkins · Mar 7, 2017
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?