SAB2#69 Determinate_budget

Inhalt der Mindmap
SAB2#69 Determinate_budget
Example:
- $2423
- $68
- $2355
- $105
- $2250
- CA1 $1850
- WP1 $100
- A1 $25
- A2 $25
- A3 $25
- A4 $25
- WP2 $250
- A5 $45
- WP3 $500
- WP1 $100
- CA2 $400
- WP4 $175
- CA1 $1850
- $2250
- $105
- $2355
- $68
- $2423
Cost AgregationProcess Steps:
- 8. Cost Budget
- 7. Management Reserve
- 6. Cost Baseline
- 5. Contingecy Reserve
- 4. Project Estimates
- 3. Control Account Estimates
- 2. Work Packages Estimates
- 1. Activity Estimates
- 2. Work Packages Estimates
- 3. Control Account Estimates
- 4. Project Estimates
- 5. Contingecy Reserve
- 6. Cost Baseline
- 7. Management Reserve
- 8. Cost Budget
Inputs
- Cost Management Plan
- Scope Baseline
- Project Schedule
- Risk register
- Organizational Process Assets
- Cost Estimates
- Basis of Estimates
- Availavility of Resources
- Agreements about costs associated with purchases
Budget Determination Process:
- 1. Determine risk management activities Including Contingency and Management Reserves
- 2.Determine Baseline adding reserves plus acitvities cost
- 3. Compare these numbers to parametric estimates to justify differences
- 4. Check Cash Flow
- 5. Recontilation with charter constrains
- 6. if project costs exceeds constrains propose alternatives to management
- 7. Update changes on budget when required
- 6. if project costs exceeds constrains propose alternatives to management
- 5. Recontilation with charter constrains
- 4. Check Cash Flow
- 3. Compare these numbers to parametric estimates to justify differences
- 2.Determine Baseline adding reserves plus acitvities cost
- 1. Determine risk management activities Including Contingency and Management Reserves
Cost budget is cost baseline plus magement reserve. Cost budget is how much money is availbale for project
Bilder und Dateien der Mindmap
Informationen
- Beschreibung
- Mindmap am SAB2#69 Determinate_budget, erstellt von Gerardo Rodríguez am 16/08/2014.
- Erstellt von
- Gerardo Rodríguez
- Aufrufe
- 67
- Tags
- Bewertung