COSS Planning and the safe work pack: mock test and revision questions
The Person in Charge, RT9909 and NR3180, site familiarity and hazards, and not starting without a safe system.
Updated 11 November 2026 for the rules in force now. The 5 December 2026 handbook changes are listed below.
Key rules
See all 13 key rulesThe Responsible Manager or team leader decides whether a COSS is suitable to act as Person in Charge; COSS competence alone does not make that person the PIC.
Network Rail NR/L2/OHS/019 Issue 12 FAQs
One person cannot carry out all three roles of Planner, Person in Charge and Responsible Manager, and the PIC and RM cannot be the same person.
Network Rail NR/L2/OHS/019 Issue 12 FAQs
The Person in Charge must be involved with the Planner in planning and verifying the safe work pack at least a shift in advance.
Network Rail NR/L2/OHS/019 Issue 12 FAQs
The Person in Charge is named in the safe work pack and must be on site to supervise and oversee the work.
Network Rail NR/L2/OHS/019 Issue 12 FAQs
A cyclic or repeatable safe work pack may cover more than one shift if it has been planned to do so.
Network Rail NR/L2/OHS/019 Issue 12 FAQs
The safe work pack includes a partly completed RT9909 and, where required, a partly completed NR3180 line blockage form.
Network Rail keypoint card: COSS, IWA, PC
The planning forms give details of any line blockage, isolation or speed restriction arranged for the work.
Network Rail keypoint card: COSS, IWA, PC
The COSS must be familiar with the site, using relevant documents or a recorded site visit.
Network Rail keypoint card: COSS, IWA, PC
Site familiarisation documents can include extracts from the National Hazard Directory and Sectional Appendix, current photographs and signalling diagrams.
Network Rail keypoint card: COSS, IWA, PC
Know the approved access points, track layout, train speeds and directions, electrification and any open-line prohibition areas.
Network Rail keypoint card: COSS, IWA, PC
Know the most suitable means of communication with the signaller and emergency services.
Network Rail keypoint card: COSS, IWA, PC
Consider site hazards including limited sighting, restricted clearances, poor underfoot conditions, electrical equipment and noise.
Network Rail keypoint card: COSS, IWA, PC
Sample questions
1. You are planning a fenced site of work using netting. Trains on the nearest open line travel at 60 mph. What is the minimum distance between the netting and that line?
- 1 metre
- 1.25 metres
- 2 metres
- 2.5 metres
Answer: C. 2 metres
At speeds from 41 to 125 mph, netting or tape must be at least 2 metres from the open line. The required distance depends on the barrier type and train speed.
- 1 metre: 1 metre is less than the specified minimum.
- 1.25 metres: 1.25 metres is the minimum for netting at speeds up to 40 mph.
- 2.5 metres: 2.5 metres is greater than the specified minimum.
Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12
2. You are setting up temporary fencing along a work site. The group needs to cross the line at one point. How should the fencing be arranged?
- Leave a gap wherever workers need access
- Fence only the sections closest to the line
- Keep it continuous, except for a proper crossing break
- End the fencing on each side of the crossing area
Answer: C. Keep it continuous, except for a proper crossing break
Temporary fencing must run continuously along the site, except where a proper break allows people to cross the line. This maintains an effective barrier while providing a crossing point.
- Leave a gap wherever workers need access: An informal gap does not provide the required proper break.
- Fence only the sections closest to the line: Fencing must extend along the whole site, not just selected sections.
- End the fencing on each side of the crossing area: Ending the fencing on both sides does not establish a proper break.
Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12
3. Your plan uses fencing to separate the group from an open line. What must you also plan for the fencing installation?
- A separate possession for storing the fencing
- A site warden to inspect the fencing after every train
- A second COSS solely to issue the fencing materials
- A safe system of work for setting up the fencing
Answer: D. A safe system of work for setting up the fencing
A safe system of work is needed to set up the fencing. The fencing cannot provide separation until it has been installed.
- A separate possession for storing the fencing: A possession is not required for storing fencing.
- A site warden to inspect the fencing after every train: A site warden is not required to inspect it after every train.
- A second COSS solely to issue the fencing materials: A second COSS is not required to issue materials.
Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12
4. You are planning a separated site of work for a group of four. What is the minimum space needed between the site and the nearest open line if no Site Warden is provided?
- 1.25 metres
- 2 metres
- 3 metres
- 4 metres
Answer: C. 3 metres
A space of at least 3 metres allows a group of any size to work without a Site Warden. At 2 metres, a group of more than two needs a Site Warden.
- 1.25 metres: 1.25 metres is less than the required space.
- 2 metres: At 2 metres, this group needs a Site Warden.
- 4 metres: 4 metres exceeds the minimum required.
Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12
5. You are preparing for tomorrow’s work. When should you ideally verify the safe system of work plan?
- After arriving at site, once work has started
- During the previous shift, before implementation
- After the group has completed the work
- During the next shift, after implementation
Answer: B. During the previous shift, before implementation
Verify the safe system of work plan before implementing it, ideally during the previous shift. This gives you an opportunity to identify issues before the work begins.
- After arriving at site, once work has started: Verification should take place before implementation, not after work starts.
- After the group has completed the work: Verification needs to take place before implementation, not after completion.
- During the next shift, after implementation: The plan must be verified before it is implemented.
Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12