Exams · UK
COSS Handbook: Role and Competence Revision Test
Who does what on site (COSS, IWA, PC, PIC), the key terms, competence and the Sentinel rules.
Updated 11 November 2026 for the rules in force now. The 5 December 2026 handbook changes are listed below.
Key rules
See all 13 key rulesA visitor with a permit issued under company instructions may take part in work without the required track safety competence.
GERT8000-HB7 General duties of a COSS, Visitor permits
The visitor must give the COSS a document confirming that the visit to the operational railway has been approved.
GERT8000-HB7 General duties of a COSS, Visitor permits
Brief the visitor on the safe system of work, sign and keep the visitor permit, and stay with the visitor until they leave the operational railway.
GERT8000-HB7 General duties of a COSS, Visitor permits
Do not undertake a task without the competence, equipment, information and knowledge needed to complete it safely.
Sentinel Scheme Rules
Be fit for work, not fatigued by excessive travel or work, and not under the influence of drugs or alcohol.
Sentinel Scheme Rules
Report anything that may affect your ability to work safely, including medication, lack of equipment or personal circumstances.
Sentinel Scheme Rules
Do not work or report for duty after working within the preceding 12 hours unless the Primary Sponsor has approved a risk assessment and suitable controls are implemented.
Sentinel Scheme Rules
Do not exceed the shortest applicable working-hours limit set by law, the infrastructure manager or your sponsor.
Sentinel Scheme Rules
Report incidents, close calls and breaches of the Sentinel Scheme Rules.
Sentinel Scheme Rules
The Primary Sponsor must establish a Contract of Sponsorship and provide each sponsored individual with a valid physical or virtual Sentinel card.
Sentinel Scheme Rules
The Primary Sponsor must provide advice, guidance or instruction on restrictions arising from medication or other medical fitness issues, which appear when checking the Sentinel profile.
Sentinel Scheme Rules
The sponsor must provide equipment for reading or verifying Sentinel cards to workers whose role requires them to check others' competences.
Sentinel Scheme Rules
Sample questions
1. A lineside warning system is operated by a lookout to warn your group about approaching trains. What is it called?
- A proceed-on-sight authority (PoSA)
- A lookout operated warning system (LOWS)
- An intermediate block home signal
- A block marker
Answer: B. A lookout operated warning system (LOWS)
LOWS is a lineside warning system operated by a lookout. It warns personnel on or near the line about approaching trains.
- A proceed-on-sight authority (PoSA): PoSA is a signal used for movements into a section affected by a signalling equipment failure.
- An intermediate block home signal: An intermediate block home signal controls the exit from an intermediate block section.
- A block marker: A block marker indicates a signalling section within ERTMS.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms
2. You are COSS at a location listed in the Sectional Appendix. What does TOWS do when switched on?
- Stops an approaching train before it reaches the group
- Warns the signaller when the group enters the line
- Warns people on or near the line audibly when a train approaches
- Shows the group a visual indication that the line is blocked
Answer: C. Warns people on or near the line audibly when a train approaches
TOWS is an audible warning system that warns personnel on or near the line about an approaching train. It gives a warning rather than stopping the train.
- Stops an approaching train before it reaches the group: TOWS gives an audible warning; it does not stop the train.
- Warns the signaller when the group enters the line: TOWS warns personnel about approaching trains, not the signaller about the group.
- Shows the group a visual indication that the line is blocked: TOWS provides an audible train warning, not a visual line-blockage indication.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms
3. A rule refers to track circuits but does not specifically exclude axle counters. How should you interpret the reference?
- It applies only where the rails form an electrical circuit.
- It includes axle counters only if the signaller confirms this.
- It applies only to equipment that detects a train's presence.
- It also includes detection by axle counters.
Answer: D. It also includes detection by axle counters.
A reference to track circuits also includes detection by axle counters unless they are specifically excluded. Check the wording of the rule before assuming axle counters are outside it.
- It applies only where the rails form an electrical circuit: The reference can also include axle-counter detection.
- It includes axle counters only if the signaller confirms this: The glossary does not make inclusion dependent on signaller confirmation.
- It applies only to equipment that detects a train's presence: The glossary includes axle-counter detection unless specifically excluded.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms
4. During your briefing, a colleague asks what a track circuit is used to detect. What should you say?
- Whether points are mechanically operated
- Whether a signal is operated from a signal box
- Whether a train or vehicle is on a line
- Whether a train has passed through trailing points
Answer: C. Whether a train or vehicle is on a line
A track circuit is a method of detecting the presence of a train or vehicle on a line. It uses the rails as part of an electrical circuit.
- Whether points are mechanically operated: Point operation describes how points are worked, not what a track circuit detects.
- Whether a signal is operated from a signal box: A track circuit does not detect where a signal is operated from.
- Whether a train has passed through trailing points: A train passing through trailing points is not the definition of track-circuit detection.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms
5. During a site briefing, you refer to the overlap beyond a stop signal. What does this term mean?
- The line between two section signals worked by the same signal box
- The distance beyond a stop signal that must be clear before the previous signal can show a proceed aspect
- The line between the home and section signals worked by the same signal box
- The location from which a route can be set or closed
Answer: B. The distance beyond a stop signal that must be clear before the previous signal can show a proceed aspect
The overlap is the distance beyond a stop signal that must be clear before the previous signal can show a proceed aspect. Understanding the term helps you follow signalling arrangements discussed during planning.
- The line between two section signals worked by the same signal box: This is not the definition of an overlap.
- The line between the home and section signals worked by the same signal box: This describes station limits, subject to the stated signalling conditions.
- The location from which a route can be set or closed: This describes a route setting position.
Source: GERT8000-GLOSSARY Glossary of railway terminology, Glossary terms