Exams · UK

COSS Planning and the safe work pack: mock test and revision questions

The Person in Charge, RT9909 and NR3180, site familiarity and hazards, and not starting without a safe system.

27 questions · 13 key rules

Updated 11 November 2026 for the rules in force now. The 5 December 2026 handbook changes are listed below.

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Safe work pack1. You are planning a fenced site of work using netting. Trains on the nearest open line travel at 60 mph. What is the minimum distance between the netting and that line?
    1. 1 metre
    2. 1.25 metres
    3. 2 metres
    4. 2.5 metres
    Show answer and explanation

    Answer: C. 2 metres

    At speeds from 41 to 125 mph, netting or tape must be at least 2 metres from the open line. The required distance depends on the barrier type and train speed.

    Why the others are wrong

    • 1 metre: 1 metre is less than the specified minimum.
    • 1.25 metres: 1.25 metres is the minimum for netting at speeds up to 40 mph.
    • 2.5 metres: 2.5 metres is greater than the specified minimum.

    Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12

  2. Safe work pack2. You are setting up temporary fencing along a work site. The group needs to cross the line at one point. How should the fencing be arranged?
    1. Leave a gap wherever workers need access
    2. Fence only the sections closest to the line
    3. Keep it continuous, except for a proper crossing break
    4. End the fencing on each side of the crossing area
    Show answer and explanation

    Answer: C. Keep it continuous, except for a proper crossing break

    Temporary fencing must run continuously along the site, except where a proper break allows people to cross the line. This maintains an effective barrier while providing a crossing point.

    Why the others are wrong

    • Leave a gap wherever workers need access: An informal gap does not provide the required proper break.
    • Fence only the sections closest to the line: Fencing must extend along the whole site, not just selected sections.
    • End the fencing on each side of the crossing area: Ending the fencing on both sides does not establish a proper break.

    Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12

  3. Safe work pack3. Your plan uses fencing to separate the group from an open line. What must you also plan for the fencing installation?
    1. A separate possession for storing the fencing
    2. A site warden to inspect the fencing after every train
    3. A second COSS solely to issue the fencing materials
    4. A safe system of work for setting up the fencing
    Show answer and explanation

    Answer: D. A safe system of work for setting up the fencing

    A safe system of work is needed to set up the fencing. The fencing cannot provide separation until it has been installed.

    Why the others are wrong

    • A separate possession for storing the fencing: A possession is not required for storing fencing.
    • A site warden to inspect the fencing after every train: A site warden is not required to inspect it after every train.
    • A second COSS solely to issue the fencing materials: A second COSS is not required to issue materials.

    Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12

  4. Safe work pack4. You are planning a separated site of work for a group of four. What is the minimum space needed between the site and the nearest open line if no Site Warden is provided?
    1. 1.25 metres
    2. 2 metres
    3. 3 metres
    4. 4 metres
    Show answer and explanation

    Answer: C. 3 metres

    A space of at least 3 metres allows a group of any size to work without a Site Warden. At 2 metres, a group of more than two needs a Site Warden.

    Why the others are wrong

    • 1.25 metres: 1.25 metres is less than the required space.
    • 2 metres: At 2 metres, this group needs a Site Warden.
    • 4 metres: 4 metres exceeds the minimum required.

    Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12

  5. Safe work pack5. You are preparing for tomorrow’s work. When should you ideally verify the safe system of work plan?
    1. After arriving at site, once work has started
    2. During the previous shift, before implementation
    3. After the group has completed the work
    4. During the next shift, after implementation
    Show answer and explanation

    Answer: B. During the previous shift, before implementation

    Verify the safe system of work plan before implementing it, ideally during the previous shift. This gives you an opportunity to identify issues before the work begins.

    Why the others are wrong

    • After arriving at site, once work has started: Verification should take place before implementation, not after work starts.
    • After the group has completed the work: Verification needs to take place before implementation, not after completion.
    • During the next shift, after implementation: The plan must be verified before it is implemented.

    Source: Network Rail keypoint card: COSS, IWA, PC (Issue 12

Sign up free

Other COSS topics

GoConqr Original. Practice questions written with AI from the Rule Book handbooks and Network Rail guidance a COSS works to, each checked against the source it cites. Think a question is wrong? Use 'Report' under it.

Independent revision resource. Not affiliated with Network Rail, RSSB or any training provider.

© Visual Maths Resources Ltd

Feedback

What is it about?