  1. Working with the PICOP1. You are discussing movements with the PICOP. Which vehicle is included in the definition of an engineering train?
    1. An on-track machine
    2. A road-rail vehicle in rail mode
    3. A rail-mounted maintenance machine
    4. An OTP trailer with guidance wheels
    Show answer and explanation

    Answer: A. An on-track machine

    An engineering train includes on-track machines, but not on-track plant. This distinction matters when discussing the type of movement.

    Why the others are wrong

    • A road-rail vehicle in rail mode: A road-rail vehicle is on-track plant, not an engineering train.
    • A rail-mounted maintenance machine: A rail-mounted maintenance machine is on-track plant, not an engineering train.
    • An OTP trailer with guidance wheels: OTP trailers with guidance wheels are included in on-track plant.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Definitions / 2

  2. Working with the PICOP2. An MC is also competent as a crane controller. What identification should they wear?
    1. A crane controller armlet or badge with black letters on white
    2. An MC armlet or badge with black letters on white
    3. A CC armlet or badge with red letters on yellow
    4. A PICOS armlet or badge with black letters on white
    Show answer and explanation

    Answer: A. A crane controller armlet or badge with black letters on white

    An MC who is also competent as a crane controller wears crane controller or CC identification instead. The lettering is black on a white background.

    Why the others are wrong

    • An MC armlet or badge with black letters on white: This is the identification for an MC who is not also competent as a crane controller.
    • A CC armlet or badge with red letters on yellow: The crane controller identification has black letters on white.
    • A PICOS armlet or badge with black letters on white: The identification specified is for a crane controller, not a PICOS.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Definitions / 2

  3. Working with the PICOP3. You need to identify the person responsible for taking and supervising a siding possession. Who is that?
    1. The PICOP
    2. The machine controller
    3. The engineering supervisor
    4. The PICOS
    Show answer and explanation

    Answer: D. The PICOS

    The PICOS is responsible for taking and supervising a possession of a siding. Identify the correct person when discussing siding possession arrangements.

    Why the others are wrong

    • The PICOP: The PICOP is not the role defined here as responsible for a siding possession.
    • The machine controller: The machine controller is responsible for the safe operation of OTP.
    • The engineering supervisor: The engineering supervisor manages a work site, not the siding possession as PICOS.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Definitions / 2

  4. Working with the PICOP4. A colleague is about to act as PICOP. What must they have with them?
    1. A valid COSS certificate issued by their employer
    2. A valid PICOP certificate issued by the signaller
    3. A valid ES certificate issued by the PICOP
    4. A valid PICOP certificate issued by their employer
    Show answer and explanation

    Answer: D. A valid PICOP certificate issued by their employer

    A person acting as PICOP must have a valid PICOP certificate of competence issued by their employer with them. This is a requirement for carrying out the role.

    Why the others are wrong

    • A valid COSS certificate issued by their employer: A COSS certificate does not meet the stated PICOP requirement.
    • A valid PICOP certificate issued by the signaller: The PICOP certificate must be issued by the person's employer.
    • A valid ES certificate issued by the PICOP: An ES certificate does not meet the stated PICOP requirement.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Definitions / 2

  5. Working with the PICOP5. You have told the PICOP that work at your work site is complete. The PICOP has already permitted a movement towards the work site. What must happen about removing the WSMBs?
    1. The PICOP may permit their removal once you confirm the work is complete.
    2. You may remove them after telling the driver that work is complete.
    3. You may remove them once the COSS has signed out of the work site.
    4. The PICOP must not permit their removal while that movement has been permitted.
    Show answer and explanation

    Answer: D. The PICOP must not permit their removal while that movement has been permitted.

    The PICOP must not permit WSMB removal if they have permitted a movement towards the work site. The assurance that work is complete does not override that restriction.

    Why the others are wrong

    • The PICOP may permit their removal once you confirm the work is complete: Work completion alone does not allow the PICOP to permit removal in this situation.
    • You may remove them after telling the driver that work is complete: Telling the driver does not replace the PICOP’s permission or the movement restriction.
    • You may remove them once the COSS has signed out of the work site: A COSS signing out does not override the restriction on WSMB removal.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Making sure the work is complete

Sign up free

Other ES topics

GoConqr Original. Practice questions written with AI from the Rule Book handbooks and Network Rail documents the ES course names, each checked by a separate AI review. Think a question is wrong? Use "Report" under it.

Independent revision resource. Not affiliated with Network Rail, RSSB or any training provider.

© Visual Maths Resources Ltd

Feedback

What is it about?