Exams · UK

ES practice questions: Briefing the COSS and IWA and the safe system of work

Work-site briefings, the RT3199 certificate, limits of the site of work and the safe systems of work.

35 questions · 21 key rules

Updated 17 November 2026 for the rules in force now and the 5 December change

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Briefing, safe systems1. Under the rules in force until 4 December 2026, you want to brief a COSS and obtain their RT3199 signature before the work site is granted. When is this permitted?
    1. When the PICOP has provisionally agreed the possession limits
    2. When the COSS has completed the group briefing and confirmed everyone is ready
    3. When the work site marker boards have been placed and the COSS has seen them
    4. When the arrangement was planned and published in advance and both you and the COSS know what will happen
    Show answer and explanation

    Answer: D. When the arrangement was planned and published in advance and both you and the COSS know what will happen

    An advance briefing and signature are permitted only when the arrangement has been planned and published in advance and both the ES and COSS know what will happen. This allows the parties to prepare before the work site is granted.

    Why the others are wrong

    • When the PICOP has provisionally agreed the possession limits: Provisional agreement of the possession limits is not the condition for this arrangement.
    • When the COSS has completed the group briefing and confirmed everyone is ready: Completing the group briefing does not replace the advance planning and publication requirement.
    • When the work site marker boards have been placed and the COSS has seen them: Seeing the marker boards does not replace the advance planning and publication requirement.

    Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3

  2. Briefing, safe systems2. Under the rules in force until 4 December 2026, you have briefed an IWA and obtained their signature before the work site is granted. What must you do before allowing them to start work?
    1. Ask them to repeat the work-site briefing to you
    2. Give them a copy of the signed RT3199
    3. Tell them that the work site has been granted
    4. Ask them to confirm the planned work is unchanged
    Show answer and explanation

    Answer: C. Tell them that the work site has been granted

    The ES must tell each IWA or COSS that the work site has been granted before allowing work to start. An advance briefing and signature do not themselves permit work to begin.

    Why the others are wrong

    • Ask them to repeat the work-site briefing to you: Repeating the briefing does not replace confirmation that the work site is granted.
    • Give them a copy of the signed RT3199: Providing a copy of the certificate does not replace confirmation that the work site is granted.
    • Ask them to confirm the planned work is unchanged: Confirming the planned work does not replace confirmation that the work site is granted.

    Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3

  3. Briefing, safe systems3. Under the rules in force until 4 December 2026, you have told a COSS, briefed in advance, that the work site has been granted. What must you then do with the authority number?
    1. Give it to the COSS and record it on the RT3199
    2. Give it to the PICOP and record it on the RT3199
    3. Give it to the COSS and record it on the RT3198
    4. Give it to the PICOP and record it on the RT3198
    Show answer and explanation

    Answer: A. Give it to the COSS and record it on the RT3199

    The ES must give each COSS or IWA an authority number and record it on the RT3199 certificate. This follows telling them that the work site has been granted.

    Why the others are wrong

    • Give it to the PICOP and record it on the RT3199: The number must be given to the COSS, not just the PICOP.
    • Give it to the COSS and record it on the RT3198: The number must be recorded on the RT3199.
    • Give it to the PICOP and record it on the RT3198: The number must be given to the COSS and recorded on the RT3199.

    Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3

  4. Briefing, safe systems4. All lines are blocked, but an engineering train must move at a COSS's site of work. What must the COSS agree with you before treating the safe system as safeguarded?
    1. The train will move at no more than 10 mph
    2. The train will stop before reaching the site of work
    3. The train will move at no more than 5 mph
    4. The train will enter only after the group has signed the RT3199
    Show answer and explanation

    Answer: C. The train will move at no more than 5 mph

    Where engineering train or OTP movements occur at the site of work, the IWA or COSS must agree with the ES that they will be made at no more than 5 mph (10 km/h). This agreement is needed before the safe system can be treated as safeguarded.

    Why the others are wrong

    • The train will move at no more than 10 mph: The permitted maximum is 5 mph, not 10 mph.
    • The train will stop before reaching the site of work: Stopping before reaching the site is not the specified agreement for a movement at the site.
    • The train will enter only after the group has signed the RT3199: A signature alone does not establish the required movement-speed agreement.

    Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Agreeing the arrangements before the / 4.3

  5. Briefing, safe systems5. A COSS wants to use a fenced safe system of work next to an open line. What must be between their site of work and that line?
    1. A site warden positioned at the open line
    2. Equipment warning for trains on the open line
    3. A safety barrier as shown in handbook 6 or 7
    4. A work site marker board beside the open line
    Show answer and explanation

    Answer: C. A safety barrier as shown in handbook 6 or 7

    A fenced safe system requires a safety barrier between the site of work and any open line. The barrier must be as shown in handbook 6 or 7.

    Why the others are wrong

    • A site warden positioned at the open line: A site warden does not provide the required safety barrier.
    • Equipment warning for trains on the open line: Equipment warning is not the barrier required for a fenced system.
    • A work site marker board beside the open line: A work site marker board is not the required safety barrier.

    Source: GERT8000-HB12 Duties of the ES in a possession (Iss 11, Safe system of work using a safety / 4.5 / 4.6

Sign up free

Other ES topics

GoConqr Original. Practice questions written with AI from the Rule Book handbooks and Network Rail documents the ES course names, each checked by a separate AI review. Think a question is wrong? Use "Report" under it.

Independent revision resource. Not affiliated with Network Rail, RSSB or any training provider.