Exams · UK

ES Questions: Train Movements in the Work Site

Movements into, within and out of the work site, and work on a rail vehicle.

45 questions · 25 key rules

Updated 17 November 2026 for the rules in force now and the 5 December change

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Train movements1. A movement within a possession but outside a work site is to be propelled. The details are published in the Engineering Notice. What else is needed for the planned movement?
    1. The details must be shown on the RT3199.
    2. The details must be published in both operating notices.
    3. The details must be shown in the method statement.
    4. The details must be shown on the RT3198.
    Show answer and explanation

    Answer: C. The details must be shown in the method statement.

    The details must also be shown in the method statement. Publication in the Engineering Notice alone does not meet both requirements for the planned movement.

    Why the others are wrong

    • The details must be shown on the RT3199: The passage requires the method statement, not an RT3199 entry.
    • The details must be published in both operating notices: Publication in either specified notice is sufficient, alongside the method statement.
    • The details must be shown on the RT3198: An RT3198 entry does not replace the method statement requirement.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Propelling

  2. Train movements2. A train is planned to leave a possession by propelling. Its details are in the method statement but have not been published. What must the PICOP obtain before allowing it?
    1. Authority from the ES.
    2. Authority from the driver.
    3. Authority from the COSS.
    4. Authority from Operations Control.
    Show answer and explanation

    Answer: D. Authority from Operations Control.

    If propelling is necessary and the details have not been published, the PICOP must obtain authority from Operations Control. The details being in the method statement do not remove that requirement.

    Why the others are wrong

    • Authority from the ES: The ES is not the specified source of authority for unpublished propelling.
    • Authority from the driver: The driver's agreement is not the specified authority.
    • Authority from the COSS: The COSS is not the specified source of authority for unpublished propelling.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Propelling

  3. Train movements3. Which proposed propelled movement is covered by the PICOP's notice and method statement requirements?
    1. A movement within the possession but outside a work site.
    2. A movement within a work site only.
    3. A movement within a siding outside the possession.
    4. A movement on an adjacent line outside the possession.
    Show answer and explanation

    Answer: A. A movement within the possession but outside a work site.

    A propelled movement within the possession but outside a work site is one of the specified movements. The PICOP must apply the notice and method statement requirements, or obtain authority from Operations Control where necessary details have not been published.

    Why the others are wrong

    • A movement within a work site only: A movement solely within a work site is not among the movements specified here.
    • A movement within a siding outside the possession: A siding outside the possession is not among the movements specified here.
    • A movement on an adjacent line outside the possession: An adjacent line outside the possession is not among the movements specified here.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, Propelling

  4. Train movements4. You are the PICOP. A rail vehicle is standing on a portion of line under your control and work is planned on it. Who will ask you to stop train movements towards the vehicle?
    1. The machine controller
    2. The designated person
    3. The driver of the vehicle
    4. The signaller on duty
    Show answer and explanation

    Answer: B. The designated person

    The designated person asks the PICOP to stop movements towards the vehicle in this situation. This allows the work to be protected from approaching trains.

    Why the others are wrong

    • The machine controller: The machine controller makes the request for work on an item of OTP.
    • The driver of the vehicle: The passage assigns the request to the designated person, not the driver.
    • The signaller on duty: The signaller is not the person assigned to make this request.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, If work is to be carried out on a rail

  5. Train movements5. You are the PICOP. Work is planned on a vehicle adjacent to a line that is not under possession. What must you ask the signaller to do?
    1. Arrange for trains to approach the vehicle at caution
    2. Block the line that is not under possession
    3. Place the adjacent line under your control
    4. Warn each driver about the vehicle before passing
    Show answer and explanation

    Answer: B. Block the line that is not under possession

    The PICOP must ask the signaller to block the line that is not under possession. This addresses movements on the line adjacent to the vehicle.

    Why the others are wrong

    • Arrange for trains to approach the vehicle at caution: A caution instruction is not the specified arrangement.
    • Place the adjacent line under your control: The requirement is to ask for a line blockage, not to take control of the line.
    • Warn each driver about the vehicle before passing: Warning drivers does not replace the required line blockage.

    Source: GERT8000-HB11 Duties of the person in charge of the possession (Iss 11, If work is to be carried out on a rail

Sign up free

Other ES topics

GoConqr Original. Practice questions written with AI from the Rule Book handbooks and Network Rail documents the ES course names, each checked by a separate AI review. Think a question is wrong? Use "Report" under it.

Independent revision resource. Not affiliated with Network Rail, RSSB or any training provider.

© Visual Maths Resources Ltd

Feedback

What is it about?