ES practice questions: Briefing the COSS and IWA and the safe system of work
Work-site briefings, the RT3199 certificate, limits of the site of work and the safe systems of work.
Updated 17 November 2026 for the rules in force now and the 5 December change
Key rules
See all 21 key rulesThe ES authorises each COSS or IWA to set up a safe system of work within the work site.
GERT8000-HB9 IWA or COSS setting up safe systems of work within possessions, Definitions / 2 / 3.1
Before work starts, the ES and each COSS or IWA must agree the limits of that person's site of work.
HB9:3.1
Before work starts, the ES and each COSS or IWA must agree the nature of the work and the safe system of work to be used.
HB9:3.1
Each COSS or IWA must receive a work-site briefing from the ES and then sign the work-site certificate RT3199.
HB9:3.1
The ES may brief, agree arrangements and obtain signatures before the work site is granted only if this has been planned and published in advance and both parties are aware.
GERT8000-HB12 Duties of the ES in a possession, Agreeing the arrangements before the / 4.3
After a pre-grant briefing, the ES must not allow work to start until each COSS or IWA has been told that the work site has been granted.
GERT8000-HB12 Duties of the ES in a possession, Agreeing the arrangements before the / 4.3
After a pre-grant briefing, the ES must give each COSS or IWA an authority number and record it on RT3199.
GERT8000-HB12 Duties of the ES in a possession, Agreeing the arrangements before the / 4.3
A COSS or IWA briefed before the work site is granted must record the authority number given by the ES.
GERT8000-HB9 IWA or COSS setting up safe systems of work within possessions, Agreeing the arrangements before the
For a safeguarded, fenced or separated safe system, the COSS or IWA must agree with the ES that there will be no train or OTP movements at the site of work, or movements will not exceed 5 mph (10 km/h).
GERT8000-HB12 Duties of the ES in a possession, Agreeing the arrangements before the / 4.3
For a safeguarded safe system, the COSS or IWA must also ensure any line at the site of work outside the work site is blocked under the relevant handbook arrangements.
GERT8000-HB9 IWA or COSS setting up safe systems of work within possessions, Safe system of work where all lines are
A safe system of work within a possession but outside a work site cannot be treated as safeguarded.
GERT8000-HB9 IWA or COSS setting up safe systems of work within possessions, Protection arrangements
For a fenced safe system, a safety barrier meeting handbook 6 or 7 requirements must stand between the site of work and any open line.
GERT8000-HB12 Duties of the ES in a possession, Safe system of work using a safety / 4.5 / 4.6
Sample questions
1. Under the rules in force until 4 December 2026, you want to brief a COSS and obtain their RT3199 signature before the work site is granted. When is this permitted?
- When the PICOP has provisionally agreed the possession limits
- When the COSS has completed the group briefing and confirmed everyone is ready
- When the work site marker boards have been placed and the COSS has seen them
- When the arrangement was planned and published in advance and both you and the COSS know what will happen
Answer: D. When the arrangement was planned and published in advance and both you and the COSS know what will happen
An advance briefing and signature are permitted only when the arrangement has been planned and published in advance and both the ES and COSS know what will happen. This allows the parties to prepare before the work site is granted.
- When the PICOP has provisionally agreed the possession limits: Provisional agreement of the possession limits is not the condition for this arrangement.
- When the COSS has completed the group briefing and confirmed everyone is ready: Completing the group briefing does not replace the advance planning and publication requirement.
- When the work site marker boards have been placed and the COSS has seen them: Seeing the marker boards does not replace the advance planning and publication requirement.
Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3
2. Under the rules in force until 4 December 2026, you have briefed an IWA and obtained their signature before the work site is granted. What must you do before allowing them to start work?
- Ask them to repeat the work-site briefing to you
- Give them a copy of the signed RT3199
- Tell them that the work site has been granted
- Ask them to confirm the planned work is unchanged
Answer: C. Tell them that the work site has been granted
The ES must tell each IWA or COSS that the work site has been granted before allowing work to start. An advance briefing and signature do not themselves permit work to begin.
- Ask them to repeat the work-site briefing to you: Repeating the briefing does not replace confirmation that the work site is granted.
- Give them a copy of the signed RT3199: Providing a copy of the certificate does not replace confirmation that the work site is granted.
- Ask them to confirm the planned work is unchanged: Confirming the planned work does not replace confirmation that the work site is granted.
Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3
3. Under the rules in force until 4 December 2026, you have told a COSS, briefed in advance, that the work site has been granted. What must you then do with the authority number?
- Give it to the COSS and record it on the RT3199
- Give it to the PICOP and record it on the RT3199
- Give it to the COSS and record it on the RT3198
- Give it to the PICOP and record it on the RT3198
Answer: A. Give it to the COSS and record it on the RT3199
The ES must give each COSS or IWA an authority number and record it on the RT3199 certificate. This follows telling them that the work site has been granted.
- Give it to the PICOP and record it on the RT3199: The number must be given to the COSS, not just the PICOP.
- Give it to the COSS and record it on the RT3198: The number must be recorded on the RT3199.
- Give it to the PICOP and record it on the RT3198: The number must be given to the COSS and recorded on the RT3199.
Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3
4. All lines are blocked, but an engineering train must move at a COSS's site of work. What must the COSS agree with you before treating the safe system as safeguarded?
- The train will move at no more than 10 mph
- The train will stop before reaching the site of work
- The train will move at no more than 5 mph
- The train will enter only after the group has signed the RT3199
Answer: C. The train will move at no more than 5 mph
Where engineering train or OTP movements occur at the site of work, the IWA or COSS must agree with the ES that they will be made at no more than 5 mph (10 km/h). This agreement is needed before the safe system can be treated as safeguarded.
- The train will move at no more than 10 mph: The permitted maximum is 5 mph, not 10 mph.
- The train will stop before reaching the site of work: Stopping before reaching the site is not the specified agreement for a movement at the site.
- The train will enter only after the group has signed the RT3199: A signature alone does not establish the required movement-speed agreement.
Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3
5. A COSS wants to use a fenced safe system of work next to an open line. What must be between their site of work and that line?
- A site warden positioned at the open line
- Equipment warning for trains on the open line
- A safety barrier as shown in handbook 6 or 7
- A work site marker board beside the open line
Answer: C. A safety barrier as shown in handbook 6 or 7
A fenced safe system requires a safety barrier between the site of work and any open line. The barrier must be as shown in handbook 6 or 7.
- A site warden positioned at the open line: A site warden does not provide the required safety barrier.
- Equipment warning for trains on the open line: Equipment warning is not the barrier required for a fenced system.
- A work site marker board beside the open line: A work site marker board is not the required safety barrier.
Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Safe system of work using a safety / 4.5 / 4.6