Time Management Processes

Jessica Kalvaitis Project Management PMP English 7 slides

Slides in this set (7)

  1. PLAN SCHEDULE MANAGEMENT

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Project Management Plan 1. Expert Judgment 1. Schedule Mgmt Plan
    • 2. Project Charter 2. Analytical Techniques
    • 3. EEF 3. Meetings
    • 4. OPAS
  2. DEFINE ACTIVITIES

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Schedule Management Plan 1. Decomposition 1. Activity List
    • 2. Scope Baseline 2. Rolling Wave Planning 2. Activity Attributes
    • 3. EEF 3. Expert Judgment 3. Milestone List
    • 4. OPAS
  3. SEQUENCE ACTIVITIES

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Schedule Management Plan 1. Procedure Diagramming 1. Project Schedule Network Diagram
    • 2. Activity List 2. Dependency Determination 2. Project Document Updates
    • 3. Activity Attributes 3. Leads & Lags
    • 4. Milestone List
    • 5. Project Scope Statement
    • 6. EEF
    • 7. OPAS
  4. ESTIMATE ACTIVITY RESOURCES

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Schedule Management Plan 1. Expert Judgment 1. Activity Resource Requirements
    • 2. Activity List 2. Alternative Analysis 2. Resource Breakdown Structure (RBS)
    • 3. Activity Attributes 3. Published Estimating Data 3. Project Document Updates
    • 4. Resource Calendars 4. Bottom Up Estimating
    • 5. Risk Register 5. Project Mgmt Software
    • 6. Activity Cost Estimates
    • 7. EEF
    • 8. OPAS
  5. ESTIMATE ACTIVITY DURATIONS

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Schedule Management Plan 1. Expert Judgment 1. Activity Duration Estimates
    • 2. Activity List 2. Analogous Estimating 2. Project Document Updates
    • 3. Activity Attributes 3. Parametric
    • 4. Activity Resource Requirements 4. Three Point
    • 5. Resource Calendar 5. Group Decision Making
    • 6. Project Scope Statement 6. Reserve Analysis
    • 7. Risk Register
    • 8. Resource Breakdown Structure (RBS)
    • 9. EEF
    • 10. OPAS
  6. DEVELOP SCHEDULE

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Schedule Management Plan 1. Schedule Network Analysis 1. Schedule Baseline
    • 2. Activity List 2. Critical Path Method 2. Project Schedule
    • 3. Activity Attributes 3. Critical Chain Method 3. Schedule Data
    • 4. Project Schedule Network Diagram 4. Resource Optimization 4. Project Calendars
    • 5. Activity Resource Requirements 5. Modeling Techniques 5. Project Mgmt Plan Updates
    • 6. Resource Calendar 6. Leads & Lags 6. Project Document Updates
    • 7. Activity Duration Estimates 7. Schedule Compression
    • 8. Project Scope Statement 8. Scheduling Tool
    • 9. Risk Register
    • 10. Project Staff Assignments
    • 11. Resource Breakdown Structure (RBS) 12. EEF 13. OPAS
  7. CONTROL SCHEDULE

    • INPUTS TOOLS & TECH OUTPUTS
    • 1. Project Management Plan 1. Performance Reviews 1. Work Performance Info
    • 2. Project Schedule 2. Project Mgmt Software 2. Schedule Forecasts
    • 3. Work Performance Data 3. Resource Optimization 3. Change Requests
    • 4. Project Calendars 4. Modeling Techniques 4. Project Mgmt Plan Updates
    • 5. Schedule Data 5. Leads & Lags 5. Project Document Updates
    • 6. OPAS 6. Schedule Compression 6. OPAS
    • 7. Scheduling Tool

Information

Description
PMP Project Management (Processes) Slide Set on Time Management Processes, created by Jessica Kalvaitis on 28/07/2016.