9. Risk Management (Rita's)

Tuan Lam PMP Exam Prep Certificate English 22 cards

Cards in this deck (22)

  1. 1When do risk identification and risk response happen?Any time during a project
  2. 2What are "Risk Categories"aka: sources of risk
    categories can be broad and common to similar projects/industry
  3. 3Who should be involved in risk identification?EVERYONE!!!
  4. 4What is the most important output of various risk management processes?Updated Risk Register
  5. 5Is the content of Risk Register different from time to time?YES. Example: when project starts, there can be: identified risks and potential responses but no response plans yet.
  6. 6When are responses documented?During both Identify Risks and Plan Risk Responses
  7. 7What can the Qualitative risk analysis be used for?Compare the risk of the project to others
    Determine whether to continue or terminate
    Determine whether to proceed to Quantitative analysis
  8. 8Qualitative vs Quantitative?Subjective vs Objective
    Rating vs Measurement (impact + probability)
  9. 9What does Monte Carlo analysis achieve?Evaluate the overall risk of the project
    Determines the probability of completion on any specific date
  10. 10Decision tree?Models all possible options to deal with an issue. Costs can appear anywhere on the tree
  11. 11When suggested changes happen?Plan Risk Response - if project work has not been started
    Control Risk - otherwise
  12. 12Can risk identification be done without knowing enough about the project?NO
  13. 13Can padding be a replacement for risk management processes?NO
  14. 14Can identified risks be general?NO
  15. 15Can a costly fact be a risk?NO. Risk is about uncertainty
  16. 16Is using one method to identify risks enough?NO
  17. 17What is the best thing to do to determine a response strategy?Consider all options and find the best combination before making the decision
  18. 18Should contracts be signed before risks are discussed?NO
  19. 19Risk event's probability: 90% and the cost is $10,000. What does $9,000 represent?Expected monetary value (EMV)
  20. 20A project: 60% of $100,000 profit and 40% of $100,000 loss. What does $20,000 represent?Expected monetary value (EMV)
  21. 21If you know the risk tolerances, what do you use the info for?Rank the project risks
    (Assign levels of risk on each work package or activity.)
  22. 22—

Information

Description
Certificate PMP Exam Prep (Tips & Tricks) Flashcards on 9. Risk Management (Rita's), created by Tuan Lam on 21/12/2015.
Created by
Tuan Lam
Views
20
Rating

Feedback

What is it about?

What do you think of the new look?

How do you like it?