  1. Electrified lines1. You receive an overhead line permit for work near OLE. What does the permit tell you?
    1. Which train movements have been stopped
    2. Which return conductors have been isolated
    3. Which emergency switch-off areas are available
    4. Which electrical equipment is isolated and earthed for the specified work
    Show answer and explanation

    Answer: D. Which electrical equipment is isolated and earthed for the specified work

    The permit identifies the equipment that is isolated and earthed on or near which the specified work can begin. Its issue does not mean that train movements have stopped.

    Why the others are wrong

    • Which train movements have been stopped: An overhead line permit does not mean train movements have stopped.
    • Which return conductors have been isolated: Return conductors cannot be isolated because they are part of the return current system.
    • Which emergency switch-off areas are available: The permit identifies equipment made safe for the specified work, not emergency switch-off areas.

    Source: GERT8000-HB16 AC electrified lines (Iss 7, Definitions

  2. Electrified lines2. A colleague says OLE is isolated because it has been connected to the traction return running rail. What is the correct distinction?
    1. That connection means the OLE is isolated; earthing requires separation from all supplies.
    2. That connection means the OLE is earthed; isolation requires secure separation from all supplies.
    3. Both isolation and earthing mean connection to the traction return running rail.
    4. Both isolation and earthing mean secure separation from all electricity supplies.
    Show answer and explanation

    Answer: B. That connection means the OLE is earthed; isolation requires secure separation from all supplies.

    Connecting normally live OLE to the traction return running rail is earthing. Isolation requires disconnection and secure separation from all electricity supplies; the terms describe different conditions.

    Why the others are wrong

    • That connection means the OLE is isolated; earthing requires separation from all supplies: The descriptions of isolation and earthing are reversed.
    • Both isolation and earthing mean connection to the traction return running rail: Connection to the running rail describes earthing, not isolation.
    • Both isolation and earthing mean secure separation from all electricity supplies: Secure separation from supplies describes isolation, not earthing.

    Source: GERT8000-HB16 AC electrified lines (Iss 7, Definitions

  3. Electrified lines3. You arrive with your group at a site where new OLE has been installed. You cannot establish whether it has been declared live. How must you treat it?
    1. As safe until an energisation warning notice is received
    2. As live and dangerous to life
    3. As safe if no train is approaching
    4. As live only where wires are directly overhead
    Show answer and explanation

    Answer: B. As live and dangerous to life

    If you are unsure whether OLE is live, you must treat it as live and dangerous to life. This prevents uncertainty being mistaken for an assurance that the equipment is safe.

    Why the others are wrong

    • As safe until an energisation warning notice is received: Uncertainty does not mean the equipment can be treated as safe.
    • As safe if no train is approaching: An approaching train is not the test of whether OLE is live.
    • As live only where wires are directly overhead: The rule applies when you are unsure whether OLE is live, not only when directly beneath wires.

    Source: GERT8000-HB16 AC electrified lines (Iss 7, General

  4. Electrified lines4. You are COSS and are told the ECO has confirmed that the electricity is switched off. What must you do?
    1. Treat the OLE as safe to touch.
    2. Allow the group to touch the OLE after a briefing.
    3. Treat the OLE as safe once work has stopped. Non-breaking
    4. Keep treating the OLE as dangerous and do not touch it.
    Show answer and explanation

    Answer: D. Keep treating the OLE as dangerous and do not touch it.

    Confirmation that the electricity is switched off does not by itself make the OLE safe to touch. Continue to treat it as dangerous until the applicable safety arrangements have been satisfied.

    Why the others are wrong

    • Treat the OLE as safe to touch: Switching off alone does not make the OLE safe to touch.
    • Allow the group to touch the OLE after a briefing: A briefing does not make the OLE safe to touch.
    • Treat the OLE as safe once work has stopped. Non-breaking: Stopping work does not make the OLE safe to touch.

    Source: GERT8000-HB16 AC electrified lines (Iss 7, Treating the OLE, pantographs and

  5. Electrified lines5. You are COSS when a member of your group notices an object hanging from the OLE. They are not specially trained or authorised to deal with it. What should you tell them?
    1. Approach the object but avoid touching the OLE.
    2. Remove the object if the wires appear undamaged.
    3. Keep away and treat the object as live and dangerous.
    4. Move the object clear using a long, dry tool.
    Show answer and explanation

    Answer: C. Keep away and treat the object as live and dangerous.

    Anything hanging from or near the OLE must be treated as live and dangerous. Do not approach or try to remove it unless specially trained and authorised.

    Why the others are wrong

    • Approach the object but avoid touching the OLE: Approaching the object is prohibited without special training and authorisation.
    • Remove the object if the wires appear undamaged: Undamaged-looking wires do not make the object safe to remove.
    • Move the object clear using a long, dry tool: Using a long, dry tool does not remove the restriction.

    Source: GERT8000-HB16 AC electrified lines (Iss 7, Objects on or near to the OLE

Sign up free

Other COSS topics

GoConqr Original. Practice questions written with AI from the Rule Book handbooks and Network Rail guidance a COSS works to, each checked against the source it cites. Think a question is wrong? Use 'Report' under it.

Independent revision resource. Not affiliated with Network Rail, RSSB or any training provider.

© Visual Maths Resources Ltd

Feedback

What is it about?