Mapa mental
lecture 2
Conteúdo do mapa
lecture 2
Programme
- large activity-meet long term objective
- can be subdivided
project
- activity-specified start/finish date-meet object
task
- project/activity-outcome, time scale, resource allocation
- deliverables of task-together-deliverable larger task
- can be divided-sub tasks-lowest level of detail
- responsible individuals
- project/activity-outcome, time scale, resource allocation
work package
- sub-project, group of related tasks-specific item
- 5-10 major groups activity
- best way work can be organised/delivered
- composed of number of tasks
- 5-10 major groups activity
- sub-project, group of related tasks-specific item
WBS
- first step in detailed plan
- identifies/catalogues activities to complete project
- as hierarchy of tasks, sub-tasks, sub sub tasks
- compiling a WBS
- develops objective, view of amount of work required
- team grasp skills-amount of resources required for project
- clear framework-assign to individuals tasks-delegate responsibility
- foundation-analyzing task dependencies, isolate/manage risk
- bottom up estimate for proj schedule
- level of detail
- tasks=small=accurate monitoring
- smallest task=5% project
- tasks=small=accurate monitoring
Programme-project-work package-deliverable/milestone-task
- 3 levels-WP, D/M, Task
Deliverable
- clearly defined-recognisable results, successfully completed activities/tasks
Milestone
- identify completion of significant segments
- indicate completion of each work package
- identify completion of significant segments
Gantt Charts
- type of bar chart
- Advantages- long time use, clear hierarchy, effective in describing project progress against milestone/deliverables
- Disadvantage- little info per unit area, difficult to read >30 tasks, not show fully relationships/dependencies. no EET, LET, CP. No risk/failure delay.
- prefer by business executive
Net work diagram
- graphically show sequential relations between tasks
- Total duration, EET, LET- displayed.
- critical tasks -extra effort is needed
- PM prefer function of ND
- potential decrease proj duration-better understanding, improved overlapping
- Two approaches-PERT, CPM
- Program evaluation and review technique
- Two approaches-PERT, CPM